rfb 6000000942
play

RFB 6000000942 OPTIONAL PRE-BID CONFERENCE * The material contained - PDF document

RFB 6000000942 OPTIONAL PRE-BID CONFERENCE * The material contained herein is for informational purposes only 1 Miami Field Station Maintains Approximately 4,734 Acres with approx. 234 miles of canal Right-of-Ways Approximately 346


  1. RFB 6000000942 OPTIONAL PRE-BID CONFERENCE * The material contained herein is for informational purposes only 1

  2. • Miami Field Station Maintains Approximately 4,734 Acres with approx. 234 miles of canal Right-of-Ways • Approximately 346 access gates • Access roads of various widths, signs, power/light poles, fences, guardrails, guy wires, boat ramps, and water control structures 2

  3. • Flat mowing grassed and/or vegetated ROWs with conventional high production large and small mowing and trimming equipment • Mowing surface 3:1 ratio or less • Conventional high production equipment ‐ Minimum 2 tractors ‐ Ranging from 100hp - 115hp ‐ 4x2 or 4x4 • Bat wing and/or bush hog mowers - 15’ to 20” deck (2) - dual wheels, foam filled flotation 3

  4. • 4 to 6 cycles per year • District can modify as needed • Monday thru Saturday excluding District holidays • Dawn to Dusk • Changes to the work schedule must be approved in writing 4

  5. • Areas, boundaries and limits have been pre- established • Area quantities have been inventoried and calculated - Width of area calculated using a Westward Distance Wheel - Distance in feet calculated using JAMAR RAC Plus 1 5

  6. • Notice to Proceed Issued - Contractor receives NTP prior to each cycle - Contractor reviews start and end dates and acreage - Contractor starts work within 7 working days of receiving NTP • Pre-Work Meeting - Contractor attendance mandatory - Contractor provides anticipated work schedule - Questions are resolved with the District Project Manager prior work • Mowing Schedule - Contractor provides detailed schedule to be completed by the NTP end date - Mutual agreement dates for inspections - Revised mowing schedule: How and when to recover from slippage 6

  7. • Contractor Removes Debris - Contractor pre-inspects ROWs and removes all debris - Debris over 150 lbs or 5’ in dimension will be removed by the District 7

  8. • Contractor Pre-Inspects ROW - Contractor inspects completed ROW prior to requesting inspection - Contractor mows ROWs • District Project Manager Inspects ROW - Contractor anticipates completion of each ROW and provides one (1) day advanced notification to the District Project Manager - The District Project Manager will inspect the ROW within two (2) business days - Upon satisfactory completion of mowing services, the District Project Manager will authorize the Contractor to begin the next right-of-way identified in the Mowing Schedule. 8

  9. • Contractor must obtain keys from the District to access work site(s). District Key Permitting current key deposit rates apply for each key requested • All gates and entry barriers must be IMMEDIATELY secured when entering or exiting a ROW Change to OPEN 9

  10. • Two way communication is vital for the success of the project - Weekly status reports are due by 12:00 PM every Monday during a mowing cycle - Immediately telephone the District Project Manager when absent from the work site or delayed in mowing on a scheduled work day. Email follow up by 7:00 AM prior to the scheduled start of work. - Respond to all telephone calls within 2 hours, followed by email and/or fax within the same business day 10

  11. • Dense vegetation may require more than 1 pass • 4” height “+” or “ - ” 1” • Within 1’ of all structures and fence lines 11

  12. • Canal Bank Conditions DO NOT MOW WHEN : - Soggy due to excessive wet conditions - Sandy due to excessive dry conditions - Will cause rutting: Contractor responsible for repairs - Contact District Project Manager 12

  13. • Around all structures on District ROWs • Trim gates for entire swing of each gate 13

  14. 14

  15. • All Contractor employees, vehicles and mowing equipment must be clearly and visibly identified • Each vehicle must contain a copy of the NTP under which work is being performed 15

  16. • Personal Protection Equipment (PPE) - Protective Eyewear - Gloves - Proper Footwear - Hearing Protection - Reflective Safety Vests - Seat Belt • Tractor Safety - Seat Belt - Mirrors - Reflectors 16

  17. • Minimal equipment maintenance allowed on ROWs • Mowing blades must be maintained and kept sharp for optimal results and to prevent scalping 17

  18. 18

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend