fresno reliability transmission projects
play

Fresno Reliability Transmission Projects Gary DeShazo Director, - PowerPoint PPT Presentation

Fresno Reliability Transmission Projects Gary DeShazo Director, Regional Transmission - North Board of Governors General Session March 25-26, 2010 Transmission is needed in the greater Fresno area by 2014 to maintain reliability. Need is


  1. Fresno Reliability Transmission Projects Gary DeShazo Director, Regional Transmission - North Board of Governors General Session March 25-26, 2010

  2. Transmission is needed in the greater Fresno area by 2014 to maintain reliability.  Need is associated with load growth in Fresno  Load growth limits opportunities for the Helms pump storage facility (Helms) to “recharge” its upper reservoir  Reliable electric service in Fresno is dependent on Helms generation  The availability of Helms to generate is dependent on its ability to “recharge”  A Helms reliability dispatch model was used to determine when reliability upgrades would be needed Slide 2

  3. The proposed transmission projects will address the reliability needs in the Fresno area Helms  Gregg Los Banos Fresno  Kings Transmission San Joaquin Network Merced  Panoche McCall Moss Landing Gates 500kV 230kV Slide 3

  4. The 2010 Transmission Plan identified these projects for approval by the ISO Board of Governors Project Estimated Cost Required In-Service Date (million) Reconductor Panoche-McMullin 230 kV line $14 May 2014 Reconductor Panoche-Helm 230 kV and Helm-McCall 230 kV lines $35 May 2014 Reconductor McMullin-Kearney 230 kV line $10 May 2015 Reconductor McCall-Henrietta 230 kV line $20 May 2014 Reconductor Certainteed-Legrand 115 kV line $13 May 2015 Replace terminal equipment on Henrietta-Gates 230 kV line section $2 May 2014 Replace wave traps on Panoche-Gates 1 & 2 230 kV lines $1 May 2014 Modifications to the Helms pump dropping SPS. $13 May 2014 Obtain interim night time temperature adjusted ratings on 7 transmission lines $13 May 2014 Install local SPS to trip McCall 115 kV firm load for Category C contingency $0.50 May 2014 Install SPS to trip firm load for the Helms-Gregg #1 and #2 230 kV DCTL $6 May 2014 contingency Total $127.50 Slide 4

  5. Panoche-Kearney and Henrietta-McCall 230 kV lines overload in 2014 with all lines in service scenario Reconductor Panoche-Kearney and Henrietta-McCall 230 kV lines by 2014 Henrietta- McCall line Slide 5

  6. Panoche-Helm and Helm-McCall, 230 kV lines overload in 2014 during contingency scenario Reconductor Panoche- Helm and Helm-McCall 230 kV lines by 2014 Slide 6

  7. Warnerville-Wilson, Wilson-Storey, Gates-Panoche, Kearney Herndon, Gates-Gregg 230 kV lines overload during contingency scenario Rerate various lines and modify Helms SPS by 2014 Gates- Gates- Gregg line Panoche lines Slide 7

  8. Management recommends that the Board approve the Fresno Reliability Transmission Projects The proposed projects will:  Address several reliability concerns in the Fresno area beginning in 2014  Provide the most cost-effective, feasible solutions to meet the identified needs in this area Slide 8

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend