REGIONAL TRANSMISSION
Broward County, Florida
Solicitation No. PNC2116651P1
REGIONAL TRANSMISSION Broward County, Florida SYSTEM MASTER PLAN - - PowerPoint PPT Presentation
REGIONAL TRANSMISSION Broward County, Florida SYSTEM MASTER PLAN Solicitation No. PNC2116651P1 Empower WWS with an Adaptive, Transparent and Defendable Regional Transmission System Master Plan ADAPTIVE MASTER PLAN & INNOVATIVE IDEAS &
Broward County, Florida
Solicitation No. PNC2116651P1
Empower WWS with an Adaptive, Transparent and Defendable
ADAPTIVE MASTER PLAN & DYNAMIC CIP INNOVATIVE IDEAS & NEW TECHNOLOGIES REDUNDANCY OF STAFF
planning cycle on their own after project completion
needed and the trigger for it
minimizing investments
tools
selector
platform
specialized in planning and asset management
assessment and master planning specialist, backed by B&V global resources
$
2
Ricardo Vieira
Project Manager
Amanda Schwerman
Master Plan Lead
3
4
Static Adaptive
RISK BASED
PRIORITIZATION
Pump Station Pipeline Emergency Plan
Based on Triggers
$20 M $18 M $6 M
DATA HUB
Key Performance
MODELING
Indicators Hydraulic, Transient / Surge
CAPITAL PLANNING
Capital, O&M, Inspections
$4 M
CIP Improvements are
Cash Flow (2015 dollars) $16 M $14 M $12 M $10 M $8 M
Important Triggers that Drive CIP
RawWaterIntake Pumping Treatment ControlValves WaterMain Storage
(cost of failure vs improvement)
$2 M $0 M
2015 2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039
Dynamic Master Planning allows the County to invest in projects only when needed.
5
Capacity and Redundancy Evaluations Condition and Reliability Evaluations
Comprehensive Capital Improvement Plan
Optimized CIP CIP Prioritization Identify Projects based
Analysis
WWS Planning & Operations Input
Transient Modeling Calibration System Evaluation Build Hydraulic Model Pipe Data Risk Prioritization WWS training Risk Prioritization Field Assessments Developing Emergency Plan Identify Projects based
(Monetizing Risk) CIP Spending Analysis (iCIP) Tool Selection & Inspection Plan Pump Station Data
Ricardo Vieira
Project Manager
Amanda Schwerman
Master Plan Lead
7
8
Innovyze’s InfoMaster Tool
data into a single platform
risk-based prioritization for rehab planning
Physical
Likelihood
Economic Characteristics Failure History
Likelihood of Failure (LoF) Consequence of Failure (CoF)
Economic-Based Replacement Strategy No Proactive Replacement Condition Monitoring- Based Strategy Predictive Monitoring Strategy Replace/ Re-design Strategy
5 10 15 20 25 4 8 12 16 20 3 6 9 12 15 2 4 6 8 10 1 2 3 4 5
Provides management strategies based on system risk
External Impacts Consequence
Environmental Social
9
Likelihood
Environmental Economic Failure History External Impacts
Likelihood of Failure (LoF)
739,398 $ 4,963,776 $ 15,334,741 $ 5,489,925 $
6,268,252 $ 49,423,588 $ 64,093,928 $ 35,576,623 $ 667,370 $ 16,430,675 $ 199,127,037 $ 276,683,409 $ 188,702,793 $ 6,768,894 $ 42,970,404 $ 261,686,497 $ 255,773,656 $ 346,974,606 $ 21,984,289 $ 1,647,806 $ 8,402,144 $ 15,177,510 $ 49,885,355 $ 9,811,598 $
Economic-Based Replacement Strategy No Proactive Replacement Condition Monitoring- Based Strategy Predictive Monitoring Strategy Replace/ Re-design Strategy
Physical Characteristics Consequence
Social
Consequence of Failure (CoF) Maximize Risk Reduction while Minimizing Investments
10
Inspection Protocol Report
Pipeline Condition Assessment
A value added Service of Select any of the following information for the pipe to be inspected
Severe Major Moderate Minor Negligible Gravity Pressurized Pumped Gas Sludge Wastewater Water ABS ACP CIP CMP CSP CU DIP ERCP FRPP GS HDPE NCS PE … Cement Mortar Medium-Thick Coatings Thin-filmed coating Isolation/Dewater/ cleaning Live 1” to 7” 8” to 35” 36” to 60” >60”
Technology Selection Support Tool
RUN REPORT RESET QUIT Major Pressurized Wastewater DIP 8” to 35” Cement Mortar Live X
Risk Rating Flow Fluid Material Coating / Lining Controls Diameter
Time Savings, Efficiencies and Consistency
Integrated Capital Improvement Tool (iCIP) is a Powerful Decision Support Tool
Mallard Connector Main Transmission Main Line Item Size Quantity Unit Cost Construction Cost 36" DIP (34000 lf) Pipe 1 36 ##### lf $244.27 /lf $8,305,300 N/A Pipe 2 0 lf $0.00 /lf $0 N/A Pipe 3 0 lf $0.00 /lf $0 36" BOL Connection BOL Connection 36 3 ea $33,980.00 /ea $101,900 36" EOL Connection EOL Connection 36 1 ea $33,980.00 /ea $34,000 36" Line Valves (17) Line Valve 36 17 ea $33,980.00 /ea $577,700 Blowoff Valves (7) Blowoff Valve 7 ea $6,000.00 /ea $42,000 N/A Fire Hydrant 0 ea $2,600.00 /ea $0 Cathodic Protection (34000 lf) Cathodic Protection ##### lf $5.00 /lf $170,000 N/A Major Roadway Crossing 0 lf $5,000.00 /lf $0 Secondary Road Crossing (750 lf) Secondary Road Crossing 750 lf $800.00 /lf $600,000 N/A Railroad Crossing 0 lf $5,000.00 /lf $0 N/A Stream Crossing 0 ea $20,000.00 /ea $0 Pavement Removal and Replacement (28000 SYD) Pavement Removal and Replacement ##### SYD $65.00 /SYD $1,820,000 Erosion Control (34000 lf) Erosion Control ##### lf $3.00 /lf $102,000 Restoration (34000 lf) Restoration ##### lf $2.50 /lf $85,000 Traffic Control (340 days) Traffic Control 340 days $1,500.00 /day $510,000 N/A Additional Construction Cost 1 N/A N/A N/A /N/A $0 N/A Additional Construction Cost 2 N/A N/A N/A /N/A $0 N/A Additional Construction Cost 3 N/A N/A N/A /N/A $0 N/A Additional Construction Cost 4 N/A N/A N/A /N/A $0 N/A Additional Construction Cost 5 N/A N/A N/A /N/A $0 N/A Additional Construction Cost 6 N/A N/A N/A /N/A $0 N/A Additional Construction Cost 7 N/A N/A N/A /N/A $0 N/A Additional Construction Cost 8 N/A N/A N/A /N/A $0 N/A Additional Construction Cost 9 N/A N/A N/A /N/A $0 N/A Additional Construction Cost 10 N/A N/A N/A /N/A $0 N/A Additional Construction Cost 11 N/A N/A N/A /N/A $0 Subtotal $12,347,900 Surveys, Record Documents, GPS Information $61,700 General Requirements (10%) $1,234,800 Contractor Fee (5%) $617,400 Mobilization (3%) $370,400 Contingencies (10%) $1,234,800 Total Construction Cost $15,867,000
We will provide Broward County with a dynamic CIP management platform
12
50 100 150 200 250 500 1,000 1,500 2,000 2,500 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Project Capital Cost (Nominal $Millions) Relative Asset Portofolio Risk
Criticality Safety Regulatory Financial Target Score Cumulative Capital Spend
Investment Drives Risk Reduction
13
13
Broward County Risk Assessment Dashboard
Monagement Group e A B
e c
rheld Beach
L~uderd~e·by
· ! he ·Se~nd Park Lauderdale
I> Bing
R1:.J;. Heat Map
Pipe Size (in) 6 54
Pipe ID Material Year Pipe Size (in)
Number of Sites Filtered
B ~
e:
WARD ~
Re.set
COUNTY
92
FLOR I DA
Management Group
Material
l ength of Pipe by Management Group (ft)
VCP •
A C
PVC • C S.JK RCP
)()()( I
B
DIP I RPM I Y
ear
1963 2010
Cross/ Ad1acen1
PACP Score
Liker.hood of
Consequence of RiskScore failure Score failure Score
...
SV0368 RCP 1%3 42 Cross
200 26
4.7 12.1
s
RCP 1963
36 Cross
2.33 2.6 4.7 12.4 LS0063 RPM 1976 27 Cross
38 46
17 7 ~ SV0367·M RCP 1963
42 Ad1~t
2.3 4.6
106 ~4
LS0078 RPM 1983 30 Cross
34 45
15.5
{!
~l.50004
xxx
1999
42 Adjaci.nt
21 4.5
9S
.,
RCP 1963 36 C1oss 2.33
23 4.5 10.7
2
.~3SV1342 RCP 2003 36 Adjaci.nt 2.45
25
4.S 11.2 SV0004-M RCP 1963
54 C1oss
2.03 26 4.5 11.6
.,
c SD0316 DIP 1990 30 CIOss 34 44 15.0
~SV0435 RCP 1963 39 Cross 2.50 2.5
4.4
11.2 g-2
6
~SV134S RCP 2003 30 Adjacent 2.60 24
44
10.S
u
LS0019 PVC 2008 42 Cross 0.00 1.3
4.4
58
v
SV0003·M RCP 1963
54 CIOSS
2.00
24
A.J 10.2
Rf"P1a;.1
~rmtt.c
, 7,
4l
<1.;J 4
~
BLACK &VEATCH
2
s
~"'
''
Likelihood of failure Total Score
Rafael Frias
Regional Manager
15
F O U N D E D I N
G L O B A L WO R K F O RC E
F L O R I DA P RO F E S S I O NA L S
O F F I C E S O N
C O N T I N E N T S P L A N N I N G A N D A S S E T M A NA G E M E N T P RO F E S S I O NA L S C O N T I N U O U S
F L O R I D A
P R E S E N C E S I N C E
Tampa Fort Myers Jacksonville
Orlando
F L O R I DA F L O R I DA C L I E N T S O F F I C E S
Lake Worth Coral Springs Coral Gables
16
Broward County, Florida
Solicitation No. PNC2116651P1