P OTOMAC Y ARD M ETRORAIL S TATION P ROJECT Potomac Yard Metrorail Implementation Work Group September 25, 2019 A GENDA Permit Update Board of Architectural Review (BAR) Update PYC Construction Update Southwest Entrance Design


  1. P OTOMAC Y ARD M ETRORAIL S TATION P ROJECT Potomac Yard Metrorail Implementation Work Group September 25, 2019

  2. A GENDA • Permit Update • Board of Architectural Review (BAR) Update • PYC Construction Update • Southwest Entrance Design Process Update • Communications Plan Update • Discussion • Public Comment 2 PYMIG| September 25, 2019

  3. PERMIT UPDA TE • Joint Permit Application (JPA) – State Water Control Board Meeting • Held September 6 • The Board unanimously approved the Virginia Water Protection Permit for the Potomac Y ard Metrorail Station Project • DEQ issued a Virginia Water Protection (VWP) Individual Permit to the City on September 6 – US Army Corps of Engineers • Staff anticipates the Army Corps will issue its permit in the coming weeks. PYMIG| September 25, 2019 3

  4. B OARD OF A RCHITECTURAL R EVIEW (BAR) U PDATE • Held September 4 • BAR approved: – Mass and scale finalized – Materials sample board: • Bridge • Platform • Mezzanine • Upcoming meetings: – Exoskeleton finish – Lighting 4 PYMIG| September 25, 2019

  5. B OARD OF A RCHITECTURAL R EVIEW (BAR) U PDATE 5 PYMIG| September 25, 2019

  6. B OARD OF A RCHITECTURAL R EVIEW (BAR) U PDATE 6 PYMIG| September 25, 2019

  7. PYC C ONSTRUCTION U PDATE 7 PYMIG| September 25, 2019

  8. C OMPLETED W ORK • Continued working with the COA and WMATA to obtain the required permits • Established office complex • Established work zone at Carpenter Rd. • Cleared non-wetland areas • Installed access road to AC switchgear building • Excavated to subgrade at AC switchgear building • Continued with design • Completed documentation of existing conditions 8 PYMIG| September 25, 2019

  9. U PCOMING W ORK • AC Switchgear Building – Install grounding and electric stub outs – Excavate for foundation footings – Form and place foundation footings North Pavilion/Bridge Pier • – Establish work zone – Excavate to subgrade – Relocate storm drainage – Drive piles – Form and place pier caps and foundations Station • – Remove circle and replace with temporary park – Establish work zone in wetland area (pending receipt of permit) • Clear and grub area • Place fill • Perform soil stabilization • Continue with fill operations • Install utilities • Start station foundation 9 PYMIG| September 25, 2019

  10. S UMMARY L OOK A HEAD S CHEDULE 2019 ACTIVITY SEP OCT NOV DEC PERMITS STATION DESIGN ADJUST TRAFFIC CIRCLE SECURE AND SETUP PARKING/STAGING AREAS/TRAILERS CONSTRUCTION OF AC SWITCHGEAR BUILDING PLACE FILL FOR STATION PREPARE SITE FOR FILL OPERATIONS PLACE FILL FOR STATION SOIL IMPROVEMENTS CONSTRUCT NORTH PAVILION/PIER Drive Piles SET UP 2601 MAINLINE BLVD 10 PYMIG| September 25, 2019

  11. A CTIVE C ONSTRUCTION – AC S WITCHGEAR B UILDING 11 PYMIG| September 25, 2019

  12. C ONSTRUCTION F ENCE W RAP 12 PYMIG| September 25, 2019

  13. T RAFFIC AND P ARKING B OARD A PPROVALS • Tennis Court Parking Removal – Traffic and Parking Board Approved 7/22/19 • Traffic Circle and MOT Plan – Presented during the 8/5/19 PYMIG meeting – Traffic and Parking Board Approved 9/23/19 • 2601 Mainline Blvd. – Presented to PYMIG tonight • Slaters Ln. & Potomac Greens Dr. – PYC is investigating potential modifications 13 PYMIG| September 25, 2019

  14. M AINTENANCE OF T RAFFIC (MOT) P LAN 14 PYMIG| September 25, 2019

  15. M AINTENANCE OF T RAFFIC (MOT) P LAN 15 PYMIG| September 25, 2019

  16. M AINTENANCE OF T RAFFIC (MOT) P LAN 16 PYMIG| September 25, 2019

  17. 2601 M AINLINE B LVD . Removal of Removal of 3 parking 3 parking spaces to spaces to allow for allow for truck new site movement entrance into site 17 PYMIG| September 25, 2019

  18. S OUTHWEST E NTRANCE D ESIGN PROCESS U PDATE • September/October – Contractor on schedule to complete alternative cost estimate analysis – Staff will present outcome of the analysis to PYMIG – Results of the alternatives cost estimate analysis will be presented to Council PYMIG| September 25, 2019 18

  19. C OMMUNICATIONS P LAN • City Website – Construction updates page • Social Media Coverage • Monthly Newsletter • Press Releases – eNews - City-wide news feed • Project Announcements – eNews - Potomac Yard Metrorail Station news feed • Community Feedback Opportunities 19 PYMIG| September 25, 2019

  20. Discussion 20 PYMIG| September 25, 2019

  21. U PCOMING M EETINGS • Board of Architectural Review (BAR) – Anticipated: October 16, 2019 • PYMIG Meetings – October and November Dates TBD – Waiting on Council budget work session schedule to be finalized 21 PYMIG| September 25, 2019

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.