Montana Department of Transportation Russell Street Broadway to Dakota Update City Council Chambers Wednesday, November 14 at 2:30 p.m. 1 Russell Street Bridge Design Russell Street Bridge rendering looking north 2 3 4 Russell Street


slide-1
SLIDE 1

Montana Department of Transportation Russell Street – Broadway to Dakota Update City Council Chambers Wednesday, November 14 at 2:30 p.m.

1

slide-2
SLIDE 2

Russell Street Bridge Design

Russell Street Bridge rendering looking north

2

slide-3
SLIDE 3

3

slide-4
SLIDE 4

4

slide-5
SLIDE 5

Russell Street Bridge rendering looking north

5

slide-6
SLIDE 6

Milwaukee Trail underpass rendering looking east

6

slide-7
SLIDE 7

7

slide-8
SLIDE 8

Open House held at the Salvation Army with more than 300 in attendance. March 14, 2018

8

slide-9
SLIDE 9

Knife River begins shoring operations for the new Russell Street Bridge April 2018

9

slide-10
SLIDE 10

Roadway excavation efforts in full swing April 2018

10

slide-11
SLIDE 11

Utility work near Idaho Street May 2018

11

slide-12
SLIDE 12

Construction update with local elected

  • fficials

May 2018

12

slide-13
SLIDE 13

Footing for retaining wall near Missoula Car and Truck May 2018

13

slide-14
SLIDE 14

Temporary work bridge erected and

  • perational

June 2018

14

slide-15
SLIDE 15

South bridge abutment formwork June 2018

15

slide-16
SLIDE 16

Milwaukee Trail pedestrian underpass construction July 2018

16

slide-17
SLIDE 17

17

slide-18
SLIDE 18

Sidewalk construction and median work begins September 2018

18

slide-19
SLIDE 19

Milwaukee Trail construction on the west side of Russell Street October 2018

19

slide-20
SLIDE 20

Girder installation on Russell Street Bridge November 2018

20

slide-21
SLIDE 21

Broadway to Dakota

21

slide-22
SLIDE 22

What’s Next?

22

Idaho Street to Mount Street

slide-23
SLIDE 23

Future Phases

23

Agreement Update to Long Range Transportation Plan (LRT) & Transportation Improvement Plan (TIP) Engineering & Design Purchase Remaining Right-of-Way Permitting Advertise & Let Project

slide-24
SLIDE 24

Questions?

24