Unit 5 The World of Project Management and The Role of Project - - PDF document

unit 5
SMART_READER_LITE
LIVE PREVIEW

Unit 5 The World of Project Management and The Role of Project - - PDF document

Unit 5 The World of Project Management and The Role of Project Manager Source: Project Management in Practice, 5th Edition, Mantel, Meredith, Shafer, Sutton, Wiley, 2014. Project Management: A Systems Approach to Planning, Scheduling, and


slide-1
SLIDE 1

Source: Project Management in Practice, 5th Edition, Mantel, Meredith, Shafer, Sutton, Wiley, 2014. Project Management: A Systems Approach to Planning, Scheduling, and Controlling, 10th Edition, Harold Kerzner, Wiley, 2009.

Unit 5

The World of Project Management and The Role of Project Manager

  • 1. The World of Project

Management

2

slide-2
SLIDE 2

What is a Project?

A project is any task within an organization that does not fit neatly into ‘business-as-usual’. The “Big Dig” project in Boston and the “787 Dreamliner” project at Boeing are two examples of large scale projects. On smaller scale, an individual might self‐build a new house, a car manufacturer may want to develop a new engine or a company may want to set up a quality system. In the school context, students are given a design and make project which needs to be managed – although on a smaller scale – using many of the same principles as the larger projects. Example: Redesigning a shopping cart https://www.youtube.com/watch?v=M66ZU2PCIcM

3

Who is Involved?

In industry, many projects are complex and may involve input from people with different kinds of knowledge and expertise. Projects usually involve a team who are managed by a project manager or project leader who may be appointed for the duration of the project. It is worth noting that project management is adopted as a career specialism by many engineers and is considered to be a mainstream engineering discipline.

4

slide-3
SLIDE 3

Definition of a Project

  • 1. A temporary endeavor undertaken to create a unique

product or service. (PMI 2008)

  • 2. A project is a formal enterprise that addresses the matter
  • f designing and developing the various systems.
  • 3. A project is typically defined as a collaborative enterprise,

frequently involving research or design, that is carefully planned to achieve a particular aim.

  • 4. A planned set of interrelated tasks to be executed over a

fixed period and within certain cost and other limitations.

  • 5. A project is specific and unique with a specific deliverable

aimed at meeting a specific need or purpose.

5

Project Characteristics

  • Have a specific objective (which may be unique
  • r one‐of‐a‐kind) to be completed within certain

specifications

  • Have defined start and end dates
  • Have funding limits (if applicable)
  • Consume human and nonhuman resources (i.e.,

money, people, equipment)

  • Be multifunctional (cut across several functional

lines)

  • Often involve conflicts

6

slide-4
SLIDE 4

Overview of Project Management

Project management techniques originated in industry to address the need for managing increasingly complex activities such as civil and mechanical engineering projects. The techniques involved are something quite different in scope and purpose from the ‘Design Process’ that is familiar to the engineers. Project management concentrates on the management of resources and time

  • ver the life cycle of a project in a systematic manner.

Project management involves applying a systematic approach to achieving the objectives of the project.

7

Definition of Project Management “The application of knowledge, skills, tools, and techniques to a broad range of activities in order to meet the requirements of a particular project.”

Project Management Institute 2007

8

slide-5
SLIDE 5

Why the Emphasis on Project Management?

  • Many tasks do not fit neatly into business‐as‐

usual

  • Organizations need to assign responsibility

and authority for the achievement of their goals

Project Management Include

  • Project Planning

– Definition of work requirements – Definition of quantity and quality of work – Definition of resources needed

  • Project monitoring

– Tracking progress – Comparing actual outcome to predicted outcome – Analyzing impact – Making adjustments

10

slide-6
SLIDE 6

Trends in Project Management?

Project management techniques are increasingly used for: Achieving Strategic Goals – e.g. Boeing 787 dreamiliner Achieving Routine Goals – e.g. routine machine maintenance Improving Project Effectiveness – e.g. creation of project

management office

Organizing Virtual Projects – e.g. Microsoft Windows 10

development involves global teams whose members operate in different countries, time zones.

Handling Quasi‐Projects – e.g. a new drug development in a

pharmaceutical company without a clearly defined objective, a fixed deadline, and a determined budget.

11

Project Management vs. General Management

Project management differs from general management as “projects” differs from “nonprojects”

 General management deals with “routine” work, project management deals with “unique” work.  General manager “manage by exception”. Project manager only deals with the exceptions.  General management success is dependent on good planning. Project success is absolutely dependent on carefully detailed planning.  “Non‐project” budget follows standard budgeting procedures while project budget is prepared from scratch, delivered directly.  “Non‐project” rarely crossing organization functional boundaries and the projects crossing them freely.  Managerial hierarchy is well defined in general management while it is informal in project management.

12

slide-7
SLIDE 7

Project Budgets

  • Project budgeting differs from standard budgeting in

the way budgets are constructed

  • Budgets for non‐projects are primarily modifications
  • f budgets for the same activity in the previous

period

  • Project budgets are newly created for each project

and often cover several “budget periods” in the future

Project Schedules

  • In manufacturing, the sequence of activities is

set when production line is designed

– Sequence is not altered when new models are produced

  • Each project has a schedule of its own

– Previous projects with deliverables similar to current one may provide a rough template – However, a specific schedule unique to the project at hand has to be prepared from scratch

slide-8
SLIDE 8

Project Organizational Structure

  • Routine work of organizations takes place within a

well‐defined structure

– The divisions, departments, sections, and similar subdivisions of the total unit

  • Typical project cannot thrive in this structure
  • The need for technical knowledge, information, and

special skills requires that departmental lines be crossed

– The multidisciplinary character of projects

Globalization

  • When large firms establish manufacturing plants or

distribution centers in different countries, a general management team is established on site

  • For projects, globalization has a different meaning

– Members of project teams may be spread across countries and speak different languages – Some project team members may never have a face‐to‐ face meeting

slide-9
SLIDE 9

Negotiation

  • With little authority, the project manager

depends on negotiation skills to gain the cooperation of departments in the

  • rganization
  • Those departments have their own objectives,

priorities, and personnel

  • The project is not their responsibility and the

project tends to get the leftovers

Three Different Types of Negotiation

  • 1. Win‐win
  • 2. Win‐lose
  • 3. Lose‐lose

Unlike general managers, project managers have responsibility for accomplishing a project but little or no legitimate authority to command the required resources from other departments. The PM must be skilled at win‐win negotiation to obtain these resources.

slide-10
SLIDE 10

What is Managed?

Project management refers to the administration of the project, its supervision and organization. It means analyzing the objectives of the project, defining the tasks needed to achieve these objectives and controlling the execution. Projects have three interrelated goals, these are to:

  • Finish on time
  • Meet the scope (specifications that satisfy the clients)
  • Meet the budget limit

19

Scope, Cost, and Time Project Performance Goals

The performance of the project and PM is measured by the degree to which these goals are achieved.

20

slide-11
SLIDE 11

Tradeoffs between Scope, Cost, and Time

The primary method of adapting to unpredicted change is to trade off one objective for another.

  • Project falls behind schedule → Add more resources.
  • Budget is short → Negotiate a later delivery date.
  • Neither cost nor schedule is negotiable → take less

profit.

  • When there is no acceptable ways to deal with the

problem → terminate the project.

21

Abilities Needed for Effective Project Management  Ability to resolve conflicts  Creativity and flexibility  Ability to adjust to change  Good planning skills  Negotiation skills

  • win‐win versus win‐lose or lose‐lose

22

slide-12
SLIDE 12

The Life Cycle of Projects

A project’s life cycle measures project completion as a function of time or resource.

 During the early stages, the PM must make sure that the project reflects the wishes of the client as well as the abilities

  • f the project team.

 During the implementation stage, the PM is focused of keeping the project on budget and schedule.  Toward the end of the project, the PM’s attention is to assure that the project’s specifications are truly met.

23

The Life Cycle of Projects

 All organisms have a life cycle (i.e., they are born, grow, wane, and die) … and so do projects  Some projects follow an S‐shaped curve … they start slowly, develop momentum, and then finish slowly (e.g. building a house)  Other project follow a J‐shaped curve … they start slowly , proceed slowly, and then finish rapidly (e.g. cooking or baking a cake)

24

slide-13
SLIDE 13

Figure 1‐2 The S‐Shaped Project Life Cycle

25

Figure 1‐3 The J‐Shaped Project Life Cycle

26

slide-14
SLIDE 14

Selecting Projects to Meet Organizational Objectives

 Project selection is the process of evaluating individual projects or groups of projects and then choosing to implement a set of them so that the objectives of the parent organization is achieved.  Conditions considered in selection

 Is it profitable? (meeting return on investment target?)  Is it required by law? (a mandate?)  Does the firm have the knowledge and skill to carry it out?  Does the project involve building competencies, consistent with the firm’s strategy?  Does the firm has the capacity to carry it out on schedule?  If R&D project, could the technical success bring economic success?

27

Nonnumeric Selection Methods

 The “Sacred Cow”‐ a pet project advocated by a

senior executive of the firm.

 The operating/competitive necessity –

any project that is necessary for the continued

  • peration of the firm.

 Comparative benefits – among complex

projects, selection could be made by individuals in the committee through rank‐ordering, such as the Q‐sort method.

28

slide-15
SLIDE 15

The Q‐Sort Method

First, separate projects into “High”, and “Low” subsets. If there are more than 7 or 8 in a group, further separate each of them into, for example, “High” and “Medium”; or “Medium” and “Low”. If necessary, rank the projects in the “High” subset into “Very High” and “High”; and “Low” into “Low” and “Very Low”. Arrange the subsets in order of rank to

  • btain the list of orders.

29

Numeric Selection Methods

 Financial assessment methods

  • payback period
  • discounted cash flow
  • opportunity cost analysis

 Scoring methods

  • unweighted 0‐1 factor method
  • weighted factor scoring method

30

slide-16
SLIDE 16

Payback Period

Inflows Cash Net Annual Investment Fixed Initial  n

The Payback Period represents the amount of time that it takes for a Capital Budgeting project to recover its initial cost. Example ‐ A project with an initial investment of $100,000 and an annual return of $25,000 each year, the payback period, n = $100,000/$25,000 = 4 years.

* Problem – not consider time value of money

31

Cash Flow Analysis

  

n t t t

r F

1

) 1 ( I

  • (project)

NPW

where I0 = the initial investment Ft = the net cash flow in period t r = the required rate of return

If considering inflation for period t, the discounting term (1+r)t becomes (1+r+p)t

32

slide-17
SLIDE 17

PsychoCeramic Science, Inc. – Prepare a net present worth analysis using an interest rate of 13% and an inflation rate of 2%

16 12 13 14 15 17 21 19 20 22

$125

18

$100 $90 $50 $105 $115 $90 $97 $75 $82 $65 $35

NPW = ‐$125,000‐$100,000(1+0.13+.02)‐1‐$90,000((1+0.13+.02)‐2 +$50,000((1+0.13+.02)‐3 + ….+ ($65,000+$35,000)((1+0.13+.02)‐10 = $17,996.77 Since NPW >0, select the project

Cash Flow Analysis ‐ Example

33

Cash Flow Analysis‐ Example

A B C D E F G

Discount Factor

NPW Inflation Year Inflow Outflow Net Flow

1/(1 + r + p)t

D x E Rate (p) 2013* 0.00 125,000.00 -125,000.00 1.0000

  • 125,000.00

0.02 2013 0.00 100,000.00 -100,000.00 0.8696

  • 86,956.52

0.02 2014 0.00 90,000.00

  • 90,000.00

0.7561

  • 68,052.93

0.02 2015 50,000.00 0.00 50,000.00 0.6575 32,875.81 0.02 2016 120,000.00 15,000.00 105,000.00 0.5718 60,034.09 0.02 2017 115,000.00 0.00 115,000.00 0.4972 57,175.32 0.02 2018 105,000.00 15,000.00 90,000.00 0.4323 38,909.48 0.02 2019 97,000.00 0.00 97,000.00 0.3759 36,465.89 0.02 2020 90,000.00 15,000.00 75,000.00 0.3269 24,517.63 0.02 2021 82,000.00 82,000.00 0.2843 23,309.52 0.02 2022 65,000.00 65,000.00 0.2472 16,067.01 0.02 2022 35,000.00 35,000.00 0.2472 8,651.46 0.02 Total 759,000.00 360,000.00 399,000.00 17,996.77

34

slide-18
SLIDE 18

Opportunity Cost Analysis

Opportunity cost is the cost of any activity measured in terms of the value of the next best alternative forgone (that is not chosen). It is the sacrifice related to the second best choice available to someone, or group, who has picked among several mutually exclusive choices. For example, if an asset such as capital is used for one purpose, the opportunity cost is the value of the next best purpose the asset could have been used for. Opportunity cost analysis is an important part of a company's decision‐ making processes, but is not treated as an actual cost in any financial statement.

35

Opportunity Cost Analysis – An Example

 Noel has just graduated from a medical college and has been offered a job at a prestigious hospital in town with $45,000 a year. His uncle, who runs a health care and fitness center, has also offered him a position for $35,000 a year. However, Noel chose to enroll for a medical research program at a local university, which would cost him $38,000 a year.

Solution: Number of Economic Alternatives = 3 ($45,000 job, $35,000 job and ‐

$38,000 research program) Desired Alternative = ‐ 38,000 Next Best Alternative = 45,000 Since, Opportunity Cost = Cost of Selected Alternative ‐ Cost of Next Best Alternative Therefore, Opportunity Cost = ‐38,000 ‐45,000 = ‐83,000 Hence, his opportunity cost not only includes the cost his Desired Alternative would incur but also the value of the Next Best Alternative which he gives up.

36

slide-19
SLIDE 19

The Unweighted 0‐1 Scoring Model

37

Unweighted 0‐1 Scoring Model ‐ A set of relevant factors is selected by management & then listed in a printed form. One or more raters score the project on each factor, whether or not it qualifies for an individual criterion.

The Weighted Scoring Model

n j j ij i

w s S

1

where Si = the total score of the ith project sij = the score of the ith project on the jth criterion wj = the weight or importance of the jth criterion

38

slide-20
SLIDE 20

 A college student needs to purchase a car. There are two primary criteria, “cost” and “reliability”, and everything else a “nicety”. Three alternatives are identified. A 5‐point scale is used in each criterion.

Weighted Scoring Model‐ Example

Criteria Cost Reliability Niceties Weights 0.4 0.4 0.2 Alternative Total A 3 2 4 2.8 B 2 4 1 2.6 C 4 3 1 3.0

39

Uncertainty

  • All projects are always carried out under conditions
  • f uncertainty

– Projects are all about uncertainty

  • Effective project management requires an ability to

deal with uncertainty

  • Projects are complex and include interfaces,

interdependencies, and assumptions, which may turn out to be wrong

– People add to the uncertainty

40

slide-21
SLIDE 21

Uncertainties Encountered in Project Management

 Time required to complete a project  Availability and cost of key resources  Timing of solutions to technological problems  Macroeconomic variables  The whims of clients  Actions taken by competitors

41

Can Uncertainty be Eliminated?

 No … uncertainty cannot be

  • eliminated. However, if managed

properly, it can be minimized

42

slide-22
SLIDE 22

Managing Risk

  • The first step in managing risk is to identify

potentially uncertain events and likelihood of

  • ccurrence

– Called risk analysis

  • Different organizations approach this differently
  • The essence of risk analysis is to make assumptions

about key risk parameters and to use models to evaluate the desirability of certain managerial decisions

43

Risk Analysis

Estimate probabilities or distributions associated with key parameters Construct a mathematical model of the situation and run a simulation ... given various scenarios Analyze distribution of outcomes generated by model

44

slide-23
SLIDE 23

Risk Analysis with Crystal Ball

45

To load Crystal Ball within Microsoft Excel: 1.Click the Office button,

  • r select the File ribbon.

2.Click the Microsoft Excel Options button, and then click the Add-I ns link. 3.In the Manage list at the bottom of the Add-Ins dialog, select COM Add-I ns and click Go. 4.In the COM Add-I ns dialog, select Crystal Ball. 5.Click OK to close the dialog and open Crystal Ball within Microsoft Excel. To unload Crystal Ball from within Microsoft Excel, follow steps 1 through 3 and then clear Crystal Ball in step 4.

Risk Analysis with Crystal Ball

 Assumption Cells  Distribution Gallery  Forecast Cells

46

slide-24
SLIDE 24

Risk Analysis with Crystal Ball – An Example

Find the total cost of a project with 5 phases

 Assumption Cells  Define Assumption  Distribution Gallery  Forecast Cells

47 47

Risk Analysis with Crystal Ball – An Example

 Press Start  Extract Data Check Statistics

48

Statistics Total Cost Trials 1000 Base Case $79,200 Mean $79,431 Median $79,784 Mode ‐‐‐ Standard Deviation $7,533 Variance $56,739,465 Skewness ‐0.0407 Kurtosis 3.18

  • Coeff. of Variation

0.0948 Minimum $57,827 Maximum $112,603 Range Width $54,777 Mean Std. Error $238

slide-25
SLIDE 25

Risk Analysis with Crystal Ball – An Example

 Find the probability that the total cost will be less than $85,000

49

Risk Analysis with Crystal Ball

An Example

PsychoCeramic Science, Inc. – Considering the installation of a new manufacturing line with the following cash flows –

End of Year Inflow Outflow Net Flow End of Year Inflow Outflow Net Flow 2013* 0.00 125,000.00 -125,000.00 2018 105,000.00 15,000.00 90,000.00 2013 0.00 100,000.00 -100,000.00 2019 97,000.00 0.00 97,000.00 2014 0.00 90,000.00

  • 90,000.00

2020 90,000.00 15,000.00 75,000.00 2015 50,000.00 0.00 50,000.00 2021 82,000.00 0.00 82,000.00 2016 120,000.00 15,000.00 105,000.00 2022 65,000.00 0.00 65,000.00 2017 115,000.00 0.00 115,000.00 2022 35,000.00 0.00 35,000.00

50

slide-26
SLIDE 26

PsychoCeramic Science, Inc. – Prepare a net present worth analysis using an interest rate of 13% and an inflation rate of 2%

16 12 13 14 15 17 21 19 20 22

$125

18

$100 $90 $50 $105 $115 $90 $97 $75 $82 $65 $35

NPW = ‐$125,000‐$100,000(1+0.13+.02)‐1‐$90,000((1+0.13+.02)‐2 +$50,000((1+0.13+.02)‐3 + ….+ ($65,000+$35,000)((1+0.13+.02)‐10 = $17,996.77 Since NPW >0, select the project

Risk Analysis with Crystal Ball

51

Risk Analysis with Crystal Ball

 PsychoCeramic Science, Inc. – Pessimistic, Most Likely, and Optimistic Estimates for Cash Inflows

  • Use BetaPERT distribution as the p.d.f. for the inflow
  • Use Normal distribution as the p.d.f. for inflation rate with a mean of

0.02 and a std. dev. Of 0.0033

52

End of Pessimistic Most Likely Optimistic End of Pessimistic Most Likely Optimistic Year Inflow Inflow Inflow Year Inflow Inflow Inflow 2015 35,000.00 50,000.00 60,000.00 2020 75,000.00 90,000.00 100,000.00 2016 95,000.00 120,000.00 136,000.00 2021 67,000.00 82,000.00 91,000.00 2017 100,000.00 115,000.00 125,000.00 2022 51,000.00 65,000.00 73,000.00 2018 88,000.00 105,000.00 116,000.00 2022 30,000.00 35,000.00 38,000.00 2019 80,000.00 97,000.00 108,000.00

slide-27
SLIDE 27

Risk Analysis with Crystal Ball

 PsychoCeramic Science, Inc. –

53

Risk Analysis with Crystal Ball

 PsychoCeramic Science, Inc. –

Statistics Net Present Value of Project Trials 1000 Base Case 17,996.77 Mean 14,423.78 Median 14,558.57 Mode

  • Standard Deviation

6,963.06 Variance 48,484,240.19 Skewness

  • 0.1192

Kurtosis 2.86

  • Coeff. of Variability

0.4827 Minimum

  • 6,805.37

Maximum 35,540.09 Range Width 42,345.46 Mean Std. Error 220.19

54

slide-28
SLIDE 28

The Project Portfolio

  • A collection of projects grouped to be

collectively managed.

  • Projects are selected to contribute to the
  • rganization’s goals.
  • Portfolio alignment identifies, selects, and

prioritizes projects to help achieve an

  • rganization’s strategic goals.

55

Steps in the Project Portfolio Process (PPP)

The PPP Attempts to link the organization’s projects directly to the goals and strategy of the organization … is also a means for monitoring and controlling the organization’s strategic projects. Steps are ‐

Establish a project council Identify project categories and criteria Collect project data Assess resource availability Reduce the project and criteria set Prioritize the projects within categories Select the projects to be funded and those to be held in reserve Implement the process

56

slide-29
SLIDE 29

Aggregate Project Plan

  • An aggregate project plan (APP) is the process
  • f creating development goals and objectives

and using these goals and objectives to improve productivity as well as development

  • capabilities. The purpose of this process is

generally to ensure that each project will accomplish its development goals and

  • bjectives. Projects can be differentiated into

four types of projects: derivative, platform, breakthrough, and R&D projects.

57

Categories of Projects in Aggregate Project Plan Derivative projects … those that are only incrementally different from existing offerings Platform projects … major departures from existing offerings … the next generation Breakthrough projects … involving a newer technology … possibly a “disruptive” technology R&D projects … “blue sky” or visionary endeavors

58

slide-30
SLIDE 30

The Aggregate Project Plan

59

Murphy’s Laws in Project Management

Projects progress quickly until they are 90% complete. Then they remain at 90% complete forever. When things are going well, something will go wrong. When things just can’t get worse, they will. When things appear to be going better, you have

  • verlooked something.

If project content is allowed to change freely, the rate of change will exceed the rate of progress. Project teams detest progress reporting because it manifests their lack of progress.

60

slide-31
SLIDE 31
  • 2. The Manager, the Organization,

and the Team

61

Introduction

  • Project manager usually selected after project is

selected

  • It is job of project manager to make sure that the

project is properly planned, implemented, and completed

  • Project manager then recruits qualified people for

the project

  • Learning project tools and techniques is easy,

succeeding as a project manager is hard

62

slide-32
SLIDE 32

Project Manager’s Job

Make sure that the project is properly planned, implemented, and completed. The hard parts ‐  Playing the many roles of PM.  Negotiating with stubborn functional managers and clients.  Keeping the peace among project team members.  Dealing with senior managers.  Being surrounded by the chaos of trying to run the project in the organization.

63

Project Manager’s Roles

 Manager‐as‐facilitator versus manager‐as‐

  • supervisor. PM is usually not a competent overseer in various areas
  • f the project and thus had a different role – the facilitator.

 Use of a systems approach as opposed to an analytical approach that could lead to

  • suboptimization. Study the bits and pieces in the system and

how they fit together, how they interact, and how they affect and are affected by their environment.

 Avoid micromanagement, one of the deadly managerial sins.  Communicate … ensure that project team members have appropriate knowledge and

  • resources. Responsible to the project team, to senior management,

to the client, and to any other stake holders.

64

slide-33
SLIDE 33

Manager as Communicator

Communication paths between a project’s parties‐ at‐interest

Solid line – the PM’s communication channels. Dotted line – other communication path bypassing PM.

65

Virtual Project Manager

 Geographically dispersed project teams. For

example, aircraft production, many parts are carried out by different organizations in different locations.

 Communication via

  • email
  • web
  • telephone
  • video conferencing

In order for virtual project to succeed, communication between PM and project team must be frequent, open , and two way.

66

slide-34
SLIDE 34

Project Manager’s Golden Rule

“Never let the boss be surprised.”

It’s the PM’s job to keep senior management up to date on the state of the project, and keep them informed about the problems affecting the project.

67

Responsibility to Senior Management

Responsibility to the Client

  • The project manager is also responsible to the client
  • Clients often want changes to the project

– Cost, schedule, scope change – Cost of changes often exceed client’s expectations

  • Project manager must be certain the client

understands the impact of the changes on the project’s goals of delivery time, cost, and scope

68

slide-35
SLIDE 35

Responsibility to Project Team

  • Facilitate the work of the team
  • Help the team succeed
  • Serve as advisor, counselor, confessor, and

interested friend

69

Project Manager’s Responsibilities to the Project

Three overriding responsibilities ‐ Acquiring resources

  • Is not difficult but getting necessary quantity and quality can be key challenges
  • Hard to get competent human resource as department managers would not want to

release them.

Fighting fires and obstacles

  • Initially, often links to the need for resources.
  • As the project progresses, associated with technical problems, supplier problems, and

client problems.

Leadership and making trade‐offs

  • Making trade‐offs between project cost, schedule, and scope.
  • Among the three goals, scope is usually the most important, followed by schedule, and

then cost.

  • Trade‐offs could be between different projects, adding to one and reduce for another.

70

slide-36
SLIDE 36

Essential Skills of Project Manager

It is not possible for the PM to meet these responsibilities without being a skilled negotiator and a resolver of conflict.

Need ability to:

  • negotiate
  • resolve conflicts
  • persuade
  • Four essential parts, 1. credible, 2. have common goals, 3. use vivid

language and compelling evidence, and 4. connect with those they try to persuade. (Jay Conger, 1998)

  • avoid “irrational optimism”

71

Characteristics of a Successful Project Manager

Hard worker is easy to find, what is needed is an individual who completes the tasks given. Among a set of such, select those who meet the following criteria at high levels.

 Credibility – he/she is believable

  • technical credibility – must know enough to explain the current state of the

project, its technical problems, and to interpret the wishes of the management and clients to project team.

  • administrative credibility – reports, appraisals, audits, and evaluations must be

timely and accurate.

 Sensitivity ‐ politically astute and aware of interpersonal conflict  Leadership, Style, Ethics – able to direct project in an ethical

  • manner. The PM shall keep team members working toward completion of the whole

project rather than its parts. The leadership style needs to be more flexible when more technical uncertainty is present, more formal when the project is more complex. The PM needs to have and to communicate a strong sense of ethics. (PMI’s Code of Ethics)

72

slide-37
SLIDE 37

Growing Importance of Multicultural Projects

Project managers have to be aware of cultural differences between countries Common practice in one country may be illegal in another

 Paying a government official to fast track an approval, leaving out obvious information in a bid, inviting a client to dinner, etc.  Project managers have to be trained to the highest ethical standards

73

Project Management as A Profession

 Project Management Institute (PMI), founded in 1969, is a project‐oriented organization with more than 300,000 members worldwide www.pmi.org  PMI publishes The Project Management Body of Knowledge (PMBOK), and Project Management Journal and PM Network  Certification – Project Management Professionals (PMPs) and Certified Associates in Project Management (CAPM)

74

slide-38
SLIDE 38

Career Path for the Project Manager

  • Starts with work (not as manager) on a small

project

  • Moves on to work in larger projects
  • Moves on to a project engineer or deputy

project manager

  • Project manager for a small project
  • Moves on to larger projects as PM
  • May manage a “megaproject”

75

Factors Increasing the Importance

  • f Projects

 Emphasis on time‐to‐market  Need for specialized knowledge from a variety of areas  Explosive rate of technological change require system‐wide responsiveness  Need for accountability and control  Rapid growth of globalized industry

76

slide-39
SLIDE 39

Project Organization

77

  • Pure Project Organization
  • Functional Project Organization
  • Matrix Project Organization
  • Mixed Project Organization

The Pure Project Organization

President Project Manager Manager Project A Manager Project B VP Marketing VP Manufacturing VP R&D

Marketing Manufacturing R&D Human Resources Marketing Manufacturing R&D Human Resources 78

slide-40
SLIDE 40

The Pure Project Organization

Advantages

  • effective and efficient for large projects
  • resources available as needed
  • broad range of specialists
  • short lines of communication

Drawbacks

  • expensive for small projects, not everyone is needed

all the time.

  • specialists may have limited technological depth, and

if so, need to hire additional specialists.

  • may require high levels of duplication for certain

specialties in the parent organization

  • “projectitis” – people got attached to a project

79

Functional Project Organization

President Manufacturing Project Marketing R & D Human Resources Finance

80

slide-41
SLIDE 41

The Functional Project Organization

 Advantages

  • Embedded in the functional group
  • Immediate, direct, and complete access to in‐depth

technology

  • Minimize the fractional need problem and “projectitis”

symptom

 Drawbacks

  • lines of communication outside functional department

can be slow

  • technological breadth can be missing
  • project rarely be given high priority in the division

81

Matrix Project Organization

President Program Manager PM1 PM2 PM3 Manufacturing 3 1 Marketing 1 ½ 4 1/2 Finance ½ ¼ 3 R&D 4 1 ½ 1/2 Human Resources ½ ¼ 1

Two distinct levels – vertical functional hierarchy and horizontal project structure overlay the functional hierarchy.

82

slide-42
SLIDE 42

Matrix Project Organization

 Advantages

  • flexibility in the way it can interface with parent organization
  • Has access to any or all of the parent organization’s technology.
  • Far less expensive than pure project organization
  • strong focus on the project itself
  • contact with functional groups minimizes “projectitis”
  • ability to manage fundamental trade‐offs across several projects

 Drawbacks

  • violation of the unity of command principle – for each subordinate,

there shall be one and only one superior. The individual specialist has two bosses, the project manager and the functional manager.

