2006 caiso transmission plan
play

2006 CAISO Transmission Plan Presentation to the California ISO - PowerPoint PPT Presentation

2006 CAISO Transmission Plan Presentation to the California ISO Board of Governors January 24, 2007 Gary L. DeShazo Director of Regional Transmission North 2006 CAISO Transmission Plan The first CAISO Transmission Plan is before you today


  1. 2006 CAISO Transmission Plan Presentation to the California ISO Board of Governors January 24, 2007 Gary L. DeShazo Director of Regional Transmission North

  2. 2006 CAISO Transmission Plan • The first CAISO Transmission Plan is before you today – Plan presented to stakeholders in early December • An old era ends – Individual PTO plans received and reviewed – CAISO review focused on individual projects, not an overall plan – Operational concerns/issues generally were not addressed • A new era begins with this 2006 Transmission Plan – Single transmission plan for the CAISO Controlled Grid – PTO and CAISO projects combined into a single plan – Operations, short-term, mid-term, and long-term focus – CAISO review focuses on overall plan – Consistent with sub-regional planning principles Gary DeShazo/Regional Transmission North 2 1/24/2007

  3. What Is In the “Plan” • Annual transmission plan prepared jointly by the CAISO and PTOs and reviewed by stakeholders • Coordinated with the PTOs, CEC, and CPUC • Documents all CAISO and PTO studies – All projects under $20M approved by CAISO Management – All projects $20M or greater are listed but individually approved by CAISO Board – All projects that are anticipated to be brought before the CAISO Board • Projects to be considered for “approval” by the CAISO must be in the Plan – No more closure letters • Fifteen year planning horizon • Five year LCR horizon • Baseline deliverability studies • Integrate relevant CEC IEPR recommendations Gary DeShazo/Regional Transmission North 3 1/24/2007

  4. 2006 “Plan” Highlights Transmission • Documents 160 transmission project proposals • Includes the seven CAISO Transmission Initiatives presented to the Board in April 2006 Number of Projects SDG&E 34 SCE PG&E 32 94 Gary DeShazo/Regional Transmission North 4 1/24/2007

  5. 2006 “Plan” Highlights Transmission • Summarizes major California and inter-regional planning initiatives – Tehachapi Project – Sun Path Project (Sunrise + Green Path) – LEAPS Project – Trans Bay Cable Project – Midway – Gregg Line – Frontier Line – New British Columbia – California Line – West Coast Cable Project Gary DeShazo/Regional Transmission North 5 1/24/2007

  6. 2006 “Plan” Highlights Deliverability • Phase I – Evaluation of all generation expected to be in operation in 2006 (58,000 MW) • Phase II Complete by February 2007 – Phase IIA evaluates all generation in the interconnection “queue” as of March 30, 2005 (22,000 MW) – Phase IIB will include all remaining generation in the interconnection queue • Phase II Report – List of new resources that do not pass deliverability test – Amount of non-deliverable capacity for new resources – Conceptual transmission project alternatives that would ensure their deliverability Gary DeShazo/Regional Transmission North 6 1/24/2007

  7. Phase IIA Captain Mali Jack n Celil o Deliverability Study Trinit Shast Round y a Mountain 14 Generation Pockets Humbol Nuclear Keswic PIT dt k River Generation Olind Cortin Generatio +50 kV a Hyat a n 50 0 k DC Feather Substatio Identified t 23 k Tabl 0 V River n Cottonwo Mountai e WECC Transfer 11 0 V k Humbol Sierr dt od n Path 5 V a Palerm o -Contra Solan Colgat o Costa Cortin Dru e m a Rio Geyser Summi Oso Geyser s t Atlanti s c Fulto Vac Gold n a Hill Lakevill Dixo e n Ignaci Brighto Bir o n Pittsburg Landin d Trac Geyser h g Win y s Bellot Maste -McCa -Wilso d Panoch Sobrant Contra a r e ll n Costa e Potrer Tesl Newar o Pittsburg k a Big h Wilso Creek n Warnervil Metca le LDWP Los lf San Gorge Helm Banos Luis SPP Silver s Peak Moss Landing Greg Kings Iny g River o Contr Intermounta Panoch ol Haiwe e in McCal Colorado Hoove e l River r Inyoker Balc n h Krame Market r Morro Place Bay Midwa Gate Victorvill Mea Perkin s y e d s McCullou Libert Magunde gh Adelant Cryst Diabl y n Mes o al Canyo o Pisga Cim a Antelop Navaj n h e a o Vince Lompo Eldorad c nt Parde o Palo Sylma Lug Mandala e Verde Lompo y r Mohav o c e Toluc Ormond Chin Beach a Mira o Castai Rinal Dever Loma East of c di North Devers s Santiag Gila Huntington o Beach Serran Valle Mirag Coachell o e y a II SONG Taleg Greater El D S a Centro Encin SD Escondid a o Encin Missio Moenko Southba a n Imperial Migu pi y Es /Sy Valley el Termoelectri c c US De ca Los Old A MEXIC Gary DeShazo/Regional Transmission North 7 1/24/2007 Mexicali O Coches Town Centr La Rosita al CF CF Hassayam II Tijuan E La E pa a Rosita

  8. LCR Outlook Requirements For 2006 & 2007 Anticipated Trend 2009 & 2011 PG&E SCE SDG&E 30,000 25,000 LCR Capacity, MW 20,000 15,000 10,000 5,000 - 2006 2007 2009 2011 Year Gary DeShazo/Regional Transmission North 8 1/24/2007

  9. 2006 “Plan” Highlights Short-term Plan and Operating Guides • Short-term Plan – Analyzes system from 1 to 3 years in advance and recommends to anticipated operations and reliability issues – Focuses on operational gaps; congestion and reliability – 21 recommendations proposed to PTOs based on 2006 summer operation • Operating Guide – Consolidates the next year calendar projects • 53 projects calendared for 2007 – Describes the transmission impacts of the project – Relates each project to the affected Operating Procedures – Provides a work-plan for updating OTC, Operating Procedures, and necessary tools Gary DeShazo/Regional Transmission North 9 1/24/2007

  10. Excerpt From the 2006 Operating Guide Targeted In- # Project Title Region Project Scope System Impact Service Date 1 Ignacio 115/60kV PG&E – Replace the 115/60kV transformers Reduces T-1 concern and increases 05/01/2007 Transformer North West with a larger unit (200 MVA) reliability to 60kV customers. Removes the Ignacio #1 or #3 Bank SPS. 2 Lakeville-Sonoma PG&E – Construct one new 115kV line from Improves L-1 voltage performance at 05/01/2007 115kV line North West Lakeville to Sonoma Sub. Sonoma and Pueblo substations. 3 Tulucay 230/60kV PG&E – Install a new 230/60kV transformer Increases transformer capacity 05/01/2007 Transformer North West (200 MVA) 4 Fulton-Lakeville PG&E – Reconfigure transmission to create a Increases Import capacity into South 11/30/2006 230kV line North West Fulton-Lakeville 230kV line. Geysers, reduces RMR requirement. 5 Reliability Project: PG&E – Replace Relays to increase the rating Increases import/export capability under 10/16/2006 Rio Dell Jct CB 42 & North West from 400A to 4/0 AL ratings of 297, some clearance conditions at Humboldt 22 Relay Replcmnt 345, 443, 473 Amps Bay PP. 6 Reliability Project: PG&E – Replace Relays to increase the rating Increases 60kV line capacity. 08/31/2006 Maple Creek CB 42 North West from 300A to 4/0 ACSR ratings of 297, Relay Replacement 345, 443, 473 Amps 7 W. Sacramento- PG&E – Reconductor the West Sacramento- Increases import capacity into Woodland 10/01/2006 Davis Transmission North East Davis 115kV line (215 MVA) and Davis 115kV system. Reduces L-1 concerns under clearance conditions. 8 Colgate-Rio Oso PG&E – Rerate 230kV transmission lines for Increase 230kV line capacity. 12/01/2006 230kV Line Re-Rate North East 3fps (429 MVA) 9 Davis-UC Davis 60kV PG&E – Convert two 60kV lines between Davis Increases voltage performance and 12/01/2006 to 115kV conversion North East and UC Davis to 115kV (252 MVA) thermal capacity to UC Davis. 10 Colgate 230/60kV PG&E – Replace 230/60kV transformer at Part of plan to radialize 60kV system. 03/01/2007 Capacity Increase North East Colgate Powerhouse with a larger unit Once radial, the Colgate T-1 concern will and install a spare phase (135 MVA) be eliminated. 11 Pease-Marysville PG&E – Construct new 60kV transmission line Part of plan to radialize 60kV system. 05/01/2007 60kV line North East (117 MVA) Once radial, the Colgate T-1 concern will be eliminated. Gary DeShazo/Regional Transmission North 10 1/24/2007 12 Mtn Quarries 60kV PG&E – Reconductor Mountain Quarries 60kV Increase 60kV line capacity. 05/01/2007 Tap Reconductor North East Tap (46 MVA)

  11. 2006 “Plan” Highlights • Area assessments – Detailed assessment and analysis of the CAISO Controlled Grid – Ten-year planning horizon – CAISO staff has identified over 30 LCR, Deliverability, and congestion issues across the Grid – Solutions are being considered for all issues • Future Plans (2007) – Scenario assessments – Congestion analysis pre and post MRTU – Resolution to LCR issues – Long-term Firm Transmission Rights – Import allocations within a Resource Adequacy framework – Probabilistic planning (LOLP) for LCR and Capacity Market – Third category of new transmission facilities – Rebuttable presumption Gary DeShazo/Regional Transmission North 11 1/24/2007

  12. End of Presentation Gary DeShazo/Regional Transmission North 12 1/24/2007

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend