utilizing collaborative lean processes to effectively
play

Utilizing Collaborative & Lean Processes to Effectively Drive - PowerPoint PPT Presentation

Utilizing Collaborative & Lean Processes to Effectively Drive Intels Program 16 th LCI Congress | San Francisco, CA | October 7-10, 2014 Overview To effectively drive Lean in an Owners program, a comprehensive set of technology and


  1. Utilizing Collaborative & Lean Processes to Effectively Drive Intel’s Program 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  2. Overview To effectively drive Lean in an Owner’s program, a comprehensive set of technology and process tools as well as cultural approaches need to be carefully orchestrated to deliver value. Project: Cleanroom retrofit with adjacent manufacturing operations 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  3. Why are we here? 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  4. Why are we here? 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  5. Key Points • Implementing a lean Design-Build delivery requires early and continuous collaboration by all stakeholders to set a plan in place and work towards it. • To obtain buy-in amongst a complex network of Owner stakeholders, a communication plan is essential to actual and perceived success. Managing perceived success can come full circle to further enable actual success . • A single model , developed with early participation of Design and Trade Partners, creates efficiencies that have ripple effects throughout the project budget and schedule . 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  6. Work Plan Process Design Process & Schedule Target Cost / Estimate QA/QC Coordination & Facility Interface Trade Productivity Planning, Scheduling & Logistics Operations / Facility Interface BIM, Technology & Collaboration 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  7. (Winding) Road to Market Pricing How do you tackle 39 binders of requirements? 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  8. Risk in Pricing Targeted Scanning ONE MODEL Cost Certainty Fabrication Drawings Experienced Vs Team Bridging or Detail Design in Place Documents Modeling with Trade Partner Engagement One Model Approach Model-Based Take-offs A complete approach currently employed on the Project Spool Sheets Approved by Trade Partners as Ready for Fabrication Existing Condition Conversion to Revit 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  9. Pull Planning per Scope / Area 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  10. Weekly Work Planning – Percent Planned Complete (PPC) 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  11. Metrics / Success Indicators • Reduced Change Orders 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  12. Metrics / Success Indicators • Reduced Change Orders • 96% Successful Completion of 62 Milestones 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  13. Metrics / Success Indicators • Reduced Change Orders • 96% Successful Completion of 62 Milestones • 79% Avg 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  14. Metrics / Success Indicators • 2:1 reduction • Reduced Change Orders • 96% Successful Completion of 62 Milestones • 79% Avg 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  15. Metrics / Success Indicators • 2:1 reduction • Reduced Change Orders • Clash Detection / Avoidance  During Early Design = ~ 500 clashes • 96% Successful Completion of 62 Milestones  During Spool Generation = ~50 clashes  During Construction = 4 clashes encountered • 79% Avg 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  16. Metrics / Success Indicators • 2:1 reduction • Reduced Change Orders • Clash Detection / Avoidance  During Early Design = ~ 500 clashes • 96% Successful Completion of 62 Milestones  During Spool Generation = ~50 clashes  During Construction = 5 clashes encountered • 5 clashes = .04% of Contingency use • 79% Avg 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  17. § Translates higher level schedule Key Takeaway activities into very specific daily tasks for field coordination § Feeds back into P6 schedule Last Planner with Weekly Work Planning Construction Pre-Installation Enabling Planning Process Technology Efficient, Effective BIM: § Opportunity to develop § Common reference point alignment between Project Communication for which all design starts management team, Field § Foundation for design management team and collaboration Stakeholders Jobsite Kiosks: § Access to BIM § Access to hyperlinked 2D documents § Access to documentation systems 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  18. § Translates higher level schedule Key Takeaway activities into very specific daily tasks for field coordination § Feeds back into P6 schedule Last Planner with Weekly Work Planning Construction Pre-Installation Enabling Planning Process Technology Efficient, Effective BIM: § Opportunity to develop § Common reference point alignment between Project Communication for which all design starts management team, Field § Foundation for design management team and collaboration Stakeholders Jobsite Kiosks: § Access to BIM § Access to hyperlinked 2D documents § Access to documentation systems 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend