the transmission lay of the land
play

The Transmission Lay of the Land Overview Energy Markets - PowerPoint PPT Presentation

The Transmission Lay of the Land Overview Energy Markets Transmission Planning Beth Soholt John Moore April 21, 2010 www.windonthewires.org Overview www.windonthewires.org Regional Transmission Organizations Organizations of


  1. The Transmission Lay of the Land Overview Energy Markets Transmission Planning Beth Soholt John Moore April 21, 2010 www.windonthewires.org

  2. Overview www.windonthewires.org

  3. Regional Transmission Organizations � Organizations of transmission owners, users, and other entities � Manage regional energy markets, grid reliability and transmission planning/expansion 3 www.windonthewires.org

  4. Focus on Midwest ISO � About 138 GW of generation – Coal-fired generation is majority of MISO’s installed capacity (52%) and an even larger proportion of the total energy produced (77%) . – Natural gas generation is second in installed capacity (almost 22%) but produces less than than 5% of the energy in the region. 4 www.windonthewires.org

  5. Focus on Midwest ISO � Provides independent and open access transmission system access � Better reliability coordination – and exclusive authority to maintain short-term reliability � Administer its own tariff and transmission pricing system � Coordinate regional transmission planning (supposed to include DR and other demand-side actions) � Responsible for calculating Total Transmission Capacity (TTC) and Available Transmission Capacity (ATC) 5 www.windonthewires.org

  6. Other MISO Facts � MISO relies heavily on imports from adjacent areas – Although power can flow in either direction depending on prevailing prices, the Midwest ISO generally imports power from PJM and Manitoba and exports power to IESO . � Development of demand participation is lagging behind PJM – Although MISO has more than 8,000 MW of total demand response (2008), much of this is interruptible load which was developed under regulated utility programs and is only curtailable for reliability purposes. www.windonthewires.org

  7. Energy Markets www.windonthewires.org

  8. Midwest ISO – Energy Markets � Markets – Day-Ahead and Real-Time Energy Markets – Financial Transmission Rights Market (hedging against congestion) – Ancillary Services Market – No binding capacity market (unlike PJM) 8 www.windonthewires.org

  9. Midwest ISO – Energy Markets � Energy Market Description: Real-time, centralized, bid-based, security-constrained economic dispatch using Locational Marginal Pricing (LMP) to manage transmission congestion. 9 www.windonthewires.org

  10. Energy Market Basics � Economic Dispatch – “The operation of generation facilities to produce energy at the lowest cost to reliably serve consumers, recognizing any operational limits of generation and transmission facilities.” – Markets use demand bids and supply offers, rather than generating unit costs, as economic measure of dispatch. (Goal is to use competitive market forces to drive down cost to the marginal cost) – Dispatch occurs every 5 minutes . www.windonthewires.org

  11. Energy Market Basics � LMPs – reflects energy value at specific time and location – Defines the marginal cost of serving the next increment of load at each location/area, taking into account the electricity demand, generation costs, and the limits of the transmission system. – Generally, the highest variable cost unit (unit on the margin) that must be dispatched to meet load within a transmission-constrained boundary will set the LMP for that area. • If no transmission constraints, LMPs will not vary across the region . � Goals of LMPs – Price signals intended to encourage new generation where they will receive higher prices – or DR and EE, in a properly designed market. – Supposed to encourage new transmission construction in congested areas to reduce the financial impact of congestion on electricity prices. www.windonthewires.org

  12. LMP Contour Map Identifies Prices, Congestion 12 www.windonthewires.org

  13. Transmission Planning www.windonthewires.org

  14. Policy Issues for Implementing Transmission for Clean Energy Vision � Planning – what to build? – Individual utility, MISO/PJM expansion plans, multi-state (UMTDI), interconnection-wide (EIPC, EISPC) � Cost Allocation – who pays? – MISO CARP (state regulators) – MISO RECB (filing July 15, 2010) � Siting/Routing - permitting 14 www.windonthewires.org

  15. New and Upgraded Transmission in SW MN for Wind Power New lines: Split Rock – Lakefield Junction * 345 kV Lakefield Junction – Fox Lake * 161 kV Nobles – Fenton – Chanarambie * 115 kV Buffalo Ridge – White * 115 kV Chanarambie – Lake Yankton – Lyon 115 kV Upgraded lines: Fox Lake – Winnebago 161 kV Martin Co – Wilmarth 345 kV * X cel Energy Certificate of Need, Minnesota Public Utilities Commission Decision 1/30/03 www.windonthewires.org

  16. CapXGroup I Lines Twin Cities – LaCrosse, WI: ~150 miles, 345 kV Fargo, ND - Twin Cities: ~250 miles, 345 kV Brookings, SD – Hampton Corners : ~200 miles, 345 kV www.windonthewires.org

  17. Regional Transmission Planning � Midwest ISO – Transmission Expansion Planning (MTEP 2010) • Regional Generation Outlet Study (RGOS) • Top Congested Flowgate, Cross Border Congested Flowgate Studies � PJM – Regional Transmission Expansion Planning (2010 RTEP) � DOE – Eastern Interconnection Planning Collaborative Eastern Interconnection States Planning Council Other Initiatives – input to regional planning � “ Strategic Area Midwest Transmission Study ” – ATC, AEP, MidAmerican, Exelon, Xcel, Northwestern – Study of transmission needed to deliver 55 GW of total wind � “ Green Power Express”, ITC , Proposal to deliver 12 GW of wind 17 www.windonthewires.org

  18. Regional Planning Initiatives - MISO � Upper Midwest Transmission Development Initiative (UMTDI) – Led by Governors of Minnesota, North Dakota, South Dakota, Iowa and Wisconsin to coordinate sub-regional transmission planning and related cost allocation issues – Provides input to MISO Regional Generation Outlet Study (RGOS) • Renewable Energy Zone Selection • Transmission Scenarios – 345 kV, 765 kV and DC lines and combinations 18 www.windonthewires.org

  19. Regional Generation Outlet Study - MISO � Developing transmission projects that will facilitate the state renewable energy mandates in the Midwest ISO footprint � Phase I (North Dakota, South Dakota, Minnesota, Wisconsin, Iowa, Illinois) – Started May 2008; Final report posted March 5, 2010 – 15 GW & 25 GW; UMTDI Scenarios plus IL zones & existing wind � Phase II (added Missouri, Illinois, Indiana, Michigan, Ohio; incorporates results for RGOS I) – Referred to as ‘RGOS’ going forward (from December 2009) – The development of zones is complete; ~ 40 GW of total wind – Iterative development of transmission plans under way; options will include 345 kV, 765 kV, and HVDC – Analysis will include power flow, production cost models (PROMOD), and business case / value metrics – Goal is to deliver one plan to Appendix B of the MTEP 2010 Report 19 www.windonthewires.org

  20. Regional Generation Outlet Study - MISO � 20 www.windonthewires.org

  21. “Green Power Express” Proposed Overlay Still In Development 21 www.windonthewires.org

  22. “Strategic Midwest Area Transmission Study” Proposed Overlays Still In Development 22 Source: Quanta Technology 2/18/10 www.windonthewires.org

  23. Extra Slides www.windonthewires.org

  24. Carbon www.windonthewires.org

  25. Carbon – Midwest ISO � MGA and Re-Amp carbon goals � Waxman-Markey proposes an 83% carbon reduction (against a 2005 baseline) by 2050 – The 2005 Carbon Baseline for the Midwest ISO is approximately 500 million tons – Would require a reduction of approximately 400 million tons by 2050 � Achieving a reduction in emissions to that level will require a combination of regulatory and policy options to be employed – Demand Response and Energy Efficiency programs to manage future load and slow need for new generation, and its associated emissions – Implementation of existing & strengthened Renewable Portfolio Standards and regional goal to implement large amounts of wind resources – Carbon pricing to support fuel switching and drive retirement 25 www.windonthewires.org

  26. Carbon Bands of Reduction MISO Board of Directors Presentation 4/13/10 26 www.windonthewires.org

  27. Carbon Bands of Reduction MISO Board of Directors Presentation 4/13/10 27 www.windonthewires.org

  28. Midwest Electric Generation is Heavily Dependent on Coal and Nuclear 28 www.windonthewires.org

  29. MISO Wind and Load www.windonthewires.org

  30. MISO Capacity Additions through 2025 120,000 96,888 100,000 80,000 74,752 57,048 60,000 50,888 50,432 49,232 45,835 41,018 39,795 40,000 28,835 20,000 ‐ CARP BAU with CARP RPS CARP CAP CARP MTEP09/JCSP MTEP09/JCSP EWITS MISO PAC BAU ML PAC BAU H PAC Carbon High D+E CAP,RPS,Smart Reference Gas Future Scenario 2 Demand and Demand and Cap future with grid, Electric Energy MH Energy Nuclear Vehicles Queue/Planned Coal CC CT NUCLEAR Wind IGCC w/Seq CC w/Seq Biomass Hydro PV DR www.windonthewires.org

  31. Power Moves from Low-Cost to High-Cost Areas • NREL ’ s EWITS report found that major new transmission paths will continue to “ drive energy from low-cost source areas in the Midwest to high cost sink areas: = lower power prices = higher power prices www.windonthewires.org

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend