SLIDE 1 I-70 Blanchette Bridge 2020-2021
Rehabilitation Eastbound I-70
River
SLIDE 2 Existing Eastbound Bridge
- 3700’ Long
- Bridge Truss (3 spans)
- Steel Plate Girder (16 spans)
SLIDE 3
Bridge history
Opened in 1978
− Provided separate eastbound bridge
Major rehab in 2005
− Expansion Joint replacement − Repairs to deck, structural steel, substructure − Full paint overcoated original paint
2005 to present
− Driving surface repair, crack repairs
Current Operations
− 5 lanes on a 68-ft roadway − 77,000 vehicles per day on eastbound bridge
SLIDE 4
Upcoming needed Maintenance
Full Paint Replacement Expansion Joints Barrier Wall Repair Structural Repairs Epoxy Overlay
SLIDE 5
Why didn’t MoDOT do this in 2012-2013?
Components were not
to end of useful life yet
Required to utilize
companion Bridge to manage traffic
Project accelerated to
2020 from 2021 original start date because of I- 270 North Design Build Project
SLIDE 6
Traffic Impacts
Westbound I-70 bridge traffic reduced to 3 WB
Lanes + 2 EB Lanes separated by barrier
Eastbound I-70 bridge traffic reduced to 2 EB
Lanes during peak commuting times
Nighttime closure of the Eastbound bridge and
EB70 on ramps from 5th Street
Closure of S. 5th Street beneath Blanchette for joint
replacement
SLIDE 7
I-70 Traffic Configuration for 2020
SLIDE 8 Schedule
Construction contract expected to be awarded in
January
Construction starts March 2020 Goal to have major traffic restrictions completed
by Thanksgiving 2020. Closures will continue in
- 2021. Lane restrictions on Eastbound I-70 only (4
lanes open, additional lane closures off-peak)
SLIDE 9
Fifth Street Access
Full-duration closure of Eastbound I-70 onramp (VMP) Nighttime closures Eastbound I-70 onramp (5th) Traffic detoured to MO-364 via S. River Road
SLIDE 10
South Main Street
Short-term closures for expansion joint rehab &
painting
Traffic detoured to 5th Street Coordination with City of St. Charles
SLIDE 11
Katy Trail
Short-term closures to allow overhead rehab work Coordination with Dept. of Natural Resources On-street detour available during long-term closures
SLIDE 12
Alternate Routes
SLIDE 13
Key Stakeholders
St. Charles County businesses Maryland Heights/North Co businesses Hospitals Emergency responders Attractions/Event facilities Regional major employers St. Charles/St. Louis commuters Regional, state and national trucking companies Interstate travelers
SLIDE 14
Key Stakeholder Issues
Access on I-70, at Fifth Street, at Earth City Schedule for the work and its impacts Availability and location of alternate routes Increased commute times Increased congestion on alternate routes Emergency response time to the bridge Increased trucking delivery times
SLIDE 15
Initial Public Outreach
Creation of I-70 Blanchette Bridge
Community Advisory Committee
− High level regional issues − Representatives from St. Charles and St.
Louis sides of the project
− Provide information to regions they
represent
Presentations to groups Media Outreach over winter 2019-2020 Web page on https://www.modot.org/i-70-
blanchette-bridge-project
SLIDE 16
For more information
Email: BlanchetteI70@modot.mo.gov Project website: https://www.modot.org/i-70-blanchette-bridge-project CONTACTS I-70 Blanchette Bridge Project Manager Chris Kelly, 314-453-5034 Christopher.Kelly@MoDOT.mo.gov MoDOT St. Charles Area Engineer Andy Tuerck, 314-453-5046 Andrew.Tuerck@MoDOT.mo.gov