The Transmission Lay of the Land Overview Energy Markets - - PowerPoint PPT Presentation

the transmission lay of the land
SMART_READER_LITE
LIVE PREVIEW

The Transmission Lay of the Land Overview Energy Markets - - PowerPoint PPT Presentation

The Transmission Lay of the Land Overview Energy Markets Transmission Planning Beth Soholt John Moore April 21, 2010 www.windonthewires.org Overview www.windonthewires.org Regional Transmission Organizations Organizations of


slide-1
SLIDE 1

www.windonthewires.org

The Transmission Lay of the Land

April 21, 2010

Overview Energy Markets Transmission Planning Beth Soholt John Moore

slide-2
SLIDE 2

www.windonthewires.org

Overview

slide-3
SLIDE 3

www.windonthewires.org

Regional Transmission Organizations

3

Organizations of transmission owners, users, and other entities Manage regional energy markets, grid reliability and transmission planning/expansion

slide-4
SLIDE 4

www.windonthewires.org

About 138 GW of generation

– Coal-fired generation is majority of MISO’s installed capacity (52%) and an even larger proportion of the total energy produced (77%) . – Natural gas generation is second in installed capacity (almost 22%) but produces less than than 5% of the energy in the region.

4

Focus on Midwest ISO

slide-5
SLIDE 5

www.windonthewires.org

5

Focus on Midwest ISO

Provides independent and open access transmission system access Better reliability coordination – and exclusive authority to maintain short-term reliability Administer its own tariff and transmission pricing system Coordinate regional transmission planning (supposed to include DR and other demand-side actions) Responsible for calculating Total Transmission Capacity (TTC) and Available Transmission Capacity (ATC)

slide-6
SLIDE 6

www.windonthewires.org

Other MISO Facts

MISO relies heavily on imports from adjacent areas

– Although power can flow in either direction depending

  • n prevailing prices, the Midwest ISO generally imports

power from PJM and Manitoba and exports power to IESO.

Development of demand participation is lagging behind PJM

– Although MISO has more than 8,000 MW of total demand response (2008), much of this is interruptible load which was developed under regulated utility programs and is only curtailable for reliability purposes.

slide-7
SLIDE 7

www.windonthewires.org

Energy Markets

slide-8
SLIDE 8

www.windonthewires.org

Markets

– Day-Ahead and Real-Time Energy Markets – Financial Transmission Rights Market (hedging against congestion) – Ancillary Services Market – No binding capacity market (unlike PJM)

8

Midwest ISO – Energy Markets

slide-9
SLIDE 9

www.windonthewires.org

9

Midwest ISO – Energy Markets

Energy Market Description:

Real-time, centralized, bid-based, security-constrained economic dispatch using Locational Marginal Pricing (LMP) to manage transmission congestion.

slide-10
SLIDE 10

www.windonthewires.org

Energy Market Basics

Economic Dispatch

– “The operation of generation facilities to produce energy at the lowest cost to reliably serve consumers, recognizing any

  • perational limits of generation and transmission facilities.”

– Markets use demand bids and supply offers, rather than generating unit costs, as economic measure of dispatch. (Goal is to use competitive market forces to drive down cost to the marginal cost) – Dispatch occurs every 5 minutes.

slide-11
SLIDE 11

www.windonthewires.org

Energy Market Basics

LMPs – reflects energy value at specific time and location

– Defines the marginal cost of serving the next increment of load at each location/area, taking into account the electricity demand, generation costs, and the limits of the transmission system. – Generally, the highest variable cost unit (unit on the margin) that must be dispatched to meet load within a transmission-constrained boundary will set the LMP for that area.

  • If no transmission constraints, LMPs will not vary across the region.

Goals of LMPs

– Price signals intended to encourage new generation where they will receive higher prices – or DR and EE, in a properly designed market. – Supposed to encourage new transmission construction in congested areas to reduce the financial impact of congestion on electricity prices.

slide-12
SLIDE 12

www.windonthewires.org

12

LMP Contour Map Identifies Prices, Congestion

slide-13
SLIDE 13

www.windonthewires.org

Transmission Planning

slide-14
SLIDE 14

www.windonthewires.org

Policy Issues for Implementing Transmission for Clean Energy Vision

Planning – what to build?

– Individual utility, MISO/PJM expansion plans, multi-state (UMTDI), interconnection-wide (EIPC, EISPC)

Cost Allocation – who pays?

– MISO CARP (state regulators) – MISO RECB (filing July 15, 2010)

Siting/Routing - permitting

14

slide-15
SLIDE 15

www.windonthewires.org

New and Upgraded Transmission in SW MN for Wind Power

New lines: Split Rock – Lakefield Junction* 345 kV Lakefield Junction – Fox Lake* 161 kV Nobles – Fenton – Chanarambie* 115 kV Buffalo Ridge – White* 115 kV Chanarambie – Lake Yankton – Lyon 115 kV Upgraded lines: Fox Lake – Winnebago 161 kV Martin Co – Wilmarth 345 kV

*Xcel Energy Certificate of Need, Minnesota Public Utilities Commission Decision 1/30/03

slide-16
SLIDE 16

www.windonthewires.org

CapXGroup I Lines

Twin Cities – LaCrosse, WI: ~150 miles, 345 kV Fargo, ND - Twin Cities: ~250 miles, 345 kV Brookings, SD – Hampton Corners : ~200 miles, 345 kV

slide-17
SLIDE 17

www.windonthewires.org

Regional Transmission Planning

Midwest ISO

– Transmission Expansion Planning (MTEP 2010)

  • Regional Generation Outlet Study (RGOS)
  • Top Congested Flowgate, Cross Border Congested Flowgate Studies

PJM

– Regional Transmission Expansion Planning (2010 RTEP)

DOE

– Eastern Interconnection Planning Collaborative Eastern Interconnection States Planning Council

Other Initiatives – input to regional planning

“Strategic Area Midwest Transmission Study”

– ATC, AEP, MidAmerican, Exelon, Xcel, Northwestern – Study of transmission needed to deliver 55 GW of total wind

“Green Power Express”, ITC, Proposal to deliver 12 GW of wind

17

slide-18
SLIDE 18

www.windonthewires.org

Regional Planning Initiatives - MISO

Upper Midwest Transmission Development Initiative (UMTDI)

– Led by Governors of Minnesota, North Dakota, South Dakota, Iowa and Wisconsin to coordinate sub-regional transmission planning and related cost allocation issues – Provides input to MISO Regional Generation Outlet Study (RGOS)

  • Renewable Energy Zone Selection
  • Transmission Scenarios

– 345 kV, 765 kV and DC lines and combinations

18

slide-19
SLIDE 19

www.windonthewires.org

Regional Generation Outlet Study - MISO

19

Developing transmission projects that will facilitate the state renewable energy mandates in the Midwest ISO footprint Phase I (North Dakota, South Dakota, Minnesota, Wisconsin, Iowa, Illinois)

– Started May 2008; Final report posted March 5, 2010 – 15 GW & 25 GW; UMTDI Scenarios plus IL zones & existing wind

Phase II (added Missouri, Illinois, Indiana, Michigan, Ohio; incorporates results for RGOS I)

– Referred to as ‘RGOS’ going forward (from December 2009) – The development of zones is complete; ~ 40 GW of total wind – Iterative development of transmission plans under way; options will include 345 kV, 765 kV, and HVDC – Analysis will include power flow, production cost models (PROMOD), and business case / value metrics – Goal is to deliver one plan to Appendix B of the MTEP 2010 Report

slide-20
SLIDE 20

www.windonthewires.org

  • 20

Regional Generation Outlet Study - MISO

slide-21
SLIDE 21

www.windonthewires.org

“Green Power Express”

21

Proposed Overlay Still In Development

slide-22
SLIDE 22

www.windonthewires.org

22

“Strategic Midwest Area Transmission Study”

Proposed Overlays Still In Development

Source: Quanta Technology 2/18/10

slide-23
SLIDE 23

www.windonthewires.org

Extra Slides

slide-24
SLIDE 24

www.windonthewires.org

Carbon

slide-25
SLIDE 25

www.windonthewires.org

Carbon – Midwest ISO

25

MGA and Re-Amp carbon goals Waxman-Markey proposes an 83% carbon reduction (against a 2005 baseline) by 2050

– The 2005 Carbon Baseline for the Midwest ISO is approximately 500 million tons – Would require a reduction of approximately 400 million tons by 2050

Achieving a reduction in emissions to that level will require a combination of regulatory and policy options to be employed

– Demand Response and Energy Efficiency programs to manage future load and slow need for new generation, and its associated emissions – Implementation of existing & strengthened Renewable Portfolio Standards and regional goal to implement large amounts of wind resources – Carbon pricing to support fuel switching and drive retirement

slide-26
SLIDE 26

www.windonthewires.org

26

MISO Board of Directors Presentation 4/13/10

Carbon Bands of Reduction

slide-27
SLIDE 27

www.windonthewires.org

27

MISO Board of Directors Presentation 4/13/10

Carbon Bands of Reduction

slide-28
SLIDE 28

www.windonthewires.org

28

Midwest Electric Generation is Heavily Dependent on Coal and Nuclear

slide-29
SLIDE 29

www.windonthewires.org

MISO Wind and Load

slide-30
SLIDE 30

www.windonthewires.org

MISO Capacity Additions through 2025

50,888 57,048 41,018 96,888 49,232 50,432 74,752 28,835 45,835 39,795 ‐ 20,000 40,000 60,000 80,000 100,000 120,000 CARP BAU with High D+E CARP RPS CARP CAP CARP CAP,RPS,Smart grid, Electric Vehicles MTEP09/JCSP Reference MTEP09/JCSP Gas Future EWITS MISO Scenario 2 PAC BAU ML Demand and Energy PAC BAU H Demand and MH Energy PAC Carbon Cap future with Nuclear Queue/Planned Coal CC CT NUCLEAR Wind IGCC w/Seq CC w/Seq Biomass Hydro PV DR

slide-31
SLIDE 31

www.windonthewires.org

  • NREL’s EWITS report found that major new transmission paths will

continue to “drive energy from low-cost source areas in the Midwest to high cost sink areas:

Power Moves from Low-Cost to High-Cost Areas

= lower power prices = higher power prices