Underground vs. Overhead Transmission TOTL Citizen Advisory Group - - PowerPoint PPT Presentation

underground vs overhead transmission
SMART_READER_LITE
LIVE PREVIEW

Underground vs. Overhead Transmission TOTL Citizen Advisory Group - - PowerPoint PPT Presentation

Underground vs. Overhead Transmission TOTL Citizen Advisory Group April 15, 2015 Transmission and Distribution Transmission System Distribution System Transmission lines Distributes electricity connect power to each customer's


slide-1
SLIDE 1

Underground vs. Overhead Transmission

 TOTL Citizen Advisory Group  April 15, 2015

slide-2
SLIDE 2

Transmission and Distribution

 Transmission lines

connect power generation plants to substations, other power generating plants, and other utilities at high voltages.

 Distributes electricity

to each customer's residence, business, or industrial plant at lower voltages.

Transmission System Distribution System

slide-3
SLIDE 3
slide-4
SLIDE 4

Transmission and Distribution

Transmission Distribution

slide-5
SLIDE 5

Underground and Overhead

 Undergrounding

transmission lines is less common

 Underground cables

have different technical requirements than

  • verhead and have

different impacts

 Undergrounding

distributions lines is more common

Transmission Distribution

slide-6
SLIDE 6

Impacts

 Design  Construction  Repair and Maintenance  Cost  Aesthetics

slide-7
SLIDE 7

Underground vs. Overhead Transmission

 Design Issues

 Specialized engineering skills required  Extensive study required to determine site-specific

subsurface obstructions or obstacles

 Longer timeframe for design  Need to provide larger budget contingency  Flood plain and wetland issues require special

consideration

 Environmental impacts

slide-8
SLIDE 8
slide-9
SLIDE 9

Underground vs. Overhead Transmission

 Construction Concerns

 Space for large vaults (8’ x 10’ X 20’)  Longer construction time frame  Dewatering in wet areas during construction  Significantly more impacts to surrounding properties

 Open trenches

 min. 5’ wide x 5’ deep

 Specialized backfill

slide-10
SLIDE 10
slide-11
SLIDE 11

Underground vs. Overhead Transmission

 Operational Concerns

 Difficult to identify outage location  Requires specialized work force  Long lead time for delivery of materials

 Need to warehouse specialized spare materials

 Increased maintenance  Shorter life span  Dewatering and cleaning of equipment in vaults

slide-12
SLIDE 12
slide-13
SLIDE 13

Underground vs. Overhead Transmission

 Cost

 Typical underground costs are 8 to 10 times the cost of

  • verhead construction

 Typical life of underground is approximately one-half the

life of overhead construction

 Depending on route may have significantly more

unanticipated problems with associated costs

 4-Cable system required to increase reliability which adds

cost

 Specialized workforce increases cost  Wetland mitigation may be substantially more depending

  • n route

 Warehousing of spare materials and equipment

slide-14
SLIDE 14
slide-15
SLIDE 15

Underground Transmission

 Generally used:

 in densely populated and urban settings  where sufficient right-of-way is not available  to reduce visual impacts

 riser poles at each end of the underground cable are large

and support additional equipment that create visual impacts

 Reliability

 May have fewer outages than overhead  When outages occur they will be more difficult to

locate and may take significantly more time to repair

slide-16
SLIDE 16
slide-17
SLIDE 17