Public Involvement Plan and Why Are We Here? Open House Goals : - - PowerPoint PPT Presentation

public involvement plan and
SMART_READER_LITE
LIVE PREVIEW

Public Involvement Plan and Why Are We Here? Open House Goals : - - PowerPoint PPT Presentation

Public Involvement Plan and Why Are We Here? Open House Goals : Raise awareness of project Report feedback from March 27 meeting, answer questions and get more feedback Demonstrate Next Open House: transparency in our Late


slide-1
SLIDE 1
slide-2
SLIDE 2

Open House Goals:

  • Raise awareness of

project

  • Report feedback from

March 27 meeting, answer questions and get more feedback

  • Demonstrate

transparency in our process

Public Involvement Plan and…

Why Are We Here? Next Open House: Late Summer-TBD

slide-3
SLIDE 3
  • Replace the bridge,

improving safety and service

  • Widen sidewalks on

the bridge

  • Provide Bicycle/

Pedestrian connection between Graehl Park and Griffin Park

Project Goals

slide-4
SLIDE 4

State Funded: GO Bond approved by voters in November 2012

Estimated Cost: $14-17 Million

slide-5
SLIDE 5

Estimated Schedule – Construction

Expect bridge to be closed for duration of construction

slide-6
SLIDE 6
  • 1. From March 27 Open House:
  • Feedback received for Bicycle/Pedestrian Connection concept
  • Selection and Reasoning
  • 2. Present selected bridge type
  • 3. Receive feedback on bridge rail and bridge lighting
  • ptions

 Return for another Open House Meeting late summer 2013

Focus of this Open House Meeting

slide-7
SLIDE 7

Fun Fact for May 8

slide-8
SLIDE 8

We Asked You:

Access Connection to the Bridge: Direct or Underpass?

slide-9
SLIDE 9

Direct Connection on Northeast Corner

w ith a New Path on Southeast Corner (Question 2)

North

slide-10
SLIDE 10

Underpass Below the North End of Bridge

(Question 3, 4, 5)

North

slide-11
SLIDE 11

Thank You for Your Comments!

  • We received 22 written responses … Thanks!
  • 67% of responses indicated either path connection

would be used at least occasionally

  • 64% indicated a tolerance toward path flooding
  • Majority of responses indicated that both connections

were either important or very important …

slide-12
SLIDE 12

Which connection option is more important?

No Clear Favorite … … we relied on what you said in your written comments

Direct vs. Underpass

6 10 6

Direct Equal Underpass

Indicated Relative Importance

slide-13
SLIDE 13

Those who favored a Direct Connection:

  • Were concerned about public safety of an underpass

pathway, and wanted to avoid encounters under the bridge

  • Had a lower tolerance toward path flooding
  • Perceived lower maintenance costs

Direct vs. Underpass

slide-14
SLIDE 14

Those who favored an Underpass Connection:

  • Liked the idea of crossing the roadway under the

bridge

  • Pointed out it would provide access to more bus

stops

  • Liked the convenience of access to the river
  • Were concerned about private property impacts

Direct vs. Underpass

slide-15
SLIDE 15
  • Handouts available after presentation
  • On the website, see:
  • All of the comments that we received
  • Our analysis and conclusions …
  • How we decided which option to pursue …

… based on your comments Where to find more in-depth information?

slide-16
SLIDE 16
  • Connects users with

more origins and destinations

  • More available space
  • Public safety concerns

can be addressed …

Our Selection: Underpass

slide-17
SLIDE 17
  • Brush clearing and land contouring
  • Opens the area below the bridge and makes it

more visible from surrounding vantage points

  • Path lighting under the bridge
  • Reduce dark, shadowy areas

Mitigating Public Safety Concerns

slide-18
SLIDE 18
  • Vertical wall abutments
  • Makes hiding spaces inaccessible
  • Reduces bridge length and bridge cost
  • Offset the path from the wall
  • Provides a more inviting open space
  • Riprap between wall and path
  • Deters congregation in the area

Mitigating Public Safety Concerns

slide-19
SLIDE 19

Bridge Abutments

“Spill Through” Sloped Abutment Vertical Wall Abutment (examples of areas under the bridge ends)

slide-20
SLIDE 20
  • Durable
  • Consistent with other

new bridge types

  • Manufactured in Alaska
  • Lowest cost option

Bridge Type:

Concrete Bulb-Tee Girder Bridge

Barnette Street Bridge

slide-21
SLIDE 21
  • Safety criteria: must be crash tested
  • Rail height requirements for pedestrians

Question 1: Bridge Rail Options

slide-22
SLIDE 22

Bridge Rail Options

Option 1- Two-tube on Concrete

Barnette Street Bridge

slide-23
SLIDE 23

Bridge Rail Options

Option 2- Three Tube “Curtain” Rail

slide-24
SLIDE 24

Bridge Rail Options

Option 3- Three Tube Rail on Curb

slide-25
SLIDE 25
  • Must meet highway lighting requirements
  • Examples are shown, exact styles may vary

Question 2: Bridge Lighting Options

slide-26
SLIDE 26

Bridge Lighting Options

Option 1- Modern Luminaire

slide-27
SLIDE 27

Bridge Lighting Options

Option 2- Braced Mast Arm

slide-28
SLIDE 28

Bridge Lighting Options

Option 3- Griffin Park Style Lighting

slide-29
SLIDE 29
  • Please take a closer look at our graphics and fill out a

comment sheet

  • Next meeting late summer, Morris Thompson—stay tuned!
  • For more information, please visit our website at:

dot.alaska.gov/nreg/wendell

  • ADOT&PF Contact:
  • Email: sarah.schacher@alaska.gov
  • Phone: (907) 451-5361

Thank You For Your Time!