Northern Line Extension Kennington Park Community Liaison Group 10 10 2016 Kennington Park: July - Oct 2016 Finished Temporary Acoustic Shed Excavated Full Depth of Shaft Excavated Tunnel to Kennington Loop Commenced Pilot
2
Kennington Park: July - Oct 2016
- Finished Temporary Acoustic
Shed
- Excavated Full Depth of Shaft
- Excavated Tunnel to
Kennington Loop
- Commenced Pilot Tunnel
Alongside Kennington Loop
3
Kennington Park – July - Oct 2016 Update on Tunnelling Progress
4
Kennington Park - SCL Tunnel Excavation
5
KP Look Ahead – SCL Tunnel Sprayed Face
6
Kennington Park Look Ahead – Oct 2016 – Jan 2017
- Completion of Pilot Tunnel
- Commencement of Step
Plate Junction Works
7
Step Plate Junction – Update
8
Step Plate Junction – Update
9
Environmental Monitoring
June to August 2016
Noise Levels 8 night time exceedances – attributed to road noise (ambulances, motor bikes etc) No noise exceedances attributed to the NLE works were recorded
10
Environmental Monitoring
June to August 2016
11
Your Feedback
You Suggested We Did
Fencing at Kennington had been contaminated with grease The anti-climb paint was quickly cleaned away by FLO and the fence line was repositioned so as to block the opening in the fence, making it safer for
- everyone. Neighbours expressed their thanks.
More information and engagement about works Provided visual and audio presentation at CLG’s and Drop In Sessions. Last
- ne at Kennington Park 28 September
Dust and noise mitigation Jet Spray equipment moved and noise mitigated where possible. Extra acoustic blankets have been installed on site. Redirection of the dust extractor at Kennington Park. Light pollution from Kennington Sites Affected residents where visited and lights have been redirected and shielded where possible. Liaison with new Kennington Park Road Resident’s Association. TfL representative attended meeting and contact established. Recording studio sensitive to SPJ tunnelling Management was advised in advance of predictive tunnelling activity so they could organise work around the studio times. Owner appreciated the liaison and thanked for the heads up.
12
Kennington Park Working Hours
- Excavation of the shaft and tunnels continues to be 24/7
- Core hours are 08:00 to 18:00 Monday to Friday and
Saturday 08:00 to 13:00 for surface works.
- NLE have applied for an extension of delivery times during the
- weekends. This application has been accepted by Lambeth,
however no use of extended deliveries is planned, except due to unforeseen circumstances, to provide services to the 24/7 underground operations.
- NLE continue to monitor works to ensure Best Practicable Means
are being used.
- Some sub-surface work may be heard in properties directly above
- it. NLE will endeavour to minimise any possible night time
disturbance to acceptable hours.
13
NLE Engagement Opportunities
- CLG meetings
- One to one meetings
- Drop in sessions
- School and Youth
Engagement
- Stakeholder Activities
- LEAP group meetings
- Cycling safety Events
14
Ways to contact us
- It is important that calls are logged through
the NLE 24/7 helpdesk on 0343 222 2424 (Option 1)