10 year transmission 10 year transmission expansion plan
play

10 Year Transmission 10 Year Transmission Expansion Plan Expansion - PowerPoint PPT Presentation

Southeastern Region Southeastern Region Transmission Planning Transmission Planning 10 Year Transmission 10 Year Transmission Expansion Plan Expansion Plan Southeastern Region Southeastern Region Transmission Planning Transmission


  1. Southeastern Region Southeastern Region Transmission Planning Transmission Planning 10 Year Transmission 10 Year Transmission Expansion Plan Expansion Plan

  2. Southeastern Region Southeastern Region Transmission Planning Transmission Planning Disclaimer � The projects described in this presentation represent the current ten (10) year expansion plan. The expansion plan is periodically reviewed and may be revised due to changes in assumptions. � This presentation does not represent a commitment to build for projects listed in the future.

  3. Southeastern Region Southeastern Region Transmission Planning Transmission Planning Input Assumptions for Input Assumptions for 10 Year Expansion Plan 10 Year Expansion Plan

  4. Southeastern Region Southeastern Region Transmission Planning Transmission Planning

  5. Southeastern Region Southeastern Region Transmission Planning Transmission Planning 2010 Regional Generation 2010 Regional Generation Dahlberg Assumptions Assumptions Conasauga Hancock CC Rocky Mtn Warren Co Bio McDonough Vogtle Wansley Tenaska Piedmont Bio Washington Co CT Kemper Central AL Warthen CT West Georgia Franklin CC Harris CC Moselle SMARR CC Lee Road SOWEGA Baconton McIntosh East Bainbridge Existing Generation Farley Future Generation

  6. Southeastern Region Southeastern Region Transmission Planning Transmission Planning Generation Assumptions for the 2010 Transmission Expansion Planning Process Year Site MW Site MW Year -100 GTC Dahlberg CT -160 GTC Dahlberg CT East Bainbridge -72 -100 Lee Road CT Franklin 2 625 45 Rocky Mountain Lindsay Hill CC 205 572 Wansley CC7 -51 McDonough 2 Coal -600 Warthen CT 2011 Rocky Mountain 44 2010 150 West GA Gen Warthen CT 390 292 SoCo Dahlberg CT PS McIntosh 4 & 5 448 942 Exelon Heard CT SoCo Farley 1 Uprate 35 -559 Franklin 1 Franklin 2 -625 -627 Harris 1 -200 McDonough 2 Coal -572 Wansley CC7

  7. Southeastern Region Southeastern Region Transmission Planning Transmission Planning Generation Assumptions for the 2010 Transmission Expansion Planning Process Site MW Year Site MW Year SoCo 55 GTC Fitzgerald Bio Central Alabama CC 885 2013 -49 841 McDonough 1 Coal McDonough CC6 150 SMEPA Moselle 78 GTC East Bainbridge -620 SoCo Conasauga 50 Lee Road CT 2012 35 Farley 2 Uprate 90 SOWEGA 2014 100 -202 Warren Co Bio McDonough 1 Coal -197 SoCo Baconton CT 841 McDonough CC4 -292 Dahlberg CT 841 McDonough CC5 600 Kemper IGCC 50 Piedmont Bio

  8. Southeastern Region Southeastern Region Transmission Planning Transmission Planning Generation Assumptions for the 2010 Transmission Expansion Planning Process Site MW Year Site MW Year GTC Dahlberg CT 300 16 Dalton Vogtle 4 -78 330 East Bainbridge GTC Vogtle 4 561 -50 Wansley CC6 Lee Road CT 2017 2015 250 MEAG Vogtle 4 605 SMARR CC 504 SoCo Vogtle 4 -90 SOWEGA -561 Wansley CC6 734 Washington Co CT 16 Dalton Vogtle 3 -300 GTC Dahlberg CT 330 Vogtle 3 2016 -70 Warthen CT 250 MEAG Vogtle 3 504 SoCo Vogtle 3

  9. Southeastern Region Southeastern Region Transmission Planning Transmission Planning Generation Assumptions for the 2010 Transmission Expansion Planning Process Site MW Year N/A N/A N/A 2018 McIntosh 6 187 PS Hancock CC1 840 2019 SoCo Harris 2 -628 2020 840 SoCo Hancock CC2

  10. Southeastern Region Southeastern Region Transmission Planning Transmission Planning Generation Assumptions for the 2010 Transmission Expansion Planning Process PTPs ending PTPs ending within the planning within the planning horizon horizon PTPs preserved through the planning horizon PTPs preserved through the planning horizon Starting in Site MW Year Site MW Year 2010 Dahlberg 75 2010 – 2014 Scherer 3 42 PTP PTP 2010 Franklin 535 2010 – 2014 Miller 164 2010 Harris 1 584 2011 Bowen 50 2010 Hillabee 700 2011 Wansley 155 2010 Scherer 3 235 2015 Miller 103 2010 Scherer 4 850 2010 Lindsay Hill 300 2011 Lindsay Hill 200 2012 Dahlberg 180 2015 Vogtle 103 2016 Vogtle 103

  11. Southeastern Region Southeastern Region Transmission Planning Transmission Planning 10 Year Transmission Expansion Plan � The in-service date of each project is June 1 st of the stated project year unless otherwise specified � The need date of each project is the same as the in-service date unless otherwise specified

  12. Southeastern Region Southeastern Region Transmission Planning Transmission Planning East Region Georgia Integrated Transmission System (ITS) � Dalton Utilities Jointly � GTC (Georgia Transmission Corporation) Planned ITS � MEAG (Municipal Electric Authority of GA) � Southern Company Transmission

  13. Southeastern Region Southeastern Region Transmission Planning Transmission Planning 2011 ITS-1a Expansion Item ITS-1a Factory Shoals � Create a 230 / 115 kV network substation at Factory Shoals. � Install one 230 / 115 kV 300 MVA transformer. � Tap the Adamsville – Douglasville 230 kV line from Buzzard Roost for 230 kV source using existing line. � Create a 115 kV network station by breakering up the Douglasville – Greenbriar 115 kV line.

  14. Southeastern Region Southeastern Region Transmission Planning Transmission Planning 2011 ITS-1b Expansion Item ITS-1b Factory Shoals � Install three 230 kV breakers at Buzzard Roost, looping in the Adamsville- Douglasville 230 kV line, with a third terminal serving Factory Shoals. Tap the Adamsville – Douglasville 230 kV line from Buzzard Roost for 230 kV source using existing line. � Alleviates the overload of Gordon Road – Hightower 115 kV T.L., Adamsville – Greenbriar 115 kV T.L. and the Douglasville 230 / 115 kV transformer given various contingencies.

  15. Factory Shoals 2011 ITS-1 Plt. Jack McDonough Problem: Loss of the Groover Lake segment 230kV of the Douglasville – Greenbriar 115kV line overloads the East Point – Gordon Rd. Jct to Mableton, to Jack Mac.- Jack Mac-West West Mar. 115 Groover Factory Mar.115 Shoals Douglasville Lake Hightower. Jct Gord Rd. Gordon 115kV Fact Shls Rd. Jct Jct Thornton Adamsville Solution: Road •Breaker up Buzzard Roost 230kV •Add 230kV line Thornton Rd. to Factory Shoals. Greenbriar Buzzard Roost •Add 230/115 autobank and 115 breakers at Factory Shoals. Bakers Boat Rock Ferry Post 230kV Road East Point

  16. Southeastern Region Southeastern Region Transmission Planning Transmission Planning 2011 ITS-2 Expansion Item ITS-2 Arkwright – Gordon #1 115 kV Transmission Line � Rebuild the Arkwright – Gordon #1 115 kV Transmission Line (23.6 miles) with 795 ACSR conductor at 100°C. � This line becomes thermally overloaded given multiple contingencies in 2011.

  17. Arkwright – Gordon #1 115 kV T.L. 2011 ITS-2 Arkwright Gordon

  18. Southeastern Region Southeastern Region Transmission Planning Transmission Planning 2012 ITS-3 Expansion Item ITS-3 Kraft – McIntosh 230 kV T.L.s � Rebuild 16 miles along the Kraft – McIntosh Black and White 230 kV T.L.s with 1622 ACCR/TW. � The loss of either Kraft – McIntosh 230 kV T.L. will overload the parallel 230 kV T.L.

  19. Kraft – McIntosh 230 kV T.L.s 2012 ITS-3 McIntosh The loss of one Kraft – McIntosh 230 kV T.L. Reconductor the Kraft – overloads the McIntosh 230 kV Black & White parallel 230 kV transmission lines with 1622 line. ACCR/TW. Kraft

  20. Southeastern Region Southeastern Region Transmission Planning Transmission Planning 2014 ITS-4 Expansion Item ITS-4 McIntosh – Blandford – Meldrim 230 kV T.L.s � Reconductor 18.2 miles along the McIntosh – Blandford – Meldrim Black and White 230 kV T.L.s. � The loss of either McIntosh – Meldrim 230 kV T.L. will overload the parallel 230 kV T.L.

  21. McIntosh – Blandford – Meldrim 230 kV T.L.s 2014 ITS-4

  22. Southeastern Region Southeastern Region Transmission Planning Transmission Planning 2015 ITS-5 Expansion Item ITS-5 Boulevard 230 / 115 kV Substation � Install a 230 / 115 kV transformer at the existing Boulevard 115 kV substation. � Rebuild the Boulevard – Dean Forest 115 kV double circuit line with 2-795 ACSR at 230 kV specifications. Operate one circuit at 115 kV and the other at 230 kV. � The loss of one of the Deptford – Kraft 115 kV T.L.s causes the other line to become overloaded.

  23. Boulevard 230 / 115 kV Substation 2015 ITS-5

  24. Southeastern Region Southeastern Region Transmission Planning Transmission Planning 2015 ITS-6a Expansion Item ITS-6a East Walton 500 / 230 kV Project � Construct a new 500 /230 kV Substation at East Walton. � Construct a new Rockville 500 kV Switching Station. � Construct a new 500 kV T.L. from the new Rockville 500 kV Switching Station to the new East Walton 500 / 230 kV substation. � Construct 230 kV T.L. from East Walton to Jacks Creek

  25. Southeastern Region Southeastern Region Transmission Planning Transmission Planning 2015 ITS-6b Expansion Item ITS-6b East Walton 500 / 230 kV Project � Construct a new 230 kV T.L. from East Walton to the new Bostwick Switching Station. � Construct a new 230 kV T.L. from Bethabara to East Walton. � The loss of the Klondike – Scherer 500 kV T.L. will thermally overload the Klondike – O’Hara 500 kV T.L.

  26. East Walton 500 / 230 kV Project 2015 ITS-6

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.