SLIDE 1
RFB 6000000942 OPTIONAL PRE-BID CONFERENCE * The material contained - - PDF document
RFB 6000000942 OPTIONAL PRE-BID CONFERENCE * The material contained - - PDF document
RFB 6000000942 OPTIONAL PRE-BID CONFERENCE * The material contained herein is for informational purposes only 1 Miami Field Station Maintains Approximately 4,734 Acres with approx. 234 miles of canal Right-of-Ways Approximately 346
SLIDE 2
SLIDE 3
RFB 6000000942
OPTIONAL PRE-BID CONFERENCE
* The material contained herein is for informational purposes only 1
SLIDE 4
- Miami Field Station Maintains Approximately 4,734
Acres with approx. 234 miles of canal Right-of-Ways
- Approximately 346 access gates
- Access roads of various widths, signs, power/light
poles, fences, guardrails, guy wires, boat ramps, and water control structures
2
SLIDE 5
- Flat mowing grassed and/or vegetated ROWs with
conventional high production large and small mowing and trimming equipment
- Mowing surface 3:1 ratio or less
- Conventional high production equipment
‐ Minimum 2 tractors ‐ Ranging from 100hp - 115hp ‐ 4x2 or 4x4
- Bat wing and/or bush hog mowers
- 15’ to 20” deck (2)
- dual wheels, foam filled flotation
3
SLIDE 6
- 4 to 6 cycles per year
- District can modify as needed
- Monday thru Saturday excluding District holidays
- Dawn to Dusk
- Changes to the work schedule must be approved in
writing
4
SLIDE 7
- Areas, boundaries and limits have been pre-
established
- Area quantities have been inventoried and calculated
- Width of area calculated using a Westward Distance Wheel
- Distance in feet calculated using JAMAR RAC Plus 1
5
SLIDE 8
- Notice to Proceed Issued
- Contractor receives NTP prior to each cycle
- Contractor reviews start and end dates and acreage
- Contractor starts work within 7 working days of receiving NTP
- Pre-Work Meeting
- Contractor attendance mandatory
- Contractor provides anticipated work schedule
- Questions are resolved with the District Project Manager prior work
- Mowing Schedule
- Contractor provides detailed schedule to be completed by the NTP
end date
- Mutual agreement dates for inspections
- Revised mowing schedule: How and when to recover from slippage
6
SLIDE 9
- Contractor Removes Debris
- Contractor pre-inspects ROWs and removes all debris
- Debris over 150 lbs or 5’ in dimension will be removed by the District
7
SLIDE 10
- Contractor Pre-Inspects ROW
- Contractor inspects completed ROW prior to requesting inspection
- Contractor mows ROWs
- District Project Manager Inspects ROW
- Contractor anticipates completion of each ROW and provides one
(1) day advanced notification to the District Project Manager
- The District Project Manager will inspect the ROW within two (2)
business days
- Upon satisfactory completion of mowing services, the District
Project Manager will authorize the Contractor to begin the next right-of-way identified in the Mowing Schedule.
8
SLIDE 11
- Contractor must obtain keys from the District to
access work site(s). District Key Permitting current key deposit rates apply for each key requested
- All gates and entry barriers must be IMMEDIATELY
secured when entering or exiting a ROW
Change to OPEN
9
SLIDE 12
- Two way communication is vital for the success of the
project
- Weekly status reports are due by 12:00 PM every Monday during a
mowing cycle
- Immediately telephone the District Project Manager when absent
from the work site or delayed in mowing on a scheduled work day. Email follow up by 7:00 AM prior to the scheduled start of work.
- Respond to all telephone calls within 2 hours, followed by email
and/or fax within the same business day
10
SLIDE 13
- Dense vegetation may require more than 1 pass
- 4” height “+” or “-” 1”
- Within 1’ of all structures and fence lines
11
SLIDE 14
- Canal Bank Conditions
DO NOT MOW WHEN:
- Soggy due to excessive wet conditions
- Sandy due to excessive dry conditions
- Will cause rutting: Contractor responsible for repairs
- Contact District Project Manager
12
SLIDE 15
- Around all structures on District ROWs
- Trim gates for entire swing of each gate
13
SLIDE 16
14
SLIDE 17
- All Contractor employees, vehicles and mowing
equipment must be clearly and visibly identified
- Each vehicle must contain a copy of the NTP under
which work is being performed
15
SLIDE 18
- Tractor Safety
- Seat Belt
- Mirrors
- Reflectors
- Personal Protection Equipment (PPE)
- Protective Eyewear
- Gloves
- Proper Footwear
- Hearing Protection
- Reflective Safety Vests
- Seat Belt
16
SLIDE 19
- Minimal equipment maintenance allowed on ROWs
- Mowing blades must be maintained and kept sharp for
- ptimal results and to prevent scalping
17
SLIDE 20
18