St. Vrain Creek Breaches Restoration Project Goals and Scoping June - - PowerPoint PPT Presentation

st vrain creek breaches restoration
SMART_READER_LITE
LIVE PREVIEW

St. Vrain Creek Breaches Restoration Project Goals and Scoping June - - PowerPoint PPT Presentation

St. Vrain Creek Breaches Restoration Project Goals and Scoping June 1, 2016 Clint Brown & Rich Tocher Project Overview www.enganalytics.com Breach 1 Post-Flood 2013 www.enganalytics.com Breach 2 Post-Flood 2013


slide-1
SLIDE 1
  • St. Vrain Creek Breaches Restoration

Project Goals and Scoping

June 1, 2016 Clint Brown & Rich Tocher

slide-2
SLIDE 2

www.enganalytics.com

Project Overview

slide-3
SLIDE 3

www.enganalytics.com

Breach 1 – Post-Flood 2013

slide-4
SLIDE 4

www.enganalytics.com

Breach 2 – Post-Flood 2013

slide-5
SLIDE 5

www.enganalytics.com

Breaches 5-9 – Post-Flood 2013

slide-6
SLIDE 6

www.enganalytics.com

Project Goals

 Provide 30% designs for resilient restoration of

the 9 breaches to the St. Vrain Creek

 Develop 2-3 restoration alternatives using

natural channel design to:

 Promote restored connectivity of vital wildlife and

aquatic habitat

 Encourage dynamic ecological processes  Maintain habitat and ecosystem health long term

 Encourage Stakeholder involvement

slide-7
SLIDE 7

Project Approach

Assessment Alternatives 30% Design Community Involvement

slide-8
SLIDE 8

www.enganalytics.com

Project Approach

 Task 1: Assessment

 Watershed and site  Survey and geotechnical  Hydraulics  Geomorphology and sediment transport  Aquatic and terrestrial species

 Ongoing  Public meeting today (June 1, 2016)

slide-9
SLIDE 9

www.enganalytics.com

Project Approach

 Task 2: Alternatives Definitions and Analysis

 Re-establishing flow along the creek alignment  Widening the floodplain  Creating a permanent creek alignment  Create split flood flow through the reach

 June-July 2016  Website: Best way to let your voice be heard

http://www.bouldercounty.org/os/openspace/pages/ssv-36-to- airport.aspx

 Public meeting (June, date/location TBD)

slide-10
SLIDE 10

www.enganalytics.com

Breach Repair Option

www.enganalytics.com

SOIL LOADED NATIVE ROCK BEDDING

slide-11
SLIDE 11

www.enganalytics.com

Stream Restoration and Habitat Creation

slide-12
SLIDE 12

Stream Restoration and Habitat Creation

www.enganalytics.com

slide-13
SLIDE 13

www.enganalytics.com

Project Approach

 Task 3: 30% Design

 Resilient restoration of breaches  Promotion of wildlife and aquatic habitats  Encourage dynamic ecological processes

 July-August 2016  Public meeting (August, date/location TBD)

slide-14
SLIDE 14

www.enganalytics.com

Community Involvement

 Public progress meetings

 Project Goals and Scoping – June 1, 2016  Alternatives – June, date/location TBD  Final Presentation – August, date/location TBD

 St. Vrain Creek Coalition meetings

 May 25, 2016  June 22, 2016  July 27, 2016

 Community Field Trip

 Date/time TBD

slide-15
SLIDE 15

www.enganalytics.com

Community Involvement

 Website – Submit your questions or comments

http://www.bouldercounty.org/os/openspace/p ages/ssv-36-to-airport.aspx

 Contact Jesse Rounds, BCPOS

jrounds@bouldercounty.org 303-678-6271

slide-16
SLIDE 16

www.enganalytics.com

Project Schedule

Task 1 – Assessment · Ongoing

 SVCC Meeting · May 25, 4pm  Public Meeting · June 1, 6pm

Task 2 – Alternatives · June-July 2016

 SVCC Meeting · June 22, 4pm  Public Meeting · June, date/location TBD

Draft 30% Design · July-August 2016

 SVCC Meeting · July 27, 4pm  Public Meeting · July, date/location TBD

Final 30% Design Report · September 1, 2016

 Public Meeting · August date/location TBD

slide-17
SLIDE 17

www.enganalytics.com

Thank you!

For more information, visit the project website

http://www.bouldercounty.org/os/openspace/pages/ssv-36-to- airport.aspx

  • r contact

Jesse Rounds at BCPOS

jrounds@bouldercounty.org 303-678-6271