RFB 6000000942 OPTIONAL PRE-BID CONFERENCE * The material contained - - PDF document

rfb 6000000942
SMART_READER_LITE
LIVE PREVIEW

RFB 6000000942 OPTIONAL PRE-BID CONFERENCE * The material contained - - PDF document

RFB 6000000942 OPTIONAL PRE-BID CONFERENCE * The material contained herein is for informational purposes only 1 Miami Field Station Maintains Approximately 4,734 Acres with approx. 234 miles of canal Right-of-Ways Approximately 346


slide-1
SLIDE 1
slide-2
SLIDE 2
slide-3
SLIDE 3

RFB 6000000942

OPTIONAL PRE-BID CONFERENCE

* The material contained herein is for informational purposes only 1

slide-4
SLIDE 4
  • Miami Field Station Maintains Approximately 4,734

Acres with approx. 234 miles of canal Right-of-Ways

  • Approximately 346 access gates
  • Access roads of various widths, signs, power/light

poles, fences, guardrails, guy wires, boat ramps, and water control structures

2

slide-5
SLIDE 5
  • Flat mowing grassed and/or vegetated ROWs with

conventional high production large and small mowing and trimming equipment

  • Mowing surface 3:1 ratio or less
  • Conventional high production equipment

‐ Minimum 2 tractors ‐ Ranging from 100hp - 115hp ‐ 4x2 or 4x4

  • Bat wing and/or bush hog mowers
  • 15’ to 20” deck (2)
  • dual wheels, foam filled flotation

3

slide-6
SLIDE 6
  • 4 to 6 cycles per year
  • District can modify as needed
  • Monday thru Saturday excluding District holidays
  • Dawn to Dusk
  • Changes to the work schedule must be approved in

writing

4

slide-7
SLIDE 7
  • Areas, boundaries and limits have been pre-

established

  • Area quantities have been inventoried and calculated
  • Width of area calculated using a Westward Distance Wheel
  • Distance in feet calculated using JAMAR RAC Plus 1

5

slide-8
SLIDE 8
  • Notice to Proceed Issued
  • Contractor receives NTP prior to each cycle
  • Contractor reviews start and end dates and acreage
  • Contractor starts work within 7 working days of receiving NTP
  • Pre-Work Meeting
  • Contractor attendance mandatory
  • Contractor provides anticipated work schedule
  • Questions are resolved with the District Project Manager prior work
  • Mowing Schedule
  • Contractor provides detailed schedule to be completed by the NTP

end date

  • Mutual agreement dates for inspections
  • Revised mowing schedule: How and when to recover from slippage

6

slide-9
SLIDE 9
  • Contractor Removes Debris
  • Contractor pre-inspects ROWs and removes all debris
  • Debris over 150 lbs or 5’ in dimension will be removed by the District

7

slide-10
SLIDE 10
  • Contractor Pre-Inspects ROW
  • Contractor inspects completed ROW prior to requesting inspection
  • Contractor mows ROWs
  • District Project Manager Inspects ROW
  • Contractor anticipates completion of each ROW and provides one

(1) day advanced notification to the District Project Manager

  • The District Project Manager will inspect the ROW within two (2)

business days

  • Upon satisfactory completion of mowing services, the District

Project Manager will authorize the Contractor to begin the next right-of-way identified in the Mowing Schedule.

8

slide-11
SLIDE 11
  • Contractor must obtain keys from the District to

access work site(s). District Key Permitting current key deposit rates apply for each key requested

  • All gates and entry barriers must be IMMEDIATELY

secured when entering or exiting a ROW

Change to OPEN

9

slide-12
SLIDE 12
  • Two way communication is vital for the success of the

project

  • Weekly status reports are due by 12:00 PM every Monday during a

mowing cycle

  • Immediately telephone the District Project Manager when absent

from the work site or delayed in mowing on a scheduled work day. Email follow up by 7:00 AM prior to the scheduled start of work.

  • Respond to all telephone calls within 2 hours, followed by email

and/or fax within the same business day

10

slide-13
SLIDE 13
  • Dense vegetation may require more than 1 pass
  • 4” height “+” or “-” 1”
  • Within 1’ of all structures and fence lines

11

slide-14
SLIDE 14
  • Canal Bank Conditions

DO NOT MOW WHEN:

  • Soggy due to excessive wet conditions
  • Sandy due to excessive dry conditions
  • Will cause rutting: Contractor responsible for repairs
  • Contact District Project Manager

12

slide-15
SLIDE 15
  • Around all structures on District ROWs
  • Trim gates for entire swing of each gate

13

slide-16
SLIDE 16

14

slide-17
SLIDE 17
  • All Contractor employees, vehicles and mowing

equipment must be clearly and visibly identified

  • Each vehicle must contain a copy of the NTP under

which work is being performed

15

slide-18
SLIDE 18
  • Tractor Safety
  • Seat Belt
  • Mirrors
  • Reflectors
  • Personal Protection Equipment (PPE)
  • Protective Eyewear
  • Gloves
  • Proper Footwear
  • Hearing Protection
  • Reflective Safety Vests
  • Seat Belt

16

slide-19
SLIDE 19
  • Minimal equipment maintenance allowed on ROWs
  • Mowing blades must be maintained and kept sharp for
  • ptimal results and to prevent scalping

17

slide-20
SLIDE 20

18