The Case for Rail In the North-West City Region Into The West - July 2019 Background A clear disparity exists in rail provision : a) East & West of the River Bann. b) Between the North-West & the rest of the island Rail Map of


slide-1
SLIDE 1

In the North-West City Region

The Case for Rail

Into The West - July 2019

slide-2
SLIDE 2

Background

  • A clear disparity exists in rail provision :

a) East & West of the River Bann. b) Between the North-West & the rest of the island

slide-3
SLIDE 3

Rail Map of Ireland

slide-4
SLIDE 4

DERRY P O R T R U S H LARNE ANTRIM B E L F A S T C I T Y 1 1 S t a t i

  • n

s BANGOR P O R T A D O W N BALLYMENA NEWRY L I S B U R N

Location of NI’s 54 Rail Stations

East 51 West 3

Total Number of Rail Stations

C O L E R A I N E

slide-5
SLIDE 5

SIX WA YS DERRY’S RAILWA Y SERVICE IS SUB-STANDARD vs EAST OF THE BANN

2 3 4 5 6 1

S I X T O F I X

slide-6
SLIDE 6

7 Key Benefits of Rail

ECONOMIC :

Jobs/People gravitate towards good infrastructure.

EMPLOYMENT: Easier to access job & training opportunities.

SOCIAL JUSTICE: No car access = 36% in Derry, 40% in Strabane.

TOURISM :

Make it easier for visitors to access our area.

STATUS :

Certain things are expected in a regional capital. CLIMATE CHANGE: A viable alternative to private vehicle usage.

QUALITY OF LIFE: Cleaner air, less congestion, easier journeys.

slide-7
SLIDE 7

History of Rail in N.W.C.R

  • Comprehensive rail network existed on both sides of the border

across North-West City Region (NWCR) until the 1960s.

  • 2001 Stormont proposed shutting Derry-Belfast line at Coleraine
  • Every penny secured for rail infrastructure west of Bann since

then had to be fought for :

  • Took public campaign to save Derry’s rail line.
  • Took public campaign to secure upgrade of Derry’s track.
  • Took public campaign to secure new Waterside station.
  • Public campaign is now seeking to secure 3rd & final phase of

track modernisation work.

slide-8
SLIDE 8

‘Phase 3 is Key’

  • Rail track between Eglinton & Downhill is out-of-date

= Limits train speed & frequency.

  • Work to modernise it supposed to happen 2013 = Culture Year.
  • Split into 3 phases instead :
  • Phase 1 :

2013 = COMPLETED.

  • Phase 2 :

2016 = COMPLETED.

  • Phase 3 :

2021 = PUT OFF TO 2027 or INDEFINITELY.

  • Phase 3 is essential to :

1) End the rail discrimination against the NW. 2) Enable future improvements to rail here.

slide-9
SLIDE 9
slide-10
SLIDE 10

Lack of Ambition for Rail in NWCR

  • No future rail proposals in Council’s key strategies :
  • Local Development Plan ?
  • Strategic Growth Plan ?
  • City Deal Proposals ?
  • No protection of former rail routes in Planning Policies.
  • No mention of any future projects for North-West in Stormont’s

‘Rail Investment Prioritisation Strategy’ (2014).

  • Without a role for rail, how will council achieve key ambitions re :
  • Regeneration. - Economic Development
  • Climate Change. - Modal Shift (Transportation).
slide-11
SLIDE 11

What Enhanced Role Could Rail Have Here ?

1) Express trains to Belfast.

  • Limited stops / 90min journey time.

2) Thru-trains to Dublin.

  • End objective = 3hr 30mins journey time.

3) New multi-purpose ‘Foyle Parkway’ Station east of Derry.

  • Local rail station for Eglinton, Ballykelly, Strathfoyle etc.
  • Park & Rail.
  • City of Derry Airport.

4) Line Extensions to Strabane & Letterkenny. 5) Western Rail Corridor. 6) ‘The Derry Road’.

slide-12
SLIDE 12

Derry

Letterkenny Strabane Foyle Parkway

1 2 3

A North-West Rail Network ?

Ballykelly ?

slide-13
SLIDE 13

‘West On Track’

slide-14
SLIDE 14

DERRY P O R T R U S H LARNE ANTRIM B E L F A S T C I T Y 1 1 S t a t i

  • n

s BANGOR P O R T A D O W N BALLYMENA NEWRY L I S B U R N

Derry - Portadown Rail Route

C O L E R A I N E S T R A B A N E O M A G H D U N G A N N O N

slide-15
SLIDE 15

None of this can happen without… The Phase 3 Works.

1 2 3

slide-16
SLIDE 16

Our Ask of DC&SDC

1) Formally Push DFI for Phase 3 Prioritisation (start 2020). 2) Include ambitious role for rail in key Council strategies. 3) Work with colleagues in Donegal CC & Causeway Coast/Glens to lobby for enhanced rail provision in NW. 4) Take strategic view re preferred location of Phase 3 passing loop. 5) Work proactively with relevant councils to progress Western Rail Corridor & reinstallation of ‘The Derry Road’. 6) Push for new Stormont Rail Investment Strategy, with projects in NWCR included. 7) Secure funding for separate feasibility studies into extending rail to Strabane & Letterkenny.