rehabilitation of the bay of quinte skyway highway 49
play

Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 April 5, 2018 Presentation Agenda PART A Bay of Quinte Skyway Bridge Rehabilitation (Site No. 11-245) PART B Highway 49 and Old

0 downloads 6 Views 2,43 MB Size Report
  1. Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 April 5, 2018

  2. Presentation Agenda  PART A  Bay of Quinte Skyway Bridge Rehabilitation (Site No. 11-245)  PART B  Highway 49 and Old Highway 2/ York Road Intersection

  3. Project Location Highway 49 / Old Highway 2 Intersection Airport Rd

  4. PART A: Bay of Quinte Skyway Project Location (Site 11-245 ) AIRPORT ROAD BAY OF QUINTE NORTHPORT ROAD SKYWAY (SITE #11-245) COUNTY ROAD 49 BAY OF QUINTE

  5. Historical Photo - 1966

  6. Existing Bridge Configuration

  7. Background Bay of Quinte Skyway Bridge, Highway 49  Constructed 1964-1967  17 span high level bridge, 847 m long  Carries 2 lanes on N-S oriented traffic  Steel girders, concrete deck  5 continuous spans, 6 expansion joints  1992-dual columns replaced with single shaft at 3 piers

  8. Existing Condition Deck:  Extensively deteriorated (corrosion)  Substandard barrier walls  Substandard lane width Girders:  Many fatigue prone details  general coating failure Substructure:  Generally sound except Pier 14 (beneath EJ)  Minor scour at Pier 13 footing  Abutments cannot accommodate widening

  9. Bridge Rehabilitation Work  Replace superstructure  Reconstruct abutments, including new caissons, new wingwalls  Replace bridge bearings/alter bridge articulation  Eliminate expansion joints over piers  Rehabilitate and strengthen piers  New approach slabs  Reconstruct highway approaches to the bridge  Illumination

  10. Rehabilitated Bridge Configuration  Continuous deck – no expansion joints over piers  Road profile – same as existing

  11. New Superstructure  225 mm thick concrete slab  TL-5 walls  4 steel girders  11.55 m wide deck  Two 3.75 m traffic lanes  Two 1.5 m wide side clearances  90 mm asphalt and waterproofing  2% crossfall

  12. Construction Overview  New superstructure with Superstructure Replacement Scheme 4 steel girders  5 segments, replace 1 segment per year  ‘Half-and-half’ staged construction with a single-lane of bi-directional traffic on the bridge controlled by temp. traffic signals for each Segment.  All lanes available during seasonal shutdown

  13. Expansion Joint (EJ) Replacement  Full closure required for modular expansion joint installation . Legend: Eliminate existing EJ Replace EJ and ramp over Temporary EJ required

  14. Construction Sequence Year Segment Major Work 1 - Advance work 2 C Replace segment 3 B Replace segment 4 D Replace segment 5 E Replace segment & Reconstruct abutment 6 A Replace segment & Reconstruct abutment 7 A Install EJ

  15. Duration & Sequencing (1) 2018 (Year 1)  Prepare site; procure structural steel for Segment C  Structural steel repair (CIF) girders in west half of Segment C;  Rehabilitate pier caps at Piers 8 and 11  Part B (Highway 49 / Old Highway 2 / York Rd. intersection) 2019 (Year 2)  Replace Segment C superstructure  Rehabilitate pier caps at Piers 5,6 and 7 to accommodate 2020 construction;  Structural steel repair (CIF) girders in west half of Segment B  Install traffic signals to accommodate 2020 construction 2020 (Year 3)  Replace Segment B superstructure  Rehabilitate pier cap at Pier 14 to accommodate 2021 construction;  Structural steel repair (CIF) girders in west half of Segment D  Install traffic signals to accommodate 2021 construction

  16. Duration & Sequencing (2) 2021 (Year 4)  Replace Segment D superstructure  Structural steel repair (CIF) girders in west half of Segment E  Install traffic signals to accommodate 2022 construction 2022 (Year 5)  Replace Segment E superstructure  Reconstruct south abutment and install modular type of expansion joint  Rehabilitate pier caps at Piers 3 and 4  Structural steel repair (CIF) girders in west half of Segment A  Install traffic signals for Segment A 2023 (Year 6)  Replace Segment A superstructure and Reconstruct north abutment  Install and maintain temporary ramp over expansion joint opening 2024 (Year 7)  Install Modular Expansion Joint in Segment A  Demolish Old Band Building

  17. Construction Duration and Sequencing (3)

  18. Construction Staging Year 2 – 2019 – Segment C Year 3 – 2020 – Segment B Year 4 – 2021 – Segment D 2019 Year 5 – 2022 – Segment E Year 6 – 2023 – Segment A 2020 2021 2022 2023

  19. Seasonal Shutdown  Seasonal shutdown each year, all traffic lanes available  Work below the bridge deck is permitted; no traffic disruption  Work on Highway 49 affecting traffic or requiring lane closures not permitted

  20. Traffic Management: Full Mainline Closures of Hwy 49 Type of Full Closure Description Short Duration Full Closures o 30 minutes during night hours (9 p.m. – 6 a.m.) o Unlimited number Extended Duration Full o ½ - 2 hours during night hours (9 p.m. – 6 a.m.) Closures o Maximum 52 occurrences Full Night Closures o 9 p.m. – 6 a.m. o Police required o Maximum of 45 occurrences  No full closures permitted in 2018  Advance notification required  Penalties for late opening

  21. Traffic Management: Full Mainline Closures of County Rd 35 Type of Full Description Closure Extended Duration o ½ - 2 hours during night (9 p.m. – 6 a.m.) o Police required o 5 occurrences  Passage for emergency vehicles shall be readily available at all times

  22. Restrictions on Crane Placement  No heavy equipment or cranes on any section of existing bridge in a 2 girder configuration

  23. Snow Removal  Contractor responsible for snow and ice removal within work area  Remove within 3 hours of a snowfall event  Dispose at appropriate dump site  Snow removal plan each year  Snow removal against barrier by AMC, vacate work area

  24. Utilities  Bell and Hydro plant traverse Hwy 49 north of CR 35  Union Gas plant crosses beneath BOQ on west side of bridge  Portions of abandoned Union Gas main may be present within the existing highway embankment near each end of BOQ Skyway Bridge

  25. MBQ Fishing Rights  Area between piers 10 and 12 to remain accessible for MBQ to exercise fishing rights during July and August each year  Exception: only when construction work is performed between the piers  Advise intention to restrict access prior to May 15

  26. Abutment Reconstruction  Reconstruction of abutments & wingwalls  Staged construction  Four - 1200 mm diameter caissons with steel liners at each abutment  South abutment and caissons – Year 5  North abutment and caissons – Year 6

  27. Navigation

  28. Environmental Issues  Navigable waters permit  Noise By Law exemption (must be renewed)  Archaeological clearance  Aeronautical lighting  SARS  Fisheries timing restrictions  Spills Prevention

  29. Environmental Constraints Environmental Specifics Species at Risk observed Yes o At least 9 species o o Exclusionary Fencing to be installed prior to April 15 of 1 st year of construction Blanding’s Turtle Barn Swallow Netting required o Breeding season timing window: March 31 - August 27 o Qualified Avian specialist required to screen for breeding migratory birds o Tree Removal Prohibited between March 31 and August 27 o Within window – Qualified Avian Biologist to conduct a nesting survey o Timing window for Barge For Segment C – No activity permitted between April 1 and May 20, 2019 o Operations For Segment D – No activity permitted between April 1 and May 17, 2021 o No sediment plumes o Timing window for all other in July 1 to September 15 o water work

  30. Existing Water Intakes

  31. Spill Prevention and Response Contingency  Submit Plan for all activities within 30 m of watercourse  Barge, equipment and other operations shall be at least 50 m away from shore wells and municipal water intakes  Provide worker training  Review Plan annually

  32. Police Jurisdictions Area Police Service to be Contacted Tyendinaga Mohawk Territory Tyendinaga Police Service Prince Edward County Ontario Provincial Police

  33. PART B Highway 49 and Old Highway 2/ York Road Intersection

  34. Highway 49 and Old Highway 2  Location:  Intersection of Highway 49 and Old Highway 2/York Road  Scope:  Removal is existing NB channelized right turn  Adjustment to existing traffic signal poles  Ditching to ensure positive drainage to existing ditch  Benefit:  Improves safety for vehicles entering or leaving trading post, gas station

  35. Highway 49 and Old Highway 2  Contract details:  To be completed in Year one of Contract prior to October 31, 2018  Access to entrances to remain open  Traffic permitted to travel on granular grade  No open granular permitted on weekends

  36. Summary  Construction Start: Spring 2018  Late season work anticipated  All Traffic lanes restored during seasonal shutdowns.  Contract Completion: May 2024

  37. Thank you

Recommend Documents


she kon greetings
SHE:KON/GREETINGS: q The Mohawks of the

SHE:KON/GREETINGS: q The Mohawks of the Bay of Quinte is located in eastern

nys s route 5 b buffalo lo sk skyway projec ject
NYS S Route 5 (B (Buffalo lo Sk

NYS S Route 5 (B (Buffalo lo Sk Skyway) ) Projec ject Publi lic Sc

qew qew
QEW QEW Garden City Skyway

10/3/2013 QEW QEW Garden City Skyway Environmental Assessment October

highway infrastructure challenges highway infrastructure
Highway Infrastructure Challenges

Highway Infrastructure Challenges Highway Infrastructure Challenges

rehabilitation at qbe and wider
Rehabilitation at QBE and wider..

Rehabilitation at QBE and wider.. Adam Shelverton Senior Rehabilitation

architecture perceptron highway networks highway networks
Architecture Perceptron Highway

Highway Networks for Visual Question Answering Aaditya Prakash PhD advisor:

trenton memorial hospital
Trenton Memorial Hospital Facts and

Our TMH Resource Committee Trenton Memorial Hospital Facts and Figures

2019 state highway system management plan shsmp
2019 State Highway System Management

TAB 60 2019 State Highway System Management Plan (SHSMP) Directors Office

robert s moore jr
Robert S. Moore, Jr. Arkansas Highway

Robert S. Moore, Jr. Arkansas Highway Commissioner Dermott Chamber of

vocational rehabilitation vr includes
Vocational Rehabilitation (VR)

Vocational Rehabilitation (VR) includes: The Bureau of Vocational At Work

ida lake dam
Ida Lake Dam Chris Wheland,

Alternatives Analysis for Ida Lake Dam Chris Wheland, Superintendent

monmouth county bridge s 17 on county route 10 west front
Monmouth County Bridge S-17 On County

Monmouth County Bridge S-17 On County Route 10, West Front Street over the

trb 91 st annual meeting session 442 trb 12 2813 outline
TRB 91 st Annual Meeting Session 442

1 First Fully Prefabricated Full-Depth Deck Panel Bridge System in Michigan:

rigid inclusions for support of roadways on challenging
Rigid Inclusions for Support of

Rigid Inclusions for Support of Roadways on Challenging Soils JASON GRIFFIN

dental implant cement flow simulations with star ccm
Dental Implant Cement Flow Simulations

Dental Implant Cement Flow Simulations with STAR-CCM+ Sabine Goodwin Problem

case presentation
Case Presentation Dr Howard Gluckman

International Multi-Center Study for the Megagen Anyridge Implant System Case

wednesday november 14 at 2 30 p m
Wednesday, November 14 at 2:30 p.m. 1

Montana Department of Transportation Russell Street Broadway to Dakota Update

connectio ion
Connectio ion? Samantha Webster &

Dental l Im Impla lants: Hex or Conic ical l Connectio ion? Samantha

sweetheart dam access challenges and design considerations
Sweetheart Dam Access Challenges and

Sweetheart Dam Access Challenges and Design Considerations Duff Mitchell

vilas park lagoon bridge replacements 08 29 30 public
Vilas Park Lagoon Bridge Replacements

Vilas Park Lagoon Bridge Replacements 08/29/30 Public Information Meeting

public involvement plan and
Public Involvement Plan and Why Are We

Public Involvement Plan and Why Are We Here? Open House Goals : Raise

technical bridge design review workshop presentation 1
Technical Bridge Design Review Workshop

Country Bridge Solutions August 2014 Technical Bridge Design Review Workshop