transmission network investments
play

Transmission Network Investments Vincent Rious, Yannick Perez - PowerPoint PPT Presentation

Anticipation for Efficient Electricity Transmission Network Investments Vincent Rious, Yannick Perez Jean-Michel Glachant Philippe Dessante Conference Belrin 9 th October 2010 Outline 2 Motivation Problem Model Illustration


  1. Anticipation for Efficient Electricity Transmission Network Investments Vincent Rious, Yannick Perez Jean-Michel Glachant Philippe Dessante Conference Belrin 9 th October 2010

  2. Outline 2 • Motivation • Problem • Model • Illustration • Conclusion

  3. Coordinated gen° and trans° investments by an integrated utility 3 Integrated Utility  Easy to know when to build each investment considering the longest construction lead time

  4. Unbundling and coordination need 4 Generation Time to Notional technology build (year) size (MW) Liberalised power system CCGT 2 800 >> Prompts investors to choose Wind onshore 2 25 generation technologies with short offshore 2 100 construction lead time Coal 4-5 150-1600 Nuclear 5-7 1600 Congestion while the network is not upgraded Right of way of powerlines facing increasing oppositions  ~ 7 years to build a powerline from study to construction itself because of administrative agreement >> 5 years!

  5. Two possible behaviors for the TSO 5 • Reactive behavior – Wait connection request to study opportunity for transmission investments • Proactive behavior – Anticipate connection request in areas with exploitable energy sources • Gas • Wind – Administrative procedures are already agreed when generators request for connection

  6. Advantages & drawbacks of the two possible behaviors 6 • Reactive behavior  Excessive congestion if CCGT or wind power involved while network is upgraded • Proactive behavior – No excessive congestion – But proactive behavior is costly because, if generation does not come, the TSO did • the study to upgrade the network • And the procedures to obtain the administrative agreement to build the line

  7. Outline 7 • Motivation • Problem • Model • Illustration • Conclusion

  8. Problem 8 • What is the efficiency of anticipating generation connection for the TSO in terms of minimization of the network cost? – No anticipation creates congestion for quite long period while network must be upgraded – But anticipation is costly if the anticipated generators do not eventually come  We must arbitrate between these two costs

  9. Outline 9 • Motivation • Problem • Model • Illustration • Conclusion

  10. Sequence of investments with a reactive TSO 10 0 Year Construction Study, admin. proced. construction d Generation Transmission Investment Investment CW ( d ) CU ( d ) Excessive congestion Optimal value for network capacity

  11. Costs faced by a reactive TSO 11 Congestion cost w ithout and after the network being u pgraded Generator invests does not invest Expected social cost TSO Probability p Probability 1- p     waits for connection E C p re active TSO CW(d) + CU(d) of power plant        0 + 0 CW d CU d before studying and    + I/(1+a) d p     d upgrading   I 1 a Transmission No congestion investment cost & no network investment

  12. Sequence of investments with a proactive TSO 12 0 Year Construction Study, admin. proced. construction Generation and Network Investments CU (0)

  13. Costs faced by a proactive TSO 13 Congestion cost with u pgrade as soon as the generator connects Generator invests does not invest Expected social cost TSO Probability p Probability 1- p     waits for connection E C p proactive TSO   of power plant     a I + 0 p I CR 0 I + CU(0) before studying and   I   a 1 p upgrading Transmission No congestion cost investment cost Anticipation cost = network study + admin proced.

  14. Condition for a proactive TSO to be efficient 14 • When is proactive as efficient as reactive? a     p              a     lim d 1 a 1 CW d CU d CW 0 I p < p lim  reactive TSO > proactive TSO p > p lim  proactive TSO > reactive TSO The anticipation strategy is all the more efficient that p lim is small For a given a, p lim as function of d

  15. Outline 15 • Motivation • Problem • Model • Illustration • Conclusion

  16. “Probability limit” and condition for a proactive TSO 16

  17. Outline 17 • Motivation • Problem • Model • Illustration • Conclusion

  18. Conclusion 18 • A model to evaluate the efficiency of anticipating of power plants to minimize the cost of the network • Illustration on a simple realistic example with CCGT – Efficient to anticipate the connection of power plants for the TSO – Planning in advance network reinforcement – Reduce congestion cost

  19. Future researches 19 • Variation of the cost of anticipating • Duplicate this study for wind farm • Interaction with regulatory actions • Use real option methods

  20. Anticipation for Efficient Electricity Transmission Network Investments Thank you for your attention Questions ? Comments ? Vincent Rious, Yannick Perez, Jean-Michel Glachant Philippe Dessante Conference Berlin 8t h October 2010

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend