kennington park
play

Kennington Park Community Liaison Group 25 July 2019 1 Kennington - PowerPoint PPT Presentation

Northern Line Extension Kennington Park Community Liaison Group 25 July 2019 1 Kennington Park May to July 2 Kennington Park July to October 3 Kennington Park Works Timeline Activity Start Date End Date Construction of basement


  1. Northern Line Extension Kennington Park Community Liaison Group 25 July 2019 1

  2. Kennington Park – May to July 2

  3. Kennington Park – July to October 3

  4. Kennington Park – Works Timeline Activity Start Date End Date Construction of basement – roof, walls, staircases – additional time required due to sequencing of works May 2018 July 2019 Kennington Park Headhouse – Above Ground Structure additional time required due to sequencing of works – does not January 2019 July 2019 affect overall completion Kennington Park Headhouse - Brickwork Facade August 2019 November 2019 Excavation around perimeter of basement to enable August 2019 Sept 2019 waterproofing to be installed. Utility works scheduled to take place at the on Kennington Park Place and St Agnes Place – date change to align with UKPN and Sept 2019 October 2019 Thames Water works – provisional Mechanical & Electrical Installation of equipment inside the headhouse structure February 2019 Spring 2020 Hard and Soft Landscaping Kennington Green – removal of Commencement early Spring - Summer 2020 remaining foundations and concrete surface from site, removal of hoardings etc Actual planting dates will be reviewed with our specialist suppliers 4

  5. Kennington Park – Site Deliveries • We continue to Work Related Road Risk (WRRR) driver training awareness for vulnerable road users, IE cyclists. • 100% WRRR compliance is being maintained. • Once abnormal deliveries have been authorised by the metropolitan police we alert the residents under section 61 explaining the reasons for either working early/late. In addition, there are no planned abnormal loads at present. • Montford Place continues to be the holding area for deliveries for Ken Park and Ken Green sites • July to October will be mainly lorries with pipework, ducting, electrical and mechanical equipment & light plant delivery lorries, visiting cranes will be required. • Approx. 5-6 deliveries per day. 5

  6. Environmental Monitoring Locations Monitoring stations and sensitive receptors 6

  7. Noise Monitoring; Daytime 10Hr Avg 7

  8. Noise Monitoring; Daytime 10Hr Avg 8

  9. Dust Monitoring – Glass Slides 9

  10. Air Quality Dust slides results 10 10 10

  11. Complaints and enquiries summary Stats for Kennington Park between 25 April and 24 July 2019 Case Status: Total: 4 cases Active: 0 (0%) Resolved: 2 (100%) Case Type: Total: 4 cases TfL enquiry: 2 (50%) Enquiry: 1 (25%) Complaint 1 (25%) 11

  12. Community Engagement and NLE Skills and Employment Site tours at Battersea: 60 students from St Thomas the Apostle (Southwark) 70 students from Scared Heart (Southwark) School engagement events: Air pollution workshop - Sacred Heart (Southwark - pic) Engineering talk – St George’s Primary (Wandsworth) Women in STEM – Harris 6th form (Westminster) Careers networking – Graveney School (Wandsworth) 12

  13. Ways to contact • It is important that calls are logged through the NLE helpdesk on 0343 222 2424 (Option 1) • Email nle@tfl.gov.uk • Drop In sessions • Please visit: https://tfl.gov.uk/northern-line-extension 13 13

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend