project management project management
play

Project management Project Management A project is a temporary - PowerPoint PPT Presentation

Project management Project Management A project is a temporary endeavour to produce a unique product, service, or result (PMI 2004). Project management (PM) techniques were originally developed Dr. James A. Bednar for engineering


  1. Project management Project Management A project is ‘a temporary endeavour to produce a unique product, service, or result’ (PMI 2004). Project management (PM) techniques were originally developed Dr. James A. Bednar for engineering projects like building construction. jbednar@inf.ed.ac.uk PM focuses on planning, scheduling, monitoring, and http://homepages.inf.ed.ac.uk/jbednar controlling the complex interdependencies among subtasks. PM techniques are most relevant when considering the entire project in which software development is embedded, which includes other activities such as documentation, training, hardware, etc. SAPM Spring 2012: Project Management 1 SAPM Spring 2012: Project Management 2 Example project Project management tasks Consider building a garden Probably before work starts, need to figure out: shed, which involves Roof • What needs to be done designing the shed, Framing figuring out what materials • What order they can be done Siding are needed, ordering or • How long each will take purchasing the materials, • How long the whole project must take in principle and putting together the various parts. Foundation • How long the whole project is expected to take, given finite resources Some of these tasks depend on the others, some must be scheduled, some take labor, etc. SAPM Spring 2012: Project Management 3 SAPM Spring 2012: Project Management 4

  2. Project scope statement Work breakdown structure In order to make any decisions about the project, it needs A WBS is a diagram showing the major subtasks of the to be made concrete (no pun intended). This is done by project: Build Shed writing a scope statement, such as: • We will build a garden shed capable of holding 2 bicycles, a lawn mower, and a small workbench Planning Obtaining Materials Constructing • Planning permission will not be needed Pour foundation Build frame • We will not connect it to electric or water mains Install siding • It cannot cost more than 1000 pounds or take longer Install roof Finish (door, etc.) than 1 month (may be a constraint rather than scope) Rule of thumb: break things down as far as necessary to Note that the scope statement includes not only what it will estimate and schedule them, and no further. do, but what will not be included. SAPM Spring 2012: Project Management 5 SAPM Spring 2012: Project Management 6 Network diagram Critical path Design Materials list Order materials Deliver materials Design Materials list Order materials Deliver materials 1 day 1 day 1 day 7 days 1 day 1 day 1 day 7 days Install siding 1 day Install siding Pour foundation Build frame Finish 1 day 2 days 1 day 1 day Install roof Pour foundation Build frame Finish 2 days 1 day 2 days 1 day Install roof The critical path is the longest path through the network 2 days diagram – it is the minimum duration of the project if there are infinite resources (so that tasks can occur in parallel) Network diagrams can be constructed from the WBS, and accurate estimates. adding dependencies and estimated durations. Note that you can have different network diagrams for the same Here, everything but putting up the siding is on the critical project, depending on your assumptions and approach. path, and must happen in the order specified. SAPM Spring 2012: Project Management 7 SAPM Spring 2012: Project Management 8

  3. Slack PERT/CPM Charts Design Materials list Order materials Deliver materials Network diagrams come in a variety of flavors with 1 day 1 day 1 day 7 days different names: Install siding 1 day A Program Evaluation and Review Technique (PERT) Pour foundation Build frame Finish 1 day 2 days 1 day Install roof chart shows dependencies and time estimates, using 2 days 3-point estimates. Tasks not on the critical path have slack – the duration by which they can be late without making the project later The Critical Path Method (CPM) chart is a related than the critical path duration. alternative, using single estimates. Here, putting up the siding has one day of slack: one day Both show similar information, but use different methods longer than estimated is ok, but if it takes longer it will be for calculating the critical path and slack. the new critical path, and delay the project. SAPM Spring 2012: Project Management 9 SAPM Spring 2012: Project Management 10 Gantt Chart Gantt Chart extras A Gantt chart shows the tasks and their durations Gantt charts can also show summary activities graphically, in calendar form, with one bar per activity. (see ‘Planning’ entry), dependencies (arrows), and The bar shows the earliest start date and expected milestones (diamonds). duration. The dependencies make slack clear (see “Siding” entry). SAPM Spring 2012: Project Management 11 SAPM Spring 2012: Project Management 12

  4. Resources Crashing/Fast tracking All these charts assume infinite resources – things that If the critical path is still not fast enough, it’s possible to can logically happen in parallel, are assumed to happen in shorten the duration by changing some assumptions. E.g.: parallel. Crashing: Change the duration of some critical task, e.g., In reality, there are limited resources, so there are often if it is possible to parallelize it by assigning more many dependencies not shown in the charts. people to it. Fast tracking: Allow tasks to be done in parallel by E.g. if only one person is available to work on the shed changing the logic in the network diagram. project, the siding and roofing tasks must be done in serial, due to the resource constraint. If tasks can be parallelized (as in building construction) these allow total duration to be greatly reduced. SAPM Spring 2012: Project Management 13 SAPM Spring 2012: Project Management 14 For more info Use PM for your software project? Project Management Institute (PMI): Largest Why? SW is just a project like any other, with tasks, international PM organization; US-based ( pmi.org ) interdependencies, resources, etc. Right? Why not? The vast majority of SW development tasks cannot International Project Management Association (IPMA): be estimated up front – doing so requires knowing the Oldest international PM organization requirements and the design, plus how long debugging will ( www.ipma.ch ) take, and after those three tasks there’s very little work left. Association for Project Management (APM): UK-based Clear win for PM: SW projects embedded into larger projects. national organization ( www.apm.org.uk ) Here, the SW must be delivered on time for the rest of the project PM Glossary: to succeed, and depends on the other parts. In such cases, PM www.maxwideman.com/pmglossary/ is very useful. Within the SW-only portion, perhaps not. SAPM Spring 2012: Project Management 15 SAPM Spring 2012: Project Management 16

  5. Summary References • Project management charts and techniques are useful PMI (2004). A Guide to the Project Management Body of Knowledge (3rd Ed.). Project Management Institute. for scheduling tasks with complex dependencies • WBS: main tasks • Network diagram: dependencies, durations • Gantt: calendar • Be careful not to trust the charts just because they look fancy; e.g., many constraints are not shown • See website for required and optional readings SAPM Spring 2012: Project Management 17 SAPM Spring 2012: Project Management 17

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend