Red Wing Bridge Project Red Wing City Council November 12, 2013 - PowerPoint PPT Presentation

Red Wing Bridge Project Red Wing City Council November 12, 2013 Overview of Past Progress Decided to proceed with new two-lane river crossing in current location Completed Bridge 9103 Rehabilitation Study Identified and refined


  1. Red Wing Bridge Project Red Wing City Council November 12, 2013

  2. Overview of Past Progress • Decided to proceed with new two-lane river crossing in current location • Completed Bridge 9103 Rehabilitation Study • Identified and refined recommended set of concepts for the MN and WI approach roadways • Identified three recommended river bridge types

  3. Rehab Bridge 9103

  4. Replace In-place

  5. Buttonhook

  6. Minnesota Approach Alternatives • Br 9103 Feasibility & Prudency • Evaluation centers on: – Purpose and Need – Cost Factors – SEE Factors • Contamination Issues

  7. Wisconsin Approach – Recommended Option

  8. New River Crossing Bridge Concepts TIED ARCH CONCRETE SEGMENTAL BOX GIRDER STEEL BOX GIRDER

  9. Tied Arch • Least approach roadway impacts • Requires periodic painting • Moderately complex construction & inspection • Highest construction cost

  10. Segmental Concrete Box Girder • Greatest approach roadway impacts • Does not require painting • Simpler construction & inspection • Most cost effective structure type

  11. Steel Box Girder • Moderate approach roadway impacts • Requires periodic painting • Simple construction & inspection • Cost effective structure type

  12. Classic Arch Bridge

  13. Contemporary Arch Bridge

  14. Classic Girder Bridge

  15. Contemporary Girder Bridge

  16. Next Steps • Continue drilling and environmental investigations; • Complete evaluation of the Minnesota approach alternatives and the three bridge types; • Obtain public input; • Identify the recommended Minnesota approach option and river bridge type; • Proceed with the Environmental Assessment (EA)

  17. Public Outreach Update • Listening Session #4 held earlier today • Open House #3 – early 2014 • Newsletter #3 – to be issued prior to Open House #3 • Project Presentation Opportunities • Website: http://www.dot.state.mn.us/d6/projects/redwing- bridge/index.html

  18. Questions / Comments Chad Hanson, P.E. Senior Design Engineer MnDOT – Rochester 507-286-7637 chad.hanson@state.mn.us

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.