LITTLE LONG DAM SAFETY PROJECT
Improving dam safety
- n the Lower
LITTLE LONG DAM SAFETY PROJECT Improving dam safety on the Lower - - PowerPoint PPT Presentation
Kapuskasing Council Presentation March 4, 2019 LITTLE LONG DAM SAFETY PROJECT Improving dam safety on the Lower Mattagami River LITTLE LONG DAM SAFETY PROJECT WHAT IS OPG PROPOSING TO DO? The discharge capacity at the Adam Creek Sluiceway
WHAT IS OPG PROPOSING TO DO?
The discharge capacity at the Adam Creek Sluiceway will be increased in order to safety pass a rare large flood type event. The proposed project will not result in changes to day-to-day water levels and flows for the Little Long Main Dam. OPG will be adding more capacity to control the water, but not more water.
WHY NOW?
The Little Long Dam Safety Project will allow OPG to meet updated dam safety legal requirements, avoid infrastructure and operational impacts to the four generating stations on the Lower Mattagami River, and reduce impacts to the environment in the event of a very large scale flood. The project will also provide local employment and commercial opportunities.
LITTLE LONG DAM SAFETY PROJECT
PROJECT DESCRIPTION
Additional gates will be added to the Adam Creek Sluiceway. The preferred location for the additional gates is on the southeast side of the existing Adam Creek Sluiceway and current conceptual designs are shown at right. Other work required by the project include upgrading the existing transmission line used to provide power to the Adam Creek Sluiceway and reliability improvements to the Little Long, Adam Creek and Smoky Falls sluice gates. Temporary construction facilities will likely include:
side of the Adam Creek Sluiceway.
materials and construction activities.
location of the previous camp at Smoky Falls.
water before release back to the natural environment.
LITTLE LONG DAM SAFETY PROJECT Concept 1 Concept 2
CULTURAL HERITAGE
LITTLE LONG DAM SAFETY PROJECT
Lower Mattagami Complex identified as being previously disturbed.
little potential for archaeological resources to be found and therefore construction can proceed with no further archaeological study.
during construction, work will be stopped in the immediate area and the find will be investigated.
Generating Station, including Adam Creek Sluiceway concluded that the facilities are non- heritage.
SOCIO-ECONOMIC CONSIDERATIONS
LITTLE LONG DAM SAFETY PROJECT
area and as such there are no human uses that
no impact on human uses.
Road over Adam Creek will need to be closed for the duration of the project. However, the Fred Flatt Road from Kapuskasing to the Lower Mattagami Complex area will remain open.
the Little Long Road?
the size of the Lower Mattagami River Project.
with the Project providing employment and contracting opportunities through the design build contractor.
LITTLE LONG DAM SAFETY PROJECT
ENVIRONMENTAL CONSIDERATIONS
Existing Environment – Adam Creek Sluiceway
habitats have been restored for many species.
summer
Minimizing/Eliminating Construction impacts
protect the environment
disturbance & to avoid restored habitats
Post construction
restored properly
installing gates that would reduce the likelihood of Sturgeon entering Adam Creek
LITTLE LONG DAM SAFETY PROJECT
Kate Cantin Stakeholder Relations Advisor (Northeast Operations) kate.cantin@opg.com General inquiries: llds@opg.com