SAXE MIDDLE SCHOOL YOUR PROJECT TEAM LO LOREL PURCELL , PE, LEED AP - - PowerPoint PPT Presentation

saxe middle school your project team
SMART_READER_LITE
LIVE PREVIEW

SAXE MIDDLE SCHOOL YOUR PROJECT TEAM LO LOREL PURCELL , PE, LEED AP - - PowerPoint PPT Presentation

SAXE MIDDLE SCHOOL YOUR PROJECT TEAM LO LOREL PURCELL , PE, LEED AP , PE, LEED AP MARK ARK JEFFK JEFFKO , LEED AP , LEED AP GEOR GEORGE GRAIK GE GRAIKOSK OSKI RO ROGER JOHNSON Project Executive Pre-Construction Manager Project Manager


slide-1
SLIDE 1

SAXE MIDDLE SCHOOL

slide-2
SLIDE 2

YOUR PROJECT TEAM

EXPERIENCE COLLABORATION EXPERTISE

Project Executive MARK ARK JEFFK JEFFKO, LEED AP

, LEED AP

Superintendent RO ROGER JOHNSON Project Manager GEOR GEORGE GRAIK GE GRAIKOSK OSKI Pre-Construction Manager LO LOREL PURCELL, PE, LEED AP

, PE, LEED AP

slide-3
SLIDE 3

PHASE 1A New Addition Jun 2016* – Fall 2017 PHASE 1B Auditorium Renovation Jun 2016* – June 2017 PHASE 1C Partial Renovation Summer 2016

  • f Existing Classrooms

PHASE 2A Convert Existing Choral Room Jun 2017* – Fall 2017 into Expanded Band Room Convert Existing Art Rooms into Choral and Storage Rooms PHASE 2B Minor Renovations to General Summer 2017 Music, Orchestra & Small Band Complete New Wing Connection * After End of School

Building Confidence

Construction Phases

Saxe Middle School

slide-4
SLIDE 4

Building Confidence

Phasing Plan

Saxe Middle School

Phase 1A Jun 2016 – Fall2017 Phase 1B Jun 2016 – Jun 2017 Phase 1C Summer 2016 Phase 2A Jun 2017 – Fall 2017 Phase 2B Summer 2017 CMU infills & HVAC ventilation work only during Phase 1C. Remainder of work Phase 2B. Abate Boiler Room

Overall ¡Construc/on: ¡ ¡June ¡2016 ¡– ¡Fall ¡2017 ¡

WORK ¡HOURS: ¡ DURING ¡SCHOOL ¡YEAR ¡ ¡12:00 ¡PM ¡– ¡8:30 ¡PM ¡ DURING ¡SUMMER ¡ ¡6:00 ¡AM ¡– ¡3:30 ¡PM ¡

slide-5
SLIDE 5

Second Floor Area B

Temporary enclosed Stair Tower from roof to grade 4’ wide aluminum planking with ballasted weighted bases and OSHA approved guardrails on both sides Temporary handrail

UP

Rated Temporary Partition

Fire Exit Plan

Saxe Middle School

Building Confidence

  • ­‑ ¡

¡ ¡ ¡ ¡ ¡ ¡

  • ­‑ ¡
slide-6
SLIDE 6

Designated Contractor Parking Dumpsters 20’ Double Drive Gate 20’ Double Drive Gate Moveable Fencing Moveable Fencing 20’ Double Drive Gate 20’ Double Drive Gate Construction Entrance Construction Entrance

Site Logistics Plan

Saxe Middle School

Building Confidence

slide-7
SLIDE 7

SAFETY IS MORE THAN A SLOGAN

Work Zone Separation Safety Coordination with Pre-construction Background Checks Job Safety Task Analysis Weekly Safety Meetings Constant Monitoring

24-HOUR SAFETY HOTLINE SAFETY MONITORING & INCIDENT TRACKING EXPERT SAFETY TEAM