schnabel-eng.com
Sweetheart Dam Access Challenges and Design Considerations Duff - - PowerPoint PPT Presentation
Sweetheart Dam Access Challenges and Design Considerations Duff - - PowerPoint PPT Presentation
Sweetheart Dam Access Challenges and Design Considerations Duff Mitchell Juneau Hydropower Inc. Tom Fitzgerald Schnabel Engineering September 21, 2017 schnabel-eng.com Agenda Project Summary and Timeline Permitting Status
SLIDE 1
SLIDE 2
Agenda
Project Summary and
Timeline
Permitting Status Project Challenges Design Concepts Recent Investigations
SLIDE 3
Sweetheart Creek first prospected by Frank Cook, discoverer of the Jualin Mine
1906 Sweetheart Lake first identified as a hydro resource
1915 to 1927 USGS gauged Sweetheart Creek
1929 Project selected by US Government as a Federal Power Site Classification Site in Public Land Order 221 May 14, 1929.
1952 Interior Secretary reports to Congress on Sweetheart Lake
1958 USGS Plan for Damsite
1983 Alaska Power Authority Plan
1983 Environmental Impact Assessment for Gilbert Bay
2009 FERC Permit filed-development and studies commenced
2014 FERC License Filed
2015 October EIS and License Process
2016 Final EIS issued-May 31, 2016
2016 FERC License issued-September 8, 2016
2016 Army Corps of Engineers 404 Permit issued
2017 ADNR Tideland Lease Permit and Easement issued
2017 ADNR Water Rights issued
Sweetheart Lake Timeline
SLIDE 4
SLIDE 5
SLIDE 6
SLIDE 7
Project Features
Dam Powerhouse
SLIDE 8
Dam Location
Gilbert Bay Proposed Dam Site Tunnel Alignment
SLIDE 9
Lower Sweetheart Lake
SLIDE 10
Powerhouse Location
Powerhouse Site Gilbert Bay
SLIDE 11
Gilbert Bay
SLIDE 12
Gilbert Bay
SLIDE 13
Gilbert Bay
SLIDE 14
Sweetheart Falls
SLIDE 15
Alaska Considerations
Average High Temp = 48.1 Average Low Temp = 36.2 Precip Avg. Inches per Year = 62 Snow Avg. Inches per Year = 88 Construction Season
Dam Site – June to October Powerhouse – May to November
- From U.S. Climate Data – Juneau Alaska
SLIDE 16
Remote Site
SLIDE 17
Steep Topography
SLIDE 18
Tongass National Forest Roadless Rules
No permanent or temporary
access roads to the dam site
No disturbance until the
project was permitted.
SLIDE 19
Geology
Site Regional Lineaments Site Area Lineaments Generally consistent with Foliation and Joint Set #1
SLIDE 20
Dam Foundation – Right Abutment Area
Stop D-04 Biotite Schist and Quartzite Shear zone at Stop D-04 Stop D-20 - Laminated Quartzite
SLIDE 21
Implications for Project
Strong Rock Suitable for Dam and
Powerhouse Foundations and Tunneling
Geologic Hazards can be Mitigated:
Sedimentation, slope stability seismicity
Multiple Sources of Rock Borrow Material Favorable Orientations of Compositional
Layering and Joints
Rock Observed does not Appear Heavily
Faulted or Sheared
SLIDE 22
Engineering Considerations - Seismicity
Peak Horizontal Ground Acceleration
(PHGA) value used for preliminary design.
Return Period (years) Ground Motion (g) 500 0.073 1,000 0.094 2,500 0.124 5,000 0.148 10,000 0.177
SLIDE 23
Deaggregation Plot
SLIDE 24
Engineering Considerations - Spillway
Drainage area of 35 square miles Surface area of Lower Sweetheart
Existing – 1,200 acres Proposed - 1,700 acres
100-year inflow 14,000 cfs PMF Inflow about 39,000 CFS Overflow spillway 125 feet wide at El.
636.0 (~76 feet above existing)
SLIDE 25
Engineering Considerations - Spillway
PMF outflow of 20,300 cfs with 14.1 feet
- f head
100-year outflow 7,000 cfs with 7.4 feet
- f head
SLIDE 26
Construction Considerations -Diversion
Fair data set Seasonal flow Low flows in winter, high
flow in spring and summer.
Not unusual to see
peaks 1,000 to 1,200 cfs
Construction duration –
1 or 2 seasons?
Concrete dam Need for Low-Level
Outlet
SLIDE 27
Conceptual Dam Type Selection
SLIDE 28
Dam Type Considerations
Spillway needs Site geometry and dam footprint Foundation conditions Construction duration Weather dependencies Access issues and equipment needs
SLIDE 29
Benefits of RCC Gravity Dam
Simple, robust design that is
adaptable to the terrain.
Less risk related to
foundation parameters.
Can be built quickly (in one
season).
Long term durability and
performance.
Can accommodate spillway
needs.
SLIDE 30
RCC Considerations
Aggregate source Mix design Foundation
Treatment
Batching and
Conveying
Equipment Placement Penetrations Facing system
SLIDE 31
SLIDE 32
SLIDE 33
SLIDE 34
SLIDE 35
SLIDE 36
SLIDE 37
Recent Investigations
SLIDE 38
SLIDE 39
SLIDE 40
SLIDE 41
SLIDE 42
SLIDE 43