Chabot Dam Chabot Dam Seismic Upgrade Project Seismic Upgrade - - PowerPoint PPT Presentation

chabot dam chabot dam seismic upgrade project seismic
SMART_READER_LITE
LIVE PREVIEW

Chabot Dam Chabot Dam Seismic Upgrade Project Seismic Upgrade - - PowerPoint PPT Presentation

Chabot Dam Chabot Dam Seismic Upgrade Project Seismic Upgrade Project Tom Boardman, Project Manager November 14, 2018 Project Location North EBMUD Chabot Dam Project Location North Oakland Chabot Reservoir (10,350 acre-ft) Outlet


slide-1
SLIDE 1

Chabot Dam Seismic Upgrade Project Chabot Dam Seismic Upgrade Project

Tom Boardman, Project Manager November 14, 2018

slide-2
SLIDE 2

Project Location

Chabot Dam EBMUD North

slide-3
SLIDE 3

Project Location

Chabot Reservoir

(10,350 acre-ft)

Outlet Works North Hayward fault zone Chabot Dam San Leandro Oakland Castro Valley

slide-4
SLIDE 4

Chabot Dam and Outlet Works

Chabot Dam

Outlet Works

Release Spill

slide-5
SLIDE 5

Project Description

  • 140-yr old dam and 90-yr old outlet works
  • During M7.25 earthquake on Hayward fault:

Earth dam settles and slides Outlet works collapses; can’t drain lake

  • In 2006, DSOD directed EBMUD to develop

plans to upgrade earth dam and outlet works to improve seismic performance

slide-6
SLIDE 6

Chabot Dam built in 1875

slide-7
SLIDE 7

Earth Dam – Seismic Displacement Model

Reservoir Level Expected displacements due to Mw 7.25 earthquake

Dam before retrofit

135-ft high

slide-8
SLIDE 8

Outlet Works Retrofit

Outlet Works, July 2013

slide-9
SLIDE 9

Outlet Tower Retrofit

Reservoir Level Release Hillside Outlet Tower 8-ft Shaft

slide-10
SLIDE 10

Temporary Park Closures

Work Area

slide-11
SLIDE 11

Site Access Issues

12-ft Spillway Bridge 

slide-12
SLIDE 12

Site Access Issues

slide-13
SLIDE 13

Site Access Issues

Cliff Swallow Dusky Footed Wood Rat Wood Rat Midden Swallow Nests

slide-14
SLIDE 14

Earth Dam Seismic Upgrade

Max Lake Level Max Lake Level 100-ft wide CDSM buttress to reduce seismic displacements Expected displacements due to Mw 7.25 earthquake

Existing Dam Dam After Upgrade

slide-15
SLIDE 15

CDSM Rig Onsite

slide-16
SLIDE 16

CDSM Buttress Drilling Pattern

slide-17
SLIDE 17

CDSM Mixing Blades

slide-18
SLIDE 18

CDSM Mixing Blades

slide-19
SLIDE 19

Seepage Trench

slide-20
SLIDE 20

Seepage Trench

slide-21
SLIDE 21

Earthwork and Seepage Trench

Before Project During Seepage Trench During Final Grading

slide-22
SLIDE 22

Outlet Works Retrofit

Outlet Works in 1924 Outlet Tower Demolition

slide-23
SLIDE 23

Outlet Works Retrofit

Shaft Liner Installation Shaft Liner Grouted in Place Brick Lined Access Shaft

slide-24
SLIDE 24

Outlet Works Retrofit

During Pipeline Removal New 42” Intake Pipeline - Lakeside After Pipeline Removal

slide-25
SLIDE 25

Outlet Works Retrofit

New Outlet Works in Rock Hillside Outlet Works After Demolition

slide-26
SLIDE 26

End of Construction

Final Downstream Slope of Dam Replacement Staff Gage and Safety Buoys View of Former Outlet Tower across Lake

slide-27
SLIDE 27

2016/2017 Winter Rainfall

  • Record breaking rainfall ~44-inches
  • Spilled Jan to May 2017
  • Delays to earthwork on dam
  • Chabot fish go over spillway

Main Spillway Jan 26, 2017 San Leandro Creek below Dam

slide-28
SLIDE 28

San Leandro Creek – Fish Flows

  • Rescued ~80 rainbow trout; returned to Chabot
  • Currently releasing ~80 gpm (0.2 cfs)
  • EBMUD still working with CDFW to develop

long-term strategy for fish flows in creek

Rescued Rainbow Trout Team of EBMUD & EBRPD rangers/biologists May 25, 2017

slide-29
SLIDE 29

Spillway Repair

During Repair Cracked Spillway After Repair

slide-30
SLIDE 30

Earthquake Monitoring

During Repair Seismograph

  • n Dam

After Repair

Mw 3.0 earthquake July 15, 2018 ~ 2 miles from Chabot Dam

slide-31
SLIDE 31

Questions?

During Repair Cracked Spillway After Repair