Royersford Spring City Bridge Rehabilitation Royersford Spring City - - PowerPoint PPT Presentation

royersford spring city bridge rehabilitation royersford
SMART_READER_LITE
LIVE PREVIEW

Royersford Spring City Bridge Rehabilitation Royersford Spring City - - PowerPoint PPT Presentation

Royersford Spring City Bridge Rehabilitation Royersford Spring City Bridge Rehabilitation Royersford - Spring City Bridge Rehabilitation Royersford - Spring City Bridge Rehabilitation Royersford & Spring City, PA Royersford & Spring


slide-1
SLIDE 1

Royersford Spring City Bridge Rehabilitation Royersford Spring City Bridge Rehabilitation Royersford - Spring City Bridge Rehabilitation

Royersford & Spring City, PA Main Street / Bridge Street (State Route 1043) over the Schuylkill River

Royersford - Spring City Bridge Rehabilitation

Royersford & Spring City, PA Main Street / Bridge Street (State Route 1043) over the Schuylkill River Main Street / Bridge Street (State Route 1043) over the Schuylkill River Main Street / Bridge Street (State Route 1043) over the Schuylkill River

PennDOT District 6-0 Steve Laws Assistant Construction Engineer Designer: TranSystems Michael J. Cuddy, P.E. Principal July 11th, 2011

slide-2
SLIDE 2

Royersford & Spring City, PA Royersford & Spring City, PA

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 2

slide-3
SLIDE 3

Bridge – Plan & Elevation Bridge – Plan & Elevation

Plan Elevation

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 3

Elevation

slide-4
SLIDE 4

Elevation – Open Spandrel Arch Elevation – Open Spandrel Arch

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 4

slide-5
SLIDE 5

Roadway Section Roadway Section

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 5

slide-6
SLIDE 6

Current Condition – Wearing Surface Current Condition – Wearing Surface

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 6

slide-7
SLIDE 7

Previous Repair Work – Emergency Deck Repairs (August 2005) Previous Repair Work – Emergency Deck Repairs (August 2005)

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 7

slide-8
SLIDE 8

Previous Repair Work– Emergency Deck Repairs (August 2005) Previous Repair Work– Emergency Deck Repairs (August 2005)

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 8

slide-9
SLIDE 9

Current Condition – Hole in Deck Found During Construction Current Condition – Hole in Deck Found During Construction

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 9

slide-10
SLIDE 10

Current Condition – Hole in Deck Found During Construction Current Condition – Hole in Deck Found During Construction

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 10

slide-11
SLIDE 11

Current Condition – Arch Ribs (Deteriorated Concrete Removed) Current Condition – Arch Ribs (Deteriorated Concrete Removed)

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 11

slide-12
SLIDE 12

Current Condition –Spandrel Columns (Deteriorated Concrete Removed) Current Condition –Spandrel Columns (Deteriorated Concrete Removed)

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 12

slide-13
SLIDE 13

Current Condition – Floorbeams (Deteriorated Concrete Removed) Current Condition – Floorbeams (Deteriorated Concrete Removed)

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 13

slide-14
SLIDE 14

Current Condition – Floorbeams (Supplemental Supports) Current Condition – Floorbeams (Supplemental Supports)

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 14

slide-15
SLIDE 15

Concrete Repairs – Underside (Patching Material Placed) Concrete Repairs – Underside (Patching Material Placed)

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 15

slide-16
SLIDE 16

Original Rehabilitation Program Original Rehabilitation Program

Deck

Remove Existing Bituminous Wearing Course & Underlying Brick g g y g Pavers Repair Original Slab as Required & Provide ¼” Deep Scarification Install Latex Modified Concrete Wearing Surface (1 ¼” Thickness) Install Latex Modified Concrete Wearing Surface (1 ¼ Thickness)

Arch Ribs, Spandrel Columns & Substructure

Concrete Repairs p

Floorbeams

Support Beam Retrofit

Construction Timeline

Work anticipated to be completed by Fall 2011 utilizing nighttime and weekend bridge closures

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 16

and weekend bridge closures.

slide-17
SLIDE 17

Accelerated Revised Deck Rehabilitation Program Accelerated Revised Deck Rehabilitation Program

Remove Existing Bituminous Wearing Course, Underlying Brick Pavers & Existing Parapets Repair Original Slabs as Required Power Wash Original Slab g Construct 8” Reinforced Deck Using High Performance Concrete Placed on Top of Original Slab Construct New Parapets with Pedestrian Railings on Top For the Safety of the Traveling Public and Our Construction Crews, this Work Necessitates Complete Closure and Detour for Approximately Eight Weeks. Construction Crews to Work “24/7, Around The Clock” to Complete the Work as Soon as Possible

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 17

Around The Clock to Complete the Work as Soon as Possible

slide-18
SLIDE 18

Rehabilitation – Roadway Surface Rehabilitation – Roadway Surface

Typical Section

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 18

slide-19
SLIDE 19

Rehabilitation – Roadway Surface Rehabilitation – Roadway Surface

Typical Deck Expansion Joint Retrofit

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 19

slide-20
SLIDE 20

Detour Detour

Detail A Detail B Detour Length ≈ 15 Miles

Royersford – Spring City Bridge Rehabilitation

July 11th, 2011 20

Detour Length 15 Miles

slide-21
SLIDE 21

Royersford Spring City Bridge Rehabilitation Royersford Spring City Bridge Rehabilitation Royersford - Spring City Bridge Rehabilitation

Royersford & Spring City, PA Main Street / Bridge Street (State Route 1043) over the Schuylkill River

Royersford - Spring City Bridge Rehabilitation

Royersford & Spring City, PA Main Street / Bridge Street (State Route 1043) over the Schuylkill River Main Street / Bridge Street (State Route 1043) over the Schuylkill River Main Street / Bridge Street (State Route 1043) over the Schuylkill River

Questions?