Team 3: The Infiltrators Project Wrap-up Outline Intro - - PowerPoint PPT Presentation
Team 3: The Infiltrators Project Wrap-up Outline Intro - - PowerPoint PPT Presentation
Team 3: The Infiltrators Project Wrap-up Outline Intro Deliverables Team Members Plan Set Project Recap Computer Model Educational Tool Design Overview Conclusions Specifics Lessons
▪
Intro
▫
Team Members
▫
Project Recap
▪
Design
▫
Overview
▫
Specifics
▫
Details
▪
Deliverables
▫
Plan Set
▫
Computer Model
▫
Educational Tool
▪
Conclusions
▫
Lessons Learned
▫
Project Assessment
Outline
Intro Design Deliverables Conclusions
Elvin Vindel
The Team
Megan Daubenmier Steven Johnson Peter Wagenmaker
Project Recap
Team 03 has come alongside the Plaster Creek Stewards to design a robust stormwater management plan for Christ Church’s property, and to aid the overall effort to restore Plaster Creek.
phpd.online.co.uk
Intro Design Deliverables Conclusions
Concerns:
- Disrupted habitats downstream from:
- Significant erosion in ravine
- Frequent flashy flows
- High sediment levels
Cause:
- High volumes and velocities of parking
lot runoff exiting site through ravine
Design Overview
Intro Design Deliverables Conclusions
1. Treatment of runoff from parking lots via rain gardens. 2. Redirection of runoff from parking lots to existing detention pond. 3. Extension of pond flow path via bioswale and regrading. 4. Redesign of pond outlet structure.
Design Solutions
Intro Design Deliverables Conclusions
Size:
- South RG = 1455 SF
- North RG = 515 SF
Specifications:
- 12- inch max depth
- Weep hole drainage
- Cobble border
- Conform to existing flow path
- Cost 7-9 $/SF
Rain Gardens
Intro Design Deliverables Conclusions
Rain Garden Detail
- Currently, half the property is impervious and drains to the ravine.
- By rerouting the runoff of 0.86 ac of impervious surface to the
pond, flow velocities will be reduced and water quality improved.
Water Redirection
Intro Design Deliverables Conclusions
Source: Google
- Given the pipe redirection design, improvements to the detention
pond are necessary. A 100-foot bioswale of 0.50% slope is designed to extend the flow path in the pond.
Bioswale Flow Extension
Intro Design Deliverables Conclusions
Source: Soil Sciences of America
- Flow Path Extension: The detention pond ”short circuits” since
the outlet and inlet are 28 feet apart. A bioswale will extend this path to 200 feet to promote retention and infiltration.
Bioswale Flow Extension
Intro Design Deliverables Conclusions
Inlet – Outlet = 28 ft Inlet – Outlet = ~200 ft
- Pond Bottom Re-Grading: To accommodate the bioswale slope,
the pond will be excavated 3 inches and replanted with native plants to encourage infiltration.
Bioswale Flow Extension
Intro Design Deliverables Conclusions
16
Bioswale Flow Extension
- By city regulations, the current outlet does not have an appropriate
release rate. An 18-inch perforated riser was designed to release at the mandated 0.05 cfs/ac.
Outlet Structure
Intro Design Deliverables Conclusions
Existing: 6.5” Exposed Outlet PVC Pipe
Plan Set
Intro Design Deliverables Conclusions
Plan Set
Intro Design Deliverables Conclusions
EPA SWMM Model
Intro Design Deliverables Conclusions
EPA SWMM Model
Intro Design Deliverables Conclusions
Educational Model
Intro Design Deliverables Conclusions
▪ EPA SWMM model validation ▪ Lack of experience in creating a
complete construction plan set.
▪ Late and incomplete topo survey ▪ Communication between industrial
consultant and objectives
▪ Financial analysis (esp. construction)
Obstacles
Intro Design Deliverables Conclusions
Source: viewstorm.com
▪ Completion of a complete sheetset
to be revised and delivered for approval to MDEQ.
▪ Working hydrologic model of the
site with proposed changes.
▪ Educational tool for PCS.
Project Deliverables
Intro Design Deliverables Conclusions
▪ Importance of project definition ▪ Teamwork and time management ▪ Communication ▪ Responsible decision-making
Lessons Learned
Intro Design Deliverables Conclusions
Source: slidescarnival.com
Acknowledgements
- Julie Wildschut, P.E. (Plaster Creek Stewards)
- Ralph Reznick (MDEQ)
- Scott Gritter (Christ Church Liaison)
- Leonard De Rooy, P.E. (Team Advisor)
- Exxel Engineering (Topographical Survey)
- Lon Tiffany (Dan Vos Construction Company)
- Robert Hoeksema (Engineering Faculty)