Roberts Field Improvement Committee April 13 th Meeting April 13, - - PowerPoint PPT Presentation

roberts field improvement committee april 13 th meeting
SMART_READER_LITE
LIVE PREVIEW

Roberts Field Improvement Committee April 13 th Meeting April 13, - - PowerPoint PPT Presentation

Roberts Field Improvement Committee April 13 th Meeting April 13, 2017 Meeting Agenda Public Input Approve March 27, 2017 Meeting Minutes Review Additional Stakeholder Information Review Howard Stein Hudson Plan Design Discuss


slide-1
SLIDE 1

Roberts Field Improvement Committee April 13th Meeting

April 13, 2017

slide-2
SLIDE 2

Meeting Agenda

  • Public Input
  • Approve March 27, 2017 Meeting Minutes
  • Review Additional Stakeholder Information
  • Review Howard Stein Hudson Plan Design
  • Discuss Master Plan Features including Feature images
  • Schedule Next Meetings
slide-3
SLIDE 3

Additional Stakeholder Information

  • The Chelmsford Agway hosted an event to benefit the Roberts

Field Improvement Committee and raised $297 in three hours.

slide-4
SLIDE 4

Additional Stakeholder Information

Chelmsford Community Band

To answer your question, the band requires about 1000 to 1200 square feet of space to perform, roughly 30 feet front-to-back and 35-40 feet wide. The structure you showed a picture of at the March 8 meeting -- the one with the steel roof structure supported on four slender columns -- looked ideal, assuming it has roughly those dimensions. If a smaller structure is being considered, there would have to be a hard, flat surface in front of the structure that has a relatively low height difference from the structure's floor (i.e., no more than 2-3 feet). The total floor space requirements (structure + surface) would be the same. A smaller structure that could accommodate, say, our 18-piece jazz ensemble would need to be about 20 feet front-to-back and maybe 25 feet wide (about 500 square feet). We would also need storage for our equipment during our summer concert

  • season. In recent seasons, we have been doing this by renting a 20 x 8 foot storage container for the duration of the season

(about 6-8 weeks). Ideally, we would be able to site this container somewhere near the performance structure. A more permanent storage structure would be nice, but not at all necessary, given the desire to minimize the construction of new permanent structures at the park. Our only other requirement would be electrical power at the performance structure. Ideally, there would be at least two 15A circuits; we'd use one for lighting and one for sound reinforcement and other needs. Hopefully, the structure would have some lighting built into it as well. Regarding possible sites -- one consideration that we need to keep in mind is that our concerts are normally in the late afternoon and evening, and the sun shining in the faces of the band members can be a huge problem. For this reason, I would strongly encourage placing the performance structure somewhere on the southern or western edges of the park. For example, I was thinking that the slight rise at the northwest corner of the park, between the parking area and the playground, would be an ideal site for a performance stage for a number of reasons:

  • no sun directly in the eyes of either performers or audience
  • parents in the audience can keep an eye on children in the playground
  • easy access from the road for storage container, etc.
  • food trucks could park nearby
  • electrical power is already available in that area

While I understand the appeal of locating the structure on the east edge of the park near the fire station, this would have the drawback of having the entire band directly facing the setting sun.

slide-5
SLIDE 5

Additional Stakeholder Information

Inv # v # GPX PX # # Street eet / / Propert rty Tree S e Spec ecies es DBH BH Cond. Notes es Map ap Spre read Heigh ght Lat. t. Long. g. Date te By By RF001 01 Roberts Field Linden Littleleaf 16 Good Split Trunk Chain imbeded 43 36 25 42° 36.356' 71° 23.343' 1/31/2017 BA/JM RF002 02 Roberts Field Linden Littleleaf 13 Fair 43 31 27 42° 36.354' 71° 23.346' 1/31/2017 BA/JM RF003 03 Roberts Field Maple Red 9.4 Poor Consat Damage to roots trunk 43 24 33 42° 36.343' 71° 23.345' 1/31/2017 BA/JM RF004 04 Roberts Field Crabapple 12 Good Suckers mower 43 30 31 42° 36.369' 71° 23.367' 1/31/2017 BA/JM RF005 05 Roberts Field Maple Red 1.5 Poor Roots & trunk construction damage 43 5 15 42° 36.333' 71° 23.338' 1/31/2017 BA/JM RF006 06 Roberts Field Elm American 4.5 Good 43 9 28 42° 36.324' 71° 23.336' 1/31/2017 BA/JM RF007 07 Roberts Field Crabapple 14 Good 43 30 35 42° 36.326' 71° 23.447' 1/31/2017 BA/JM RF008 08 Roberts Field Maple Sugar 14.4 Good Sap Sucker 43 38 45 42° 36.322' 71° 23.444' 1/31/2017 BA/JM RF009 09 Roberts Field Pear Bradford 13.6 Fair trunk vandalized 43 24 32 42° 36.317' 71° 23.442' 1/31/2017 BA/JM RF010 10 Roberts Field Linden Littleleaf 14 Good 43 33 40 42° 36.309' 71° 23.444' 1/31/2017 BA/JM RF011 11 Roberts Field Maple Sugar 22.1 Good 43 43 53 42° 36.297' 71° 23.443' 1/31/2017 BA/JM RFO12 12 Roberts Field Oak Red 26 Good Boundry Line Tree 43 56 60 42° 36.321' 71° 23.462' 1/31/2017 BA/JM RF013 13 Roberts Field Oak Red 35.3 Fair Boundry Line Tree old wire 44 60 68 42° 36.238' 71° 23.422' 1/31/2017 BA/JM RF014 14 Roberts Field Oak Red 51.3 Good Pruning 37.5/32.5/12.5 44 77 70 42° 36.226' 71° 23.404' 1/31/2017 BA/JM RF015 15 Roberts Field Maple Red 36 Fair 43 56 38 42° 36.382' 71° 23.344' 2/27/2017 BA/BJ/JM RF016 16 Roberts Field Oak Black 3 Good 43 12 20 42° 36.385' 71° 23.340' 2/27/2017 BA/BJ/JM RF017 17 Roberts Field Maple Red 10 Good 43 22 40 42° 36.385' 71° 23.345' 2/27/2017 BA/BJ/JM RF018 18 Roberts Field Maple Red 11.3 Good 43 22 40 42° 36.384' 71° 23.349' 2/27/2017 BA/BJ/JM RFO19 19 Roberts Field Maple Red 13 Good 43 21 40 42° 36.386' 71° 23.345' 2/27/2017 BA/BJ/JM RFO20 20 Roberts Field Maple Red 15 Fair 43 22 30 42° 36.381' 71° 23.346' 2/27/2017 BA/BJ/JM RF021 21 Roberts Field Maple Red 8.9 Fair 43 20 40 42° 36.387' 71° 23.346' 2/27/2017 BA/BJ/JM RF022 22 Roberts Field Maple Red 15 Fair Construction damage 43 31 35 42° 36.386' 71° 23.349' 2/27/2017 BA/BJ/JM RF023 23 Roberts Field Oak Red 25.4 Good 43 48 48 42° 36.400' 71° 23.336' 2/27/2017 BA/BJ/JM RF024 24 Roberts Field Maple Red 9.9 Good 43 31 42 42° 36.387' 71° 23.335' 2/27/2017 BA/BJ/JM RF025 25 Roberts Field Maple Red 8.6 Good 43 23 42 42° 36.387' 71° 23.335' 2/27/2017 BA/BJ/JM RF026 26 Roberts Field Maple Red 15.9 Good 43 34 42 42° 36.387' 71° 23.335' 2/27/2017 BA/BJ/JM RF027 27 Roberts Field Cherry Black 8 Fair Weed Barrier 43 26 30 42° 36.393' 71° 23.331' 2/27/2017 BA/BJ/JM RF028 28 Roberts Field Maple Red 11.7 Good Weed Barrier 43 21 30 42° 36.393' 71° 23.331' 2/27/2017 BA/BJ/JM RF029 29 Roberts Field Maple Red 15.4 Fair Weed Barrier 43 33 30 42° 36.394' 71° 23.329' 2/27/2017 BA/BJ/JM RF030 30 Roberts Field Maple Red 18.6 Good 7.4,8,6,8.5,7.5,8 43 48 51 42° 36.398' 71° 23.319' 2/27/2017 BA/BJ/JM RF031 31 Roberts Field Cherry Black 8.5 Poor 43 25 35 42° 36.400' 71° 23.305' 2/27/2017 BA/BJ/JM RF032 32 Roberts Field Maple Sugar 7.7 Good 43 24 35 42° 36.400' 71° 23.305' 2/27/2017 BA/BJ/JM RF033 33 Roberts Field Maple Red 7.8 Good 5,6 43 29 36 42° 36.394' 71° 23.291' 2/27/2017 BA/BJ/JM RF034 34 Roberts Field Maple Red 23.5 Good 11.8,15.3,8.7,10.1 43 51 54 42° 36.393' 71° 23.293' 2/27/2017 BA/BJ/JM RF035 35A Roberts Field Maple Red 9.7 Fair 9,7 43 34 45 42° 36.388' 71° 23.293' 2/27/2017 BA/BJ/JM RF035 35B Roberts Field Maple Red 20 Good 18,8.8 43 44 56 42° 36.382' 71° 23.284' 2/27/2017 BA/BJ/JM RF036 36 Roberts Field Maple Red 23.7 Fair 21.7,9.5 43 56 45 42° 36.381' 71° 23.285' 2/27/2017 BA/BJ/JM RF037 37 Roberts Field Maple Red 19.9 Fair Boundry Line Tree 13,15 43 48 45 42° 36.377' 71° 23.287' 2/27/2017 BA/BJ/JM RF038 38 Roberts Field Maple Red 16.8 Poor 7,15 43 33 40 42° 36.384' 71° 23.295' 2/27/2017 BA/BJ/JM RF039 39 Roberts Field Maple Red 19.3 Fair 5.7,5.2,5.8,6.2,14.2 43 36 40 42° 36.382' 71° 23.292' 2/27/2017 BA/BJ/JM RF040 40 Roberts Field Oak Red 33.1 Good Boundry Tree? 44 73 75 42° 36.232' 71° 23.417' 3/30/2017 JM RF041 41 Roberts Field Oak Red 31.1 Good 12.1/18.9/17.3/12.8 44 60 65 42° 36.239' 71° 23.382' 3/30/2017 JM RF042 42 Roberts Field Oak Red 22.1 Good 17.3/4/13.2 44 61 45 42° 36.244' 71° 23.379' 3/30/2017 JM RF043 43 Roberts Field Oak Red 29.3 Good 44 75 74 42° 36.245' 71° 23.375' 3/30/2017 JM RF044 44 Roberts Field Oak Red 39 Good 22.4/28.9/13.6 44 60 73 42° 36.246' 71° 23.373' 3/30/2017 JM

Park Tree inventory

slide-6
SLIDE 6

Additional Stakeholder information

Inventoried Tree Protection Guidelines

Protect the inventoried trees’ Critical Root Zone (area around the tree trunk that extends outward from the trunk with a diameter of 12 times the diameter of the tree trunk. The tree trunk is measured at a point 4 ½ feet above ground level. It shall be the responsibility of the Towns Site Supervisor to enforce all of these Guidelines. Construction Standards

  • A protective 8 foot high chain link fence will be installed before any construction work begins. The fence is to remain in place in good

condition and not be removed, even temporarily, until after all construction work is completed and equipment removed from the work site.

  • The fence is to be located completely surrounding the outer margin of the Critical Root Zone.
  • Nothing is to be stored, even temporarily, inside the Root Zone including surplus soil, plant material, supplies, equipment, machinery, tools,

vehicles, fuel, or anything else that could potentially harm the tree.

  • There will be no fires within 100 feet of the Protection Zone.
  • Protection Zone signage is to be weather proof and installed to the fence every 8 feet with a minimum of 2 signs.
  • When there is to be a grade change adjacent to the Critical Root Zone, a trench, located 1 foot outside the protective fence, will be dug by

hand to a depth of 24 inches. The exposed root ends are to be cleanly cut on the side toward the tree with sharp pruning tools. Do not make slanting cuts. The roots are not to be chopped, crushed, ripped, or torn. The roots are not to be allowed to dry out. Cover with moist soil as soon as they are properly cut.

  • If necessary for safety reasons, dead branches over 3 inches in diameter should be removed from the tree before work commences by

properly trained and qualified tree workers in accordance with the Z-133 & A-300 Standards, under the direct supervision of a Massachusetts Certified Arborist.

  • Trees are not to be topped or to have the canopy thinned or reduced.
  • The tree should NOT be fertilized before or during construction but one year or more later if necessary by soil & tissue test.
  • Underground utilities such as water or electrical lines or irrigation pipes are not to be installed by trenching through the Critical Root
  • Zone. If necessary, by boring at a depth of 35 inches or greater under the tree from one side or the other.
slide-7
SLIDE 7

Questionable Tree Pruning Large Oak Before

slide-8
SLIDE 8

Large Oak After

slide-9
SLIDE 9

Questionable Tree Removals North of Playground

slide-10
SLIDE 10

Area north west of old play area

slide-11
SLIDE 11

Soil Issues/Questions Roberts Field Google Earth May, 2016

slide-12
SLIDE 12

North Edge Proposed Soccer Field

slide-13
SLIDE 13

West Ball Field

slide-14
SLIDE 14

Ball Field Texture

slide-15
SLIDE 15

Old Soccer field center

Note color change right & left

slide-16
SLIDE 16

Thank for this opportunity

Questions now or in the future

Please contact me: Jim Martin, Retired Consulting Arborist Cell (781) 572-7924 E-mail Jimtrees@aol.com

slide-17
SLIDE 17

Additional Stakeholder Information

Other Park and Playground Pictures

  • Dracut Veterans Park
  • Natural Playground Structures
slide-18
SLIDE 18

Dracut Veterans Park

slide-19
SLIDE 19

Dracut Veterans Park

slide-20
SLIDE 20

Natural Playground Structures

slide-21
SLIDE 21

Natural Playground Structures

slide-22
SLIDE 22

Natural Playground Structures

slide-23
SLIDE 23

Review HSH Master Plan Design

slide-24
SLIDE 24

Playground and Park Feature Cost Estimates

  • Sample costs for playground and Park features provided by the Town

DPW

slide-25
SLIDE 25

Estimated Cost Features $11-$12,000 Lacrosse Field (no nets) leveling out the area, new loam and seed (less if Town supplied materials) $44-$47,500 (2) Baseball Fields with backstop and dugout benches 2 backstops, dugout fencing, clay infield (some reuse of clay), min grading, loaming and seeding ? Cricket Field (Pitch cost identified at meeting = $15k) will require extensive grading and leveling of the entire surface $250-$275,000 "Manufactured Natural" Play Structures for Playground assumes same footprint as existing (1 large structure, 3-4 smaller structures, 5-6 swings or slides) $375-$400,000 40-50% larger footprint, maybe 2 large structures 4-5 smaller 5-6 swings/slides $3-$5,000 Landform Play areas (berms, tunnel, bridge, meadow, hills, big rocks, digging area) shaping material, loam and seed $18-$22 per foot Perimeter Playground fencing black vinyl coated 4 foot high, top rail and bottom rail see slides (2) Playground shade structures (large enough for 2 picnic tables each) $200-$750 ea (2) playground benches (metal) $200-$750 ea (3) Pond side benches (metal to match metal picnic tables) see slides Bandstand/Picnic Pavillion/Skating seating with power and lights (larger 30'x40', smaller 20'x25) Storage Sheds for athletic fields and bandstand (3 smaller, 1 larger and 1 smaller) 8x12 $4-$5,000 installed, basic options 16x24 $12-$15,000 installed, basic options $25 per foot Walking Track (8' wide) based on DPW material pricing (if road paver will do, drop price by 50%) Portable bathroom enclosure (large enough to accommodate 2 handicapped units, bench seating, screened walls) Handicap porta potty $105/month each, reg $50 clean and stock once a week (2) handicapped portable bathrooms $25-$30,000 Irrigation system and well Deep well, irrigation on all fields and grass areas, Stub to pol park $20-$24,000 Security Cameras 3 cameras, upgraded server, approx 300yds fiber $8-$12 LF Underground utilities to pond and playground lights conduit and wire DPW install (playground run will have ledge) $12,500.00 Parking lot fencing to replace guardrails (similar style to Westford Street/Old Westford Road white fence) similar to wood guard rail installed at East (includes removal of existing) $500-$6,000 Restripe upper and lower parking lots Paint or thermo? $17500-$20,000 Hardscape play area next to Engine #3 (half basketball court, four square) grade, gravel, 3.5 inches mix, lines and 1 bball hoop and 4 square set up $20-$22,000 Repair swale, add curbing and driveway improvements along side and back of Engine #3 granite curb along edge, ovelay entire lot with 1-1/2 inches $13-$20,000 Repair Parks garage $20,000 includes new door and windows. $500 (2) Map Kiosks (park entrance, rear trail entrance) Roberts Field Improvement Committeee Park Feature Cost Estimates 4/13/2017

slide-26
SLIDE 26

Playground Structure Cost Estimates

slide-27
SLIDE 27

Large Structure $123,000 – (34’x50’)

slide-28
SLIDE 28

Large Structure $88,000 (38’x55’)

slide-29
SLIDE 29

XL Structure - $203,000 – (135’ x 130’)

slide-30
SLIDE 30

Small/Medium Structure $15,000 (28’x23’)

slide-31
SLIDE 31

Small Structure $7,000 (25’x18’)

slide-32
SLIDE 32

100FT Zip Line $13,000 – (120’ x 25’)

slide-33
SLIDE 33

Double Hill slide $3,800

slide-34
SLIDE 34

Solo Flyer $900

slide-35
SLIDE 35

Dome Climber $3000

slide-36
SLIDE 36

4 Swings $1600 (plus swings)

slide-37
SLIDE 37

Wood Shade and Pavilion Cost Estimates

slide-38
SLIDE 38

24' x 44' Wood Gable Rectangular Savannah Pavilion Selected Options: 3:12 Roof Pitch, 30 Year Shingle Roofing, Factory Stain, No Cupola, Treated Glue Laminated Columns Total with Options: $20,599 for kit (does not include footings or concrete slab)

slide-39
SLIDE 39

12’x12’ $6,299 for kit

slide-40
SLIDE 40

20’x28’ $12,699 for kit

slide-41
SLIDE 41

50’ x 54’ Appalachian Laminated Beam Band Shell Pavilion with Included Storage Unit Design

slide-42
SLIDE 42

47’ x 27’ Niagara Arched Beam Band Shell Pavilion with Included Back Wall Design

slide-43
SLIDE 43

Steel Shade and Pavilion Cost Estimates

slide-44
SLIDE 44

24' x 44' All Steel Gable Rectangular Savannah Pavilion $37,699 for kit (doesn’t include footings or concrete slab)

slide-45
SLIDE 45

12' x 12' All Steel Gable Rectangular Savannah Pavilion $11,599 for kit

slide-46
SLIDE 46

$22,599 for kit 20' x 30' All Steel Gable Savannah Pavilion Shown w/Powder Coated Steel

slide-47
SLIDE 47

Schedule Next Meetings

  • Try to schedule two meetings in May
  • Best Days – May 4, 15, 17, 25, 31
  • Next Best Days – May 16, 18, 22, 30
  • Later Meeting Start Time (7:30pm) – May 2, 3, 11, 24
  • June Public Input Session