RED WING BRIDGE PROJECT US 63 River Bridge and Approach Roadways - - PowerPoint PPT Presentation

red wing bridge project
SMART_READER_LITE
LIVE PREVIEW

RED WING BRIDGE PROJECT US 63 River Bridge and Approach Roadways - - PowerPoint PPT Presentation

RED WING BRIDGE PROJECT US 63 River Bridge and Approach Roadways Agenda Design Process Approach Roadways Design River Bridge Design Visual Quality Staging Project Schedule Right of Way Update Design Process


slide-1
SLIDE 1

RED WING BRIDGE PROJECT

US 63 River Bridge and Approach Roadways

slide-2
SLIDE 2

Agenda

  • Design Process
  • Approach Roadways Design
  • River Bridge Design
  • Visual Quality
  • Staging
  • Project Schedule
  • Right of Way Update
slide-3
SLIDE 3

Design Process

  • Preliminary Design/Environmental Review
  • Final Design: Approach Roadways
  • Minnesota
  • Wisconsin
  • Final Design: River Bridge
  • Letting
slide-4
SLIDE 4

Approach Roadways Design

slide-5
SLIDE 5

Approach Roadways Design

  • Box Culvert Replacement
slide-6
SLIDE 6

Approach Roadways Design

  • Pedestrian Ramps
  • Sidewalk along

Coca-Cola & Bluff St

slide-7
SLIDE 7

Approach Roadways Design

  • Remove Pond
  • Use Ditches and

Water Quality

  • Manholes instead
slide-8
SLIDE 8

River Bridge Design

slide-9
SLIDE 9

River Bridge Design

slide-10
SLIDE 10

River Bridge Final Design

slide-11
SLIDE 11

Visual Quality

  • Light Wash
slide-12
SLIDE 12

Visual Quality

  • River Bridge Piers
slide-13
SLIDE 13

Visual Quality

  • River Bridge overlook and spires (Day)
slide-14
SLIDE 14

Visual Quality

  • River Bridge overlook and spires (Evening)
slide-15
SLIDE 15

Visual Quality

  • Hwy 61 overpass bridge and retaining walls
slide-16
SLIDE 16

Visual Quality

  • Slip ramp bridge
slide-17
SLIDE 17

Visual Quality

  • Landscaping
slide-18
SLIDE 18

Visual Quality

  • Lighting Overview
slide-19
SLIDE 19

Visual Quality

  • Lighting Overview
slide-20
SLIDE 20

Visual Quality

  • MnDOT Standard Lighting
slide-21
SLIDE 21

Visual Quality

  • City of Red Wing Lighting
slide-22
SLIDE 22

Staging - 2017 – Stage 1A

Construction

  • Begin construction of River Bridge
  • Surcharge the poor soils for Wisconsin embankment
  • Construct temporary bridge over Hwy 61
  • Construct button-hook connection
  • Construct Hwy 61 east of the temporary bridge

Traffic

  • Hwy 63 traffic remains on existing River Bridge
  • One lane traffic each way on Hwy 61
  • 825th St closed at River Bridge and traffic detoured
slide-23
SLIDE 23

Staging - 2017 – Stage 1B

Construction

  • Begin construction of River Bridge
  • Surcharge the poor soils for Wisconsin embankment
  • Construct temporary bridge over Hwy 61
  • Construct button-hook connection
  • Construct Hwy 61 east of the temporary bridge

Traffic

  • Hwy 63 traffic remains on existing River Bridge
  • One lane traffic each way on Hwy 61
  • 825th St closed at River Bridge and traffic detoured
slide-24
SLIDE 24

Staging - 2018 – Stage 2

Construction

  • Construction of River Bridge
  • Construct new bridge over Hwy 61, slip ramp,

slip ramp bridge, 3rd Street, and Bluff Street

Traffic

  • Hwy 63 traffic remains on existing River Bridge and routed
  • nto temporary bridge and button-hook connection to new

signalized intersection with Hwy 61

  • 825th St closed at River Bridge and traffic detoured
  • 3rd St closed, traffic allowed thru at Potter St.
slide-25
SLIDE 25

Staging - 2019 – Stage 3

Construction

  • Construction of River Bridge
  • Construct Hwy 63 in Wisconsin

Traffic

  • Hwy 63 traffic remains on existing River Bridge and routed onto

temporary bridge and button-hook connection to new signalized intersection with Hwy 61

  • Two lane traffic each way on Hwy 61
  • 825th St closed at River Bridge and traffic detoured
  • 3rd St and Bluff St open
slide-26
SLIDE 26

Staging - 2020 – Stage 4A

Traffic

  • Hwy 63 traffic on new River Bridge
  • One lane traffic each way on Hwy 61
  • 825th St open at River Bridge
  • Slip ramp open

Construction

  • Construction of River Bridge complete, remove existing

River Bridge

  • Construct Hwy 61 under Hwy 63 bridge
slide-27
SLIDE 27

Staging - 2020 – Stage 4B

Traffic

  • Hwy 63 traffic on new River Bridge
  • One lane traffic each way on Hwy 61
  • 825th St open at River Bridge

Construction

  • Construction of River Bridge complete, remove

existing River Bridge

  • Construct Hwy 61 under Hwy 63 bridge
  • Slip ramp open
slide-28
SLIDE 28

Staging - 2020 – Stage 5

Construction

  • Construction of River Bridge complete, remove

existing River Bridge

  • Construct Hwy 61 under Hwy 63 bridge
  • Complete 825th St Ring Road

Traffic

  • Hwy 63 traffic on new River Bridge
  • One lane traffic each way on Hwy 61
  • 825th St open at River Bridge
  • Slip ramp open
slide-29
SLIDE 29

Project Schedule

  • Final design initiated: September 2015
  • Environmental review complete (FONSI): mid-March
  • Right-of-way acquisition: 2016
  • Final design complete: November 2016
  • Project letting: February 2017
  • Construction: 2017-2020
slide-30
SLIDE 30

Right-of-Way Process

  • Total Acquisitions (began February 2016)
  • Legal descriptions being prepared
  • Appraisals nearing completion
  • Environmental clearance needed
  • Partial Acquisitions/Easement
  • Construction limits currently being finalized
slide-31
SLIDE 31

Questions/Comments

Chad Hanson, P.E. David Koepp

MnDOT Project Manager WisDOT 507-286-7637 715-836-2078 chad.hanson@state.mn.us david.koepp@dot.wi.gov