Regi gion 1 on 1 Sum Summer r Cons onstru ruct ction Proj - - PowerPoint PPT Presentation

regi gion 1 on 1 sum summer r cons onstru ruct ction proj
SMART_READER_LITE
LIVE PREVIEW

Regi gion 1 on 1 Sum Summer r Cons onstru ruct ction Proj - - PowerPoint PPT Presentation

Regi gion 1 on 1 Sum Summer r Cons onstru ruct ction Proj Project cts Up Updates ~ 2019 19 ~ Matt Freitag, Area Manager West Shelli Romero, Area Manager Central Paul Scarlett, Area Manager East 2 3 2019 P 2019


slide-1
SLIDE 1

Regi gion 1

  • n 1

Sum Summer r Cons

  • nstru

ruct ction Proj Project cts Up Updates ~ 2019 19 ~

slide-2
SLIDE 2

2 

Matt Freitag, Area Manager West

Shelli Romero, Area Manager Central

Paul Scarlett, Area Manager East

slide-3
SLIDE 3

3

slide-4
SLIDE 4

West – Matt Freitag

OR99W: Lane St (Portland) – Naeve St (Tigard) OR8 Pedestrian Crossing Upgrade at 44th/45th OR8 at OR219 Intersection Improvements

Central – Shelli Romero

US26: Outer Powell: SE 122nd – SE 136th I-5 Variable Speed Signs: Marine Drive to Fremont I-405: Fremont Bridge Joint Replacement Marquam Bridge Electrical

East – Paul Scarlett

OR99E: Railroad Tunnel Illumination & VMS sign I-205: OR 224 (Sunrise Expressway) to Sunnyside Blvd. I-205: Johnson Creek Blvd. to Glenn Jackson Bridge, Phase 1& I-205: Johnson Creek Blvd. to Glenn Jackson Bridge, Phase 2 I-84: Graham Road Bridges R1 High Friction Surface Treatment OR35 at MP 63.72 and MP 72.9 281: Hood River County Intersection Improvements

2019 P 2019 Proje jects by by Area rea

slide-5
SLIDE 5

OR R 99W 99W: Lane S Str treet t (Portland) –S. S.W. N Naev eve St St ( (Tigard)

Project E t Eleme ments nts

  • Sidewalk infill
  • Relocate bus stop
  • Upgrade ADA ramps

Sche hedul ule

  • Bids Opened 4/11/19
  • Construction 2019
  • Completion 2020

Tr Traf affic I Impact acts

  • Lane closures
  • Crosswalk closures
  • Temp transit impacts
slide-6
SLIDE 6

OR 8 OR 8 Pede destria ian C Cros rossin ing U Upgr pgrade at at S S.E.

  • E. 44

44th

th/45

45th

th Ave.

e.

Project E t Eleme ments nts

  • New flashing beacon
  • Improve lighting
  • Upgrade ADA ramps

Sche hedul ule

  • Bids Opened 5/9/19
  • Construction 2019
  • Completion 2020

Tr Traf affic I Impact acts

  • Noise
  • Lane closures
  • Crosswalk closures
slide-7
SLIDE 7

7

OR 8 R 8 at at OR 219 R 219 Int ntersec ection I Impro provem emen ents

.

Project E t Eleme ments nts

  • New signals &

signs

  • Upgrade ADA

ramps

  • Left turn lanes

Sche hedul ule

  • Bids Opened 5/9/19
  • Construction 2019
  • Completion 2020

Tr Traf affic I Impact acts

  • Noise
  • Lane closures
  • Crosswalk closures
slide-8
SLIDE 8

8

Ma Marqua rquam B Brid ridge E e Elec lectrical

Sch Schedule & & Tr Traf affic I Impact acts

  • Construction starts summer 2019
  • Nighttime lane closures
  • No construction during large public events in

the area or major holidays.

.

Project E t Eleme ments nts

  • Replace outdated electrical
  • Replace lighting systems
slide-9
SLIDE 9

9

US US26: Out Outer Po er Powel ell: S SE 122nd

nd to SE 136

136th

th

  • Add sidewalks
  • Improve crosswalks
  • Pedestrian activated mid-block crossings
  • New curbs and separated bicycle lanes
  • Center turn lanes for safer turns, reducing

back-ups

  • Improved stormwater management

Project E t Eleme ments nts

slide-10
SLIDE 10

10

U.S .S. 26 . 26: Out Outer er Po Powel ell: S SE 122nd

nd to S

SE 136 136th

th

Tra raffic ic Imp mpacts ts

Nighttime single lane closures with flaggers.

Sche hedul ule

Construction: May-fall 2020 Landscaping: Spring 2021

slide-11
SLIDE 11

11

I-5 5 Varia riable le Speed Signs: Marin rine Drive to Fre remo mont

Sche hedul ule

Fall 2019-Summer 2020

Project E t Eleme ments nts

  • Install new ODOT RealTime signs

○ Advisory Speed signs ○ Traveler Information signs

  • Relocated guide signs to:
  • Assist in reducing crashes
  • Improve travel time reliability
  • Enhance transit operations

Tr Traf affic I Impact acts

  • Nighttime construction
  • Noise during work hours
  • Intermittent on-and off-ramp

closures in both directions

  • 2-4 nighttime full closures of I-5 in

both directions

  • 1 week closure of the Alberta Street

northbound on-ramp and southbound off-ramp

.

slide-12
SLIDE 12

12

I-405 05: : Frem remont B Bri ridg dge J e Join int R Repla eplacement

West Side Side

Project E t Eleme ments nts

  • Replace and repair 42 bridge joints

Tr Traf affic I Impact acts

  • Nighttime, weekend and extended on-

and off-ramp closures.

  • Sidewalk & lane closures below the

freeway when work is performed above.

  • Intermittent of on- and off-ramp

closures:

○ Nighttime and weekends ○ Approximately 25 total weekend

closures (Fri 8PM-Mon 10AM)

  • Extended closures:

○ US30 East to I-405 SB, 11 days ○ US30 EB to I-405 NB, 18 days

slide-13
SLIDE 13

13

I-405: F Frem remont B Bri ridg dge J e Join int R Repla eplacement

East Side t Side

Sche hedul ule

Construction March 2019 – fall 2020

Tra raffic ic Imp mpacts ts

  • Nighttime, weekend and

extended on- and off-ramp closures.

  • Sidewalk and lanes closures

below the freeway when work is being done from above.

  • Intermittent nighttime and

weekend on-and off- ramp closures.

slide-14
SLIDE 14

14

Sche hedul ule

Construction February-Summer 2019

OR OR99E R Railr ilroad T Tunnel unnel I Ill llum umination & n & VMS MS Sig ign

Project E t Eleme ments nts

  • Add new LED Tunnel Lighting
  • Install a Variable Message sign

south of the tunnel

Tr Traf affic I Impact acts

  • Night time closures with

flagging

  • Daytime weekday closures

9 a.m.-3pm

  • Periodic night time closure of

tunnel

slide-15
SLIDE 15

15

Sche hedul ule

  • February 2019 to

Summer 2020

I-205: S Sunr unrise Expre xpressway t to Sunn unnyside de B Blv lvd

Project E t Eleme ments nts

  • Paving and adding

auxiliary lane

  • Install two new sign

structures

  • Stormwater and water

evaluation

Tr Traf affic I Impact acts

  • Nighttime lane closures

8 p.m.to 5 a.m.

slide-16
SLIDE 16

I-205: J Johns hnson C Creek reek Blv lvd t d to Glenn lenn J Jackson B Br

Phas ase 1 e 1-Aux Auxil ilia iary ry Lanes nes & Paving ing

Project E t Eleme ments nts

  • Paving I-205
  • Southbound auxiliary lane

(I-84 EB – Division/Powell)

  • Northbound auxiliary lane

(I-84 EB – Killingsworth off ramp)

  • Repair and replace bridge

joints

  • Install ADA ramps at Glisan,

Washington, Stark, JCR and Foster and Woodstock

Tr Traf affic I Impact acts

  • Week night lane, ramp and

shoulder closure from 8 p.m. to 5:30am

Sche hedul ule

March 2018-November 2019

slide-17
SLIDE 17

Sche hedul ule

February 2019 – Fall 2019

I-205: J Johns hnson C Creek reek Blv lvd t d to Glenn lenn J Jackson B Br

Phas ase 2 e 2 Auxili iliary ary L Lanes nes & & ODOT RealT lTim ime Signs

Project E t Eleme ments nts

  • Auxiliary lane (Powell –to

I-84 WB)

  • Sign Structures
  • RealTime Signs
  • Full weekend closure (Aug. 2-5,

2019)

Tr Traf affic I Impact acts

  • Weeknight lane closures 8 p.m. to

5:30am

  • Full weekend closure of

northbound lane at Division 8/2- 5/10 from 10pm to 5am

slide-18
SLIDE 18

Sche hedul ule

February 2019 to Winter 2020

I-84: Gra raha ham R Road B d Brid ridges

Project E t Eleme ments nts

  • Replace I-84 bridge to

increase the vertical clearance for large trucks

  • Widen Graham Road to

three lanes

  • Increase vertical

clearance for trucks

  • Improve bicycle and

pedestrian access under

  • n Graham Road

Tr Traf affic I Impact acts

Nighttime single lane closures Week 10:00 p.m. to 5:30 a.m.

slide-19
SLIDE 19

Tr Traf affic I Impact acts

Daytime single lane closure managed by flaggers

OR35 at R35 at M MP 63.72 63.72 an and MP 72.9 72.9

Project E t Eleme ments nts

Mt Hood Meadows

  • Rock & tree removal on slope
  • Slope Stabilization

Hood River Canyons/”The Narrows”

  • Remove rocks
  • Repair & maintenance to existing rockfall

catchment fence

Sche hedul ule

Summer to Fall 2019

slide-20
SLIDE 20

Tr Traf affic I Impact acts

Flaggers directing traffic at either/both intersections during daylight hours

Sche hedul ule

March 2019 - Summer 2019

Hood River County Intersection Improvements

Project E t Eleme ments nts

  • Widening of 2 intersections to accommodate truck turning
  • Country Club Road at Barrett Drive
  • Tucker Road (OR 281) at Guignard Drive
slide-21
SLIDE 21

Partne ners rship w hip with L h Law En Enfor

  • rceme

ment t To ensu sure sa safety ty for r work rkers a and nd the he publi public!

slide-22
SLIDE 22

For more information please visit: www.Oregon.gov/ODOT/HWY/ Region1/Pages/ProjectPage.aspx

Wher here t e to get et more I re Inf nformation:

TripCheck.com