  • complexity of managing the organization’s full set of projects
  • intrateam conflict, individuals are often committed to their

functional area rather than to the project. Same people is expected to be at different projects and functional area at the same time.

83

Mixed Project Organization

President Project M Finance Engineering Project Z Manufacturing

84

slide-43
SLIDE 43

Project Management Offices

 There is another way of solving the problems of choosing one

  • r another organizational form … setting up a project

management office (PMO) … act as staff to some or all projects … shall never replace PM as officer in charge of the project … useful for small project with short lives.  There can be several different types of PMOs in large firms … with different and sometimes overlapping areas of operations

  • CPMO (corporate project management office)
  • EPMO (enterprise project management office)

 Project management maturity could be measured by PMI’s OPM3 (Organizational Project Management Maturity Model)

  • r other models.

85

Organizational Project Management Maturity Model – OPM3

  • Provides a way for organizations to measure

themselves against best in practices of managing projects, programs, and portfolios.

  • Shows the maturity of organizations in

implementing OPM to achieve their

  • rganizational objectives.
  • Highlights needed areas of improvement for
  • rganizations to help them achieve better

business results.

86

  • 2013 Project management Institute, Inc.
slide-44
SLIDE 44
  • In this system, the final project maturity of an
  • rganization is assessed as being one of five levels:

1. Ad‐hoc – disorganized, accidental success, and failures; 2. Abbreviated – some processes exist, inconsistent

management, unpredictable results;

3. Organized – standardized process, more predictable results; 4. Managed – controlled and measured processes, results

more in line with plans;

5. Adaptive – continuous improvement in processes, success

is normal, performance keeps improving.

87

Organizational Project Management Maturity Model – OPM3

Characteristics of Effective Project Team Members

 Team members must be/have:

  • technically competent
  • politically sensitive (for senior members)
  • problem oriented
  • goal oriented (could not succeed if view it as a 9 to 5 job)
  • high self‐esteem
  • sufficient trust in their fellow team members

88

slide-45
SLIDE 45

Matrix Team Problems

 The smaller the project, the more likely it is to be organized as a weak (functional)

  • matrix. As a result:

» PM may have no direct reports » his/her ability to communicate directly with team members will be critical » important to maintain good morale … since team loyalty may be limited » a PMO (a project’s war room) may be helpful

89

Multidisciplinary Teams‐Balancing Pleasure and Pain

  • Using multidisciplinary teams on projects raises

serious problems for the project manager

– A.k.a. transdisciplinary teams

  • Managing the way these groups work together is

called interface coordination

– Arduous and complicated

  • Coordinating the work of these groups is called

integration management

– Arduous and complicated

90

slide-46
SLIDE 46

Five Dysfunctions of a Team

  • 1. Absence of trust
  • 2. Fear of conflict
  • 3. Lack of commitment
  • 4. Avoidance of accountability
  • 5. Inattention to results

91

Interface Coordination‐Interface Management

  • One of more difficult problems with multidisciplinary

teams is coordinating the work

  • Team members come from different functional areas

and are not used to working together

  • Have no established dependencies on each other
  • One approach to the problem is to expose the

structure of the work assigned to the team

  • No single approach to interface coordination is

sufficient alone

92

slide-47
SLIDE 47

Integration Management

  • Different groups worked independently and sequentially.
  • No good communications between different groups and

conflicts were legendary.

  • Each group tried to sub‐optimize its own contribution
  • One approach to the problem is to change the project

from one that proceeded sequentially to one where the steps are carried out concurrently – parallel tasking.

  • Involving people from different groups from the

beginning of the process – interdisciplinary approach

93

Six Signs of Excessive Stress in the Workplace

  • 1. Inability to switch‐off work issues
  • 2. Disturbed sleep
  • 3. Lack of pleasure in non‐work‐related leisure

activities

  • 4. Difficulty concentrating or making decisions
  • 5. Tendency to anger quickly
  • 6. Lack of energy

94

slide-48
SLIDE 48

Ways to Keep Stress Under Control

  • 1. Keep a journal
  • 2. Prioritize all tasks
  • 3. Give yourself time to unwind
  • 4. Engage in after‐work physical activities
  • 5. Improve your physical surroundings
  • 6. Become aware of the control you have

95

‐ The End ‐ Thank You!

96