regional transmission system master plan
play

REGIONAL TRANSMISSION SYSTEM MASTER PLAN Solicitation PNC2116651P1 - PowerPoint PPT Presentation

REGIONAL TRANSMISSION SYSTEM MASTER PLAN Solicitation PNC2116651P1 Tobon Engineering PROJECT SCOPE HYDRAULIC MODEL REGIONAL TRANSMISSION SYSTEM MASTER PLAN DATA COLLECTION UPDATE & CALIBRATE SCENARIOS PHASE I TRANSIENT MODEL HYDRAULIC


  1. REGIONAL TRANSMISSION SYSTEM MASTER PLAN Solicitation PNC2116651P1 Tobon Engineering

  2. PROJECT SCOPE HYDRAULIC MODEL REGIONAL TRANSMISSION SYSTEM MASTER PLAN DATA COLLECTION UPDATE & CALIBRATE SCENARIOS PHASE I TRANSIENT MODEL HYDRAULIC MODEL SYSTEM PRESSURE DATA SCENARIOS PHYSICAL OBSERVATIONS STRUCTURAL ELECTRICAL MECHANICAL Solicitation PNC2116651P1 RISK-BASED ANALYSIS CONDITION CRITICALITY PHASE II CAPITAL IMPROVEMENT PLAN PRIORITIZATION COST ANAYLSIS BUDGETING EMERGENCY RESPONSE PLAN RESPONSIVENESS EFFECTIVENESS GIS INTEGRATION

  3. PROJECT TEAM Robert Wilson, P.E. Broward County WWS Project Manager REGIONAL TRANSMISSION SYSTEM MASTER PLAN James F. Thompson, P.E. Project Manager & Principal-in-Charge H YDRAULIC P HYSICAL R ISK -B ASED E MERGENCY T RANSIENT C APITAL M ODELING M ODELING O BSERVATIONS A NALYSIS I MPROVEMENT R ESPONSE Solicitation PNC2116651P1 WSP THOMPSON & ASSOC. WSP THOMPSON & ASSOC. THOMPSON & ASSOC. THOMPSON & ASSOC. TOBON ENGINEERING THOMPSON & ASSOC. MUENGINEERING WSP WSP WSP THOMPSON & ASSOC. SMITH ENGINEERING PREMIER DESIGN TOBON ENGINEERING TOBON ENGINEERING ROSS ENGINEERING PREMIER DESIGN GIS S ERVICES FLORIDA TECHNICAL CONSULTANTS / WSP / PREMIER DESIGN / THOMPSON & ASSOC. QA / QC THOMPSON & ASSOC. / WSP / ROSS ENGINEERING

  4. DATA COLLECTION  DIANYS AROCHO, PE – REGIONAL TRANSMISSION SYSTEM MASTER PLAN GIS EXPERT  OBTAIN CURRENT GIS FILES  REVIEW AS-BUILTS  REVIEW MAINTENANCE Solicitation PNC2116651P1 RECORDS  CONDUCT O&M STAFF INTERVIEWS  FIELD VERIFICATIONS

  5. DEVELOP HYDRAULIC MODEL (INFOWATER) REGIONAL TRANSMISSION SYSTEM MASTER PLAN REGIONAL TRANSMISSION SYSTEM MASTER PLAN DATA GAPS AND ASSUMPTIONS FILE MANAGEMENT AND DELIVERY FORMAT MODEL NETWORK DEVELOPMENT PLAN Solicitation PNC2116651P1 Solicitation PNC2116651P1 MODEL BUILDER BOUNDARY CONDITIONS MODELING AND CALIBRATION APPROACH MODEL VALIDATION AND PERFORMANCE ANALYSIS ALTERNATIVE ANALYSIS

  6. DEVELOP HYDRAULIC MODEL (INFOWATER) ALTERNATIVE ANALYSIS REGIONAL TRANSMISSION SYSTEM MASTER PLAN  RASHEED AHMAD, PE, PhD INFOWATER EXPERT  POPULATION GROWTH  SEA LEVEL RISE & CLIMATE Solicitation PNC2116651P1 CHANGE  LARGE-USER AGREEMENTS  NIP & UAZ IMPROVEMENTS (I/I)  SEPTIC TANK ELIMINATION PROGRAM

  7. DEVELOP TRANSIENT MODEL (INFOSURGE)  JEAN-LUC DAVIAU, PE – INFOSURGE EXPERT REGIONAL TRANSMISSION SYSTEM MASTER PLAN  TRANSIENT (RAPID CHANGE) PRESSURES:  BURST / COLLAPSE PIPES  LEAKING JOINTS  DANGER TO O&M STAFF 120 Solicitation PNC2116651P1 Normal pump Normal pump  Simulated Power MODEL PARAMETERS: start-up shut-down 110 Failure Steady  Steady state PUMPS (ON/OFF) 100 Pressure (psi) Normal pump 90 start-up  BACKFLOW (OPEN/CLOSE/SLAM) 80  VALVES (OPEN/CLOSE/THROTTLE) Periodic 70 Transient 1 Less Pump Pressures  POWER OUTAGES 60 Attenuating Starting Time: 3:38:20 PM, May 4, 2000 50 0 10 20 30 40 Elapsed Time (min)

  8. DEVELOP TRANSIENT MODEL (INFOSURGE) POSSIBLE RECOMMENDATIONS: REGIONAL TRANSMISSION SYSTEM MASTER PLAN  FLOW & PRESSURE SENSORS  SCADA MONITORING  VFD MOTORS  SLOW-CLOSING BACKFLOW VALVES Solicitation PNC2116651P1  ATTENUATION CYLINDERS  SURGE TANKS  SURGE ANTICIPATOR VALVES  DUAL ARV’S

  9. PERFORM PHYSICAL OBSERVATIONS REGIONAL MASTER PUMP STATION REGIONAL TRANSMISSION SYSTEM MASTER PLAN 440 – NEW ASSESSMENT 410 – UPDATE 2016 ASSESSMENT 451 – UPDATE 2016 ASSESSMENT 455 – UPDATE 2016 ASSESSMENT 460 – UPDATE 2016 ASSESSMENT Solicitation PNC2116651P1 452 – DESIGN TO START 12/18 458 – DESIGN TO START 12/18 462 – DESIGN TO START 12/18 454 – DESIGN COMPLETED 5/18 456 – CONSTRUCTION TO BE COMPLETED 4/19 450 – CONSTRUCTION COMPLETED 9/18

  10. PERFORM PHYSICAL OBSERVATIONS   STRUCTURAL INSPECTIONS: MEP INSPECTIONS: REGIONAL TRANSMISSION SYSTEM MASTER PLAN   CONCRETE CONDITION (SPALLING, MECHANICAL SYSTEMS CRACKING, ETC.)  HVAC HANDLERS  METAL CORROSION  FULL OSHA REVIEW  EXTERIOR CONDITION (ROOF,  DRYWELL SUMP EQUIPMENT WINDOWS)  ELECTRICAL SYSTEMS Solicitation PNC2116651P1  SITE SECURITY / EMERGENCY ACCESS  DUAL-GRID PROTECTION  CONTROL PANEL CONDITION  GENERATOR CAPACITY  LIGHTNING / SURGE PROTECTION  COMMUNICATIONS  ALARMS / SECURITY CAMERAS  SCADA

  11. COMPLETE RISK–BASED ANALYSIS  COMPLETE A RISK-BASED ANALYSIS REGIONAL TRANSMISSION SYSTEM MASTER PLAN  DEFINE SYSTEM COMPONENTS  EVALUATE CHARACTERISTICS  RANK IMPACTS  PRIORITIZE RISKS  Solicitation PNC2116651P1 CREATE A MATRIX  SUMMARIZE RESULTS

  12. DEVELOP CAPITAL IMPROVEMENT PLAN  PRIORITIZE PROJECTS REGIONAL TRANSMISSION SYSTEM MASTER PLAN  DEVELOP ESTIMATES OF PROBABLE COSTS  CREATE SCHEDULES (DESIGN/CONSTRUCTION)  IDENTIFY ANNUAL BUDGET GOALS Solicitation PNC2116651P1  CREATE A 5-YEAR BUDGET  ASSIST BCWWS  IDENTIFY ALTERNATIVE FUNDING SOURCES (SECTION 319(H) GRANTS, TMDL GRANTS, SFWMD COOP FUNDING)

  13. DEVELOP CAPITAL IMPROVEMENT PLAN WE WILL ASSIST BCWWS EVERY STEP OF THE WAY! REGIONAL TRANSMISSION SYSTEM MASTER PLAN COUNTY PRESENTATION TO BCWWS ADMINISTRATOR COUNTY ASSESS NEEDS REVIEW COMMISSION (YEAR ROUND) (JUNE) (JULY) Solicitation PNC2116651P1 OMBC REVIEW COUNTY DEVELOPMENT OF FUNDING COMMISSION 5-YEAR CIP ANALYSIS REVIEW (APRIL TO MAY) (NOV. TO DEC.) (AUGUST) BCWWS OMBC PRIORITIZES CAPITAL PROGRAM SUBMITS CAPITAL PROJECTS ADOPTION REQUESTS (MARCH) (SEPTEMBER) (DEC. TO FEB.)

  14. DEVELOP EMERGENCY MANAGEMENT PLAN  AWWA MANUAL OF PRACTICE M19 REGIONAL TRANSMISSION SYSTEM MASTER PLAN  CATEGORIZE EVENTS (EMERGENCY, MAJOR, MINOR, NATURAL, OTHERS)  COMMUNICATION CHART (EMERGENCY CALL LIST)  CREATE RESPONSE FLOWCHART Solicitation PNC2116651P1  INTEGRATE GIS TOOLS  UTILIZE REAL-TIME SCADA INFO  STAFF TRAINING

  15. THE RIGHT TEAM FOR THIS PROJECT • T&A IS LOCAL AND AVAILABLE AT A MOMENTS REGIONAL TRANSMISSION SYSTEM MASTER PLAN RESPONSIVE NOTICE. • T&A HAS A 20 YEAR TRACK RECORD FOR EXPERIENCED DELIVERING BCWWS PROJECTS. • THE T&A TEAM HAS NATIONALLY RECOGNIZED Solicitation PNC2116651P1 COMPETENT EXPERTS THAT WILL SAVE TIME AND BUDGET. • THE T&A TEAM ELIMINATES REDUNDANT EFFICENT EFFORTS AND STREAMLINES TASKS. • THE T&A TEAM KNOWS THE BCWWS KNOWLEDGABLE PROCESSES, HISTORY AND GOALS.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend