1
Anderson Dam Seismic Retrofit Project Update
Public Meeting – City of Morgan Hill| March 22, 2017
Retrofit Project Update Public Meeting City of Morgan Hill| March - - PowerPoint PPT Presentation
Anderson Dam Seismic Retrofit Project Update Public Meeting City of Morgan Hill| March 22, 2017 1 Santa Clara Valley Water District serves 2 million people 15 cities 4,700 well owners San Francisco Bay Area 13 water retailers 2 Morgan
1
Public Meeting – City of Morgan Hill| March 22, 2017
2 Morgan Hill Public Meeting 3-22-2017
San Francisco Bay Area
3 Morgan Hill Public Meeting 3-22-2017
10 reservoirs 3 pump stations 142 miles of pipelines 3 water treatment plants 1 advanced purification plant 393 acres of recharge ponds 275 miles of jurisdictional streams
4 Morgan Hill Public Meeting 3-22-2017
Anderson: 90,000 Acre-Feet
Lexington Guadalupe Coyote Chesbro Calero Almaden Stevens Creek Uvas Vasona
Total Countywide Storage: 169,000 Acre-Feet
5 Morgan Hill Public Meeting 3-22-2017
Anderson Reservoir Coyote Reservoir
Coyote Creek Streamflow Gauge Anderson Dam Storage Gauge Coyote Reservoir Rainfall Gauge
6 Morgan Hill Public Meeting 3-22-2017
0.5 1 1.5 2 2.5 3 11/1 11/3 11/5 11/7 11/9 11/11 11/13 11/15 11/17 11/19 11/21 11/23 11/25 11/27 11/29 12/1 12/3 12/5 12/7 12/9 12/11 12/13 12/15 12/17 12/19 12/21 12/23 12/25 12/27 12/29 12/31
7 Morgan Hill Public Meeting 3-22-2017
0% 20% 40% 60% 80% 100% 120% 20,000 40,000 60,000 80,000 100,000 11/1 11/3 11/5 11/7 11/9 11/11 11/13 11/15 11/17 11/19 11/21 11/23 11/25 11/27 11/29 12/1 12/3 12/5 12/7 12/9 12/11 12/13 12/15 12/17 12/19 12/21 12/23 12/25 12/27 12/29 12/31
Reservoir Capacity (625.0 ft elev. / 91,373 af) Interim DSOD Restriction (599.5 ft elev. / 61,810 af)
Emergency Storage (20,000 af)
Note: Anderson Reservoir Actual Storage Level is solid blue line
8 Morgan Hill Public Meeting 3-22-2017
10 20 30 40 50 60 11/1 11/3 11/5 11/7 11/9 11/11 11/13 11/15 11/17 11/19 11/21 11/23 11/25 11/27 11/29 12/1 12/3 12/5 12/7 12/9 12/11 12/13 12/15 12/17 12/19 12/21 12/23 12/25 12/27 12/29 12/31
Anderson Reservoir outlet release to Coyote Creek: 40 cfs – 50 cfs
9 Footer
0.5 1 1.5 2 2.5 3 11/1 11/8 11/15 11/22 11/29 12/6 12/13 12/20 12/27
Rainfall (inches)
Coyote Reservoir Precipitation Gauge (ALERT gauge 6021)
0% 20% 40% 60% 80% 100% 120% 20,000 40,000 60,000 80,000 100,000 11/1 11/8 11/15 11/22 11/29 12/6 12/13 12/20 12/27
Percent Full Storage (acre-feet)
Anderson Reservoir Storage (ALERT gauge 1480)
Reservoir Capacity (625.0 ft elev. / 91,373 af) Interim DSOD Restriction (599.5 ft elev. / 61,810 af)
Nov 1 to Dec 30, 2016
Emergency Storage (20,000 af)
Rainfall Coyote Creek Flows Downstream of Anderson Dam Anderson Dam Storage Levels (blue line)
10 20 30 40 50 60 11/1 11/8 11/15 11/22 11/29 12/6 12/13 12/20 12/27
Flow (cfs)
Coyote Creek at Madrone Streamflow Gauge (ALERT gauge 5082)
10 Morgan Hill Public Meeting 3-22-2017
0.5 1 1.5 2 2.5 3 1/1 1/3 1/5 1/7 1/9 1/11 1/13 1/15 1/17 1/19 1/21 1/23 1/25 1/27 1/29 1/31 2/2 2/4 2/6 2/8 2/10 2/12 2/14 2/16 2/18 2/20 2/22 2/24 2/26 2/28
11 Morgan Hill Public Meeting 3-22-2017
0% 20% 40% 60% 80% 100% 120% 20,000 40,000 60,000 80,000 100,000 1/1 1/3 1/5 1/7 1/9 1/11 1/13 1/15 1/17 1/19 1/21 1/23 1/25 1/27 1/29 1/31 2/2 2/4 2/6 2/8 2/10 2/12 2/14 2/16 2/18 2/20 2/22 2/24 2/26 2/28
Interim DSOD Restriction (599.5 ft elev. / 61,810 af) Emergency Storage (20,000 af) Reservoir Capacity (625.0 ft elev. / 91,373 af)
Note: Anderson Reservoir Actual Storage Level is solid blue line
12 Morgan Hill Public Meeting 3-22-2017
1000 2000 3000 4000 5000 6000 7000 8000 1/1 1/3 1/5 1/7 1/9 1/11 1/13 1/15 1/17 1/19 1/21 1/23 1/25 1/27 1/29 1/31 2/2 2/4 2/6 2/8 2/10 2/12 2/14 2/16 2/18 2/20 2/22 2/24 2/26 2/28
Anderson Reservoir outlet
Anderson Reservoir begins to spill on 2/18 Anderson Reservoir outlet is closed on 2/20 as spillway flows exceed 2,000 cfs Anderson Reservoir spillway flows peak at above 7,000 cfs Anderson Reservoir
reopened
Anderson Reservoir stops spilling on 2/28
13 13 Footer
0.5 1 1.5 2 2.5 3 1/1 1/3 1/5 1/7 1/9 1/11 1/13 1/15 1/17 1/19 1/21 1/23 1/25 1/27 1/29 1/31 2/2 2/4 2/6 2/8 2/10 2/12 2/14 2/16 2/18 2/20 2/22 2/24 2/26 2/28
Rainfall (inches)
Coyote Reservoir Precipitation Gauge (ALERT gauge 6021)
0% 20% 40% 60% 80% 100% 120% 20,000 40,000 60,000 80,000 100,000 1/1 1/8 1/15 1/22 1/29 2/5 2/12 2/19 2/26
Percent Full Storage (acre-feet)
Anderson Reservoir Storage (ALERT gauge 1480)
Interim DSOD Restriction (599.5 ft elev. / 61,810 af) Emergency Storage (20,000 af)
Coyote Creek Flows Downstream of Anderson Dam
Reservoir Capacity (625.0 ft elev. / 91,373 af)
Jan 1 to Feb 28, 2017
Rainfall Anderson Dam Storage Levels (blue line)
2000 4000 6000 8000 1/1 1/3 1/5 1/7 1/9 1/11 1/13 1/15 1/17 1/19 1/21 1/23 1/25 1/27 1/29 1/31 2/2 2/4 2/6 2/8 2/10 2/12 2/14 2/16 2/18 2/20 2/22 2/24 2/26 2/28
Flow (cfs)
Coyote Creek at Madrone Streamflow Gauge (ALERT gauge 5082)
14 Morgan Hill Public Meeting 3-22-2017
15 Morgan Hill Public Meeting 3-22-2017
16
|
Morgan Hill Public Meeting 3-22-2017
► Provide the latest information on the seismic findings
► Address community questions and concerns ► Reinforce our commitment to public safety and
|
17
|
Morgan Hill Public Meeting 3-22-2017
18
|
Morgan Hill Public Meeting 3-22-2017
1989 Loma Prieta (6.9) 1979 Coyote Lake (5.7) 1984 Morgan Hill (6.1) 1911 Calaveras (6.5)
19
|
Morgan Hill Public Meeting 3-22-2017
1989 Loma Prieta Earthquake magnitude 6.9
1984 Morgan Hill Earthquake magnitude 6.1
20
|
Morgan Hill Public Meeting 3-22-2017
► Embankment slumps up to 25 feet due to
► Outlet conduit buckles up to 4 feet due to fault
► Outlet works does not meet current emergency
► Spillway undersized for Probable Maximum Flood
21
|
Morgan Hill Public Meeting 3-22-2017
22
|
Morgan Hill Public Meeting 3-22-2017
10 feet high cofferdam (drained reservoir) Upstream embankment buttress Downstream embankment buttress
Existing outlet pipe
23
|
Morgan Hill Public Meeting 3-22-2017
New sloping intake 10 feet high cofferdam (drained reservoir) Spillway modifications New High Level Outlet conduit Upstream embankment buttress Downstream embankment buttress New lower level conduit in tunnel
Abandon existing
24
|
Morgan Hill Public Meeting 3-22-2017
X X X X X X X
Shown: Mapped traces of Coyote Creek Fault
X
Zone 1 Liquefaction
25
|
Morgan Hill Public Meeting 3-22-2017
►
►
►
►
CRACK
26
|
Morgan Hill Public Meeting 3-22-2017
►
Retrofitted embankment similar footprint to existing dam.
►
Remove all liquefiable material (compared to previous buttress approach)
►
New high level and low level outlet
►
Spillway wall raise
►
Temporary cofferdam
►
New sloping intake
►
Crest raise for additional freeboard
27
|
Morgan Hill Public Meeting 3-22-2017
“ “
“ “
28
|
Morgan Hill Public Meeting 3-22-2017
Existing dam clay core Remnant dam clay core to remain Post Project dam footprint Existing dam footprint
29
|
Morgan Hill Public Meeting 3-22-2017
Year 1:
Lower Dam to Interim Height (El 570 ft) Lower Dam to remnant core; re-build to Interim Height (El 570 ft)
Dry Season* Year 2: Dry Season Year 3: Dry Season Year 4: Winter Year 4:
Reservoir begins to re-fill Full Height Over Winter (El 647 ft) Interim EL (570 ft) Winter 1 Interim EL (570 ft) Winter 2 Complete Construction (El 656 ft) Build Dam to Full Elevation (El 656 ft) Dewatering, Outlet Tunnel Construction
* Dry Season = April to October
30
|
Morgan Hill Public Meeting 3-22-2017
We are here
NEPA / CEQA / Permitting Design Construction 20202024
► Modified Project Cost ~ $400M
31
|
Morgan Hill Public Meeting 3-22-2017
► Public meeting in early 2018
► A public meeting for Draft EIR in late summer 2018
► Pre-construction meetings in 2019-2020
|
32
|
Morgan Hill Public Meeting 3-22-2017
► Sign up to receive project updates via email. ► View project reports, maps, history and other
► Coming later in 2017: project blog
plam@valleywater.org (408) 630-2710
33
|
Morgan Hill Public Meeting 3-22-2017
Tiburon Paintbrush Coyote Ceanothus
Smooth Lessingia Metcalf Canyon Jewel-flower
California Red-Legged Frog Dusky Footed Woodrat Western Pond Turtle California Tiger Salamander