Northern Line Extension Kennington Park Community Liaison Group 10 10 2016 Kennington Park: July - Oct 2016 Finished Temporary Acoustic Shed Excavated Full Depth of Shaft Excavated Tunnel to Kennington Loop Commenced Pilot


  1. Northern Line Extension Kennington Park Community Liaison Group 10 10 2016

  2. Kennington Park: July - Oct 2016 • Finished Temporary Acoustic Shed • Excavated Full Depth of Shaft • Excavated Tunnel to Kennington Loop • Commenced Pilot Tunnel Alongside Kennington Loop 2

  3. Kennington Park – July - Oct 2016 Update on Tunnelling Progress 3

  4. Kennington Park - SCL Tunnel Excavation 4

  5. KP Look Ahead – SCL Tunnel Sprayed Face 5

  6. Kennington Park Look Ahead – Oct 2016 – Jan 2017 • Completion of Pilot Tunnel • Commencement of Step Plate Junction Works 6

  7. Step Plate Junction – Update 7

  8. Step Plate Junction – Update 8

  9. Environmental Monitoring June to August 2016 Noise Levels 8 night time exceedances – attributed to road noise (ambulances, motor bikes etc) No noise exceedances attributed to the NLE works were recorded 9

  10. Environmental Monitoring June to August 2016 10

  11. Your Feedback You Suggested We Did Fencing at Kennington had The anti-climb paint was quickly cleaned away by FLO and the fence line been contaminated with was repositioned so as to block the opening in the fence, making it safer for grease everyone. Neighbours expressed their thanks. Provided visual and audio presentation at CLG’s and Drop In Sessions. Last More information and engagement about works one at Kennington Park 28 September Dust and noise mitigation Jet Spray equipment moved and noise mitigated where possible. Extra acoustic blankets have been installed on site. Redirection of the dust extractor at Kennington Park. Light pollution from Affected residents where visited and lights have been redirected and Kennington Sites shielded where possible. Liaison with new TfL representative attended meeting and contact established. Kennington Park Road Resident’s Association. Recording studio sensitive Management was advised in advance of predictive tunnelling activity so they to SPJ tunnelling could organise work around the studio times. Owner appreciated the liaison and thanked for the heads up. 11

  12. Kennington Park Working Hours • Excavation of the shaft and tunnels continues to be 24/7 • Core hours are 08:00 to 18:00 Monday to Friday and Saturday 08:00 to 13:00 for surface works. • NLE have applied for an extension of delivery times during the weekends. This application has been accepted by Lambeth, however no use of extended deliveries is planned, except due to unforeseen circumstances, to provide services to the 24/7 underground operations. • NLE continue to monitor works to ensure Best Practicable Means are being used. • Some sub-surface work may be heard in properties directly above it. NLE will endeavour to minimise any possible night time disturbance to acceptable hours. 12

  13. NLE Engagement Opportunities • CLG meetings • One to one meetings • Drop in sessions • School and Youth Engagement • Stakeholder Activities • LEAP group meetings • Cycling safety Events 13

  14. Ways to contact us • It is important that calls are logged through the NLE 24/7 helpdesk on 0343 222 2424 (Option 1) • Email nle@tfl.gov.uk • Drop In sessions • Please visit: https://tfl.gov.uk/northern-line-extension 14

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.