Fresno Reliability Transmission Projects Gary DeShazo Director, - - PowerPoint PPT Presentation
Fresno Reliability Transmission Projects Gary DeShazo Director, - - PowerPoint PPT Presentation
Fresno Reliability Transmission Projects Gary DeShazo Director, Regional Transmission - North Board of Governors General Session March 25-26, 2010 Transmission is needed in the greater Fresno area by 2014 to maintain reliability. Need is
Slide 2
Transmission is needed in the greater Fresno area by 2014 to maintain reliability.
- Need is associated with load growth in Fresno
- Load growth limits opportunities for the Helms pump
storage facility (Helms) to “recharge” its upper reservoir
- Reliable electric service in Fresno is dependent on
Helms generation
- The availability of Helms to generate is dependent on its
ability to “recharge”
- A Helms reliability dispatch model was used to
determine when reliability upgrades would be needed
The proposed transmission projects will address the reliability needs in the Fresno area
Slide 3
Los Banos Gates Moss Landing McCall Panoche Helms Kings San Joaquin Merced
Fresno Transmission Network
Gregg
500kV 230kV
The 2010 Transmission Plan identified these projects for approval by the ISO Board of Governors
Slide 4
Project Estimated Cost (million) Required In-Service Date Reconductor Panoche-McMullin 230 kV line $14 May 2014 Reconductor Panoche-Helm 230 kV and Helm-McCall 230 kV lines $35 May 2014 Reconductor McMullin-Kearney 230 kV line $10 May 2015 Reconductor McCall-Henrietta 230 kV line $20 May 2014 Reconductor Certainteed-Legrand 115 kV line $13 May 2015 Replace terminal equipment on Henrietta-Gates 230 kV line section $2 May 2014 Replace wave traps on Panoche-Gates 1 & 2 230 kV lines $1 May 2014 Modifications to the Helms pump dropping SPS. $13 May 2014 Obtain interim night time temperature adjusted ratings on 7 transmission lines $13 May 2014 Install local SPS to trip McCall 115 kV firm load for Category C contingency $0.50 May 2014 Install SPS to trip firm load for the Helms-Gregg #1 and #2 230 kV DCTL contingency $6 May 2014 Total $127.50
Panoche-Kearney and Henrietta-McCall 230 kV lines
- verload in 2014 with all lines in service scenario
Reconductor Panoche-Kearney and Henrietta-McCall 230 kV lines by 2014
Henrietta- McCall line
Slide 5
Panoche-Helm and Helm-McCall, 230 kV lines
- verload in 2014 during contingency scenario
Reconductor Panoche- Helm and Helm-McCall 230 kV lines by 2014
Slide 6
Warnerville-Wilson, Wilson-Storey, Gates-Panoche, Kearney Herndon, Gates-Gregg 230 kV lines overload during contingency scenario
Rerate various lines and modify Helms SPS by 2014
Gates- Gregg line Gates- Panoche lines
Slide 7
Management recommends that the Board approve the Fresno Reliability Transmission Projects
The proposed projects will:
- Address several reliability concerns in the Fresno area
beginning in 2014
- Provide the most cost-effective, feasible solutions to
meet the identified needs in this area
Slide 8