Transmission Network Investments Vincent Rious, Yannick Perez - - PowerPoint PPT Presentation

transmission network investments
SMART_READER_LITE
LIVE PREVIEW

Transmission Network Investments Vincent Rious, Yannick Perez - - PowerPoint PPT Presentation

Anticipation for Efficient Electricity Transmission Network Investments Vincent Rious, Yannick Perez Jean-Michel Glachant Philippe Dessante Conference Belrin 9 th October 2010 Outline 2 Motivation Problem Model Illustration


slide-1
SLIDE 1

Anticipation for Efficient Electricity Transmission Network Investments

Vincent Rious, Yannick Perez Jean-Michel Glachant Philippe Dessante

Conference Belrin 9th October 2010

slide-2
SLIDE 2

Outline

  • Motivation
  • Problem
  • Model
  • Illustration
  • Conclusion

2

slide-3
SLIDE 3

Coordinated gen° and trans° investments by an integrated utility

Integrated Utility  Easy to know when to build each investment considering the longest construction lead time

3

slide-4
SLIDE 4

Unbundling and coordination need

Liberalised power system >> Prompts investors to choose generation technologies with short construction lead time

Right of way of powerlines facing increasing oppositions  ~ 7 years to build a powerline from study to construction itself because of administrative agreement >> 5 years!

Generation technology Time to build (year) Notional size (MW) CCGT 2 800 Wind onshore 2 25

  • ffshore

2 100 Coal 4-5 150-1600 Nuclear 5-7 1600

Congestion while the network is not upgraded

4

slide-5
SLIDE 5

Two possible behaviors for the TSO

  • Reactive behavior

– Wait connection request to study opportunity for transmission investments

  • Proactive behavior

– Anticipate connection request in areas with exploitable energy sources

  • Gas
  • Wind

– Administrative procedures are already agreed when generators request for connection

5

slide-6
SLIDE 6

Advantages & drawbacks of the two possible behaviors

  • Reactive behavior

 Excessive congestion if CCGT or wind power involved while network is upgraded

  • Proactive behavior

– No excessive congestion – But proactive behavior is costly because, if generation does not come, the TSO did

  • the study to upgrade the network
  • And the procedures to obtain the administrative

agreement to build the line

6

slide-7
SLIDE 7

Outline

  • Motivation
  • Problem
  • Model
  • Illustration
  • Conclusion

7

slide-8
SLIDE 8

Problem

  • What is the efficiency of anticipating

generation connection for the TSO in terms

  • f minimization of the network cost?

– No anticipation creates congestion for quite long period while network must be upgraded – But anticipation is costly if the anticipated generators do not eventually come  We must arbitrate between these two costs

8

slide-9
SLIDE 9

Outline

  • Motivation
  • Problem
  • Model
  • Illustration
  • Conclusion

9

slide-10
SLIDE 10

Construction Generation Investment Year

CU(d) CW(d)

Transmission Investment

d

Study, admin. proced. construction

Sequence of investments with a reactive TSO

10

Excessive congestion Optimal value for network capacity

slide-11
SLIDE 11

Costs faced by a reactive TSO

Generator TSO invests Probability p does not invest Probability 1-p Expected social cost waits for connection

  • f power plant

before studying and upgrading CW(d) + CU(d) + I/(1+a)d 0 + 0

 

 

     

         

d TSO active

a I d CU d CW p p C E 1

re

Congestion cost without and after the network being upgraded Transmission investment cost No congestion & no network investment

11

slide-12
SLIDE 12

Construction Year Study,

  • admin. proced.

construction Generation and Network

Investments CU(0)

Sequence of investments with a proactive TSO

12

slide-13
SLIDE 13

Costs faced by a proactive TSO

Generator TSO invests Probability p does not invest Probability 1-p Expected social cost waits for connection

  • f power plant

before studying and upgrading I + CU(0) aI + 0

Congestion cost with upgrade as soon as the generator connects Transmission investment cost

 

 

      I

p CR I p p C E

TSO proactive

a     1

Anticipation cost = network study + admin proced. No congestion cost

13

slide-14
SLIDE 14

Condition for a proactive TSO to be efficient

  • When is proactive as efficient as reactive?

       

 

 

I CW d CU d CW a p

d

1 1

lim

       

a a

p < plim  reactive TSO > proactive TSO p > plim  proactive TSO > reactive TSO The anticipation strategy is all the more efficient that plim is small For a given a, plim as function of d

14

slide-15
SLIDE 15

Outline

  • Motivation
  • Problem
  • Model
  • Illustration
  • Conclusion

15

slide-16
SLIDE 16

“Probability limit” and condition for a proactive TSO

16

slide-17
SLIDE 17

Outline

  • Motivation
  • Problem
  • Model
  • Illustration
  • Conclusion

17

slide-18
SLIDE 18

Conclusion

  • A model to evaluate the efficiency of

anticipating of power plants to minimize the cost of the network

  • Illustration on a simple realistic example

with CCGT

– Efficient to anticipate the connection of power plants for the TSO – Planning in advance network reinforcement – Reduce congestion cost

18

slide-19
SLIDE 19

Future researches

  • Variation of the cost of anticipating
  • Duplicate this study for wind farm
  • Interaction with regulatory actions
  • Use real option methods

19

slide-20
SLIDE 20

Anticipation for Efficient Electricity Transmission Network Investments

Vincent Rious, Yannick Perez, Jean-Michel Glachant Philippe Dessante

Conference Berlin 8th October 2010 Thank you for your attention Questions ? Comments ?