Sweetheart Dam Access Challenges and Design Considerations Duff - - PowerPoint PPT Presentation

sweetheart dam access challenges and design considerations
SMART_READER_LITE
LIVE PREVIEW

Sweetheart Dam Access Challenges and Design Considerations Duff - - PowerPoint PPT Presentation

Sweetheart Dam Access Challenges and Design Considerations Duff Mitchell Juneau Hydropower Inc. Tom Fitzgerald Schnabel Engineering September 21, 2017 schnabel-eng.com Agenda Project Summary and Timeline Permitting Status


slide-1
SLIDE 1

schnabel-eng.com

Sweetheart Dam Access Challenges and Design Considerations

Duff Mitchell – Juneau Hydropower Inc. Tom Fitzgerald – Schnabel Engineering

September 21, 2017

slide-2
SLIDE 2

Agenda

 Project Summary and

Timeline

 Permitting Status  Project Challenges  Design Concepts  Recent Investigations

slide-3
SLIDE 3

Sweetheart Creek first prospected by Frank Cook, discoverer of the Jualin Mine

1906 Sweetheart Lake first identified as a hydro resource

1915 to 1927 USGS gauged Sweetheart Creek

1929 Project selected by US Government as a Federal Power Site Classification Site in Public Land Order 221 May 14, 1929.

1952 Interior Secretary reports to Congress on Sweetheart Lake

1958 USGS Plan for Damsite

1983 Alaska Power Authority Plan

1983 Environmental Impact Assessment for Gilbert Bay

2009 FERC Permit filed-development and studies commenced

2014 FERC License Filed

2015 October EIS and License Process

2016 Final EIS issued-May 31, 2016

2016 FERC License issued-September 8, 2016

2016 Army Corps of Engineers 404 Permit issued

2017 ADNR Tideland Lease Permit and Easement issued

2017 ADNR Water Rights issued

Sweetheart Lake Timeline

slide-4
SLIDE 4
slide-5
SLIDE 5
slide-6
SLIDE 6
slide-7
SLIDE 7

Project Features

Dam Powerhouse

slide-8
SLIDE 8

Dam Location

Gilbert Bay Proposed Dam Site Tunnel Alignment

slide-9
SLIDE 9

Lower Sweetheart Lake

slide-10
SLIDE 10

Powerhouse Location

Powerhouse Site Gilbert Bay

slide-11
SLIDE 11

Gilbert Bay

slide-12
SLIDE 12

Gilbert Bay

slide-13
SLIDE 13

Gilbert Bay

slide-14
SLIDE 14

Sweetheart Falls

slide-15
SLIDE 15

Alaska Considerations

 Average High Temp = 48.1  Average Low Temp = 36.2  Precip Avg. Inches per Year = 62  Snow Avg. Inches per Year = 88  Construction Season

 Dam Site – June to October  Powerhouse – May to November

  • From U.S. Climate Data – Juneau Alaska
slide-16
SLIDE 16

Remote Site

slide-17
SLIDE 17

Steep Topography

slide-18
SLIDE 18

Tongass National Forest Roadless Rules

 No permanent or temporary

access roads to the dam site

 No disturbance until the

project was permitted.

slide-19
SLIDE 19

Geology

Site Regional Lineaments Site Area Lineaments Generally consistent with Foliation and Joint Set #1

slide-20
SLIDE 20

Dam Foundation – Right Abutment Area

Stop D-04 Biotite Schist and Quartzite Shear zone at Stop D-04 Stop D-20 - Laminated Quartzite

slide-21
SLIDE 21

Implications for Project

 Strong Rock Suitable for Dam and

Powerhouse Foundations and Tunneling

 Geologic Hazards can be Mitigated:

 Sedimentation,  slope stability  seismicity

 Multiple Sources of Rock Borrow Material  Favorable Orientations of Compositional

Layering and Joints

 Rock Observed does not Appear Heavily

Faulted or Sheared

slide-22
SLIDE 22

Engineering Considerations - Seismicity

 Peak Horizontal Ground Acceleration

(PHGA) value used for preliminary design.

Return Period (years) Ground Motion (g) 500 0.073 1,000 0.094 2,500 0.124 5,000 0.148 10,000 0.177

slide-23
SLIDE 23

Deaggregation Plot

slide-24
SLIDE 24

Engineering Considerations - Spillway

 Drainage area of 35 square miles  Surface area of Lower Sweetheart

 Existing – 1,200 acres  Proposed - 1,700 acres

 100-year inflow 14,000 cfs  PMF Inflow about 39,000 CFS  Overflow spillway 125 feet wide at El.

636.0 (~76 feet above existing)

slide-25
SLIDE 25

Engineering Considerations - Spillway

 PMF outflow of 20,300 cfs with 14.1 feet

  • f head

 100-year outflow 7,000 cfs with 7.4 feet

  • f head
slide-26
SLIDE 26

Construction Considerations -Diversion

 Fair data set  Seasonal flow  Low flows in winter, high

flow in spring and summer.

 Not unusual to see

peaks 1,000 to 1,200 cfs

 Construction duration –

1 or 2 seasons?

 Concrete dam  Need for Low-Level

Outlet

slide-27
SLIDE 27

Conceptual Dam Type Selection

slide-28
SLIDE 28

Dam Type Considerations

 Spillway needs  Site geometry and dam footprint  Foundation conditions  Construction duration  Weather dependencies  Access issues and equipment needs

slide-29
SLIDE 29

Benefits of RCC Gravity Dam

 Simple, robust design that is

adaptable to the terrain.

 Less risk related to

foundation parameters.

 Can be built quickly (in one

season).

 Long term durability and

performance.

 Can accommodate spillway

needs.

slide-30
SLIDE 30

RCC Considerations

 Aggregate source  Mix design  Foundation

Treatment

 Batching and

Conveying

 Equipment  Placement  Penetrations  Facing system

slide-31
SLIDE 31
slide-32
SLIDE 32
slide-33
SLIDE 33
slide-34
SLIDE 34
slide-35
SLIDE 35
slide-36
SLIDE 36
slide-37
SLIDE 37

Recent Investigations

slide-38
SLIDE 38
slide-39
SLIDE 39
slide-40
SLIDE 40
slide-41
SLIDE 41
slide-42
SLIDE 42
slide-43
SLIDE 43

Questions?