Unit 28 Technical Memorandum 1 Unit 28 Remedial Action Unit 28: 107 acres Fieldwork completed in June 2017 212 MEC items recovered (See MEC Recovery Table) 2 Unit 28 Inaccessible Areas Extreme terrain within Unit 28


slide-1
SLIDE 1

1

Unit 28 Technical Memorandum

slide-2
SLIDE 2

2

Unit 28 Remedial Action

  • Unit 28: 107 acres
  • Fieldwork completed in June 2017
  • 212 MEC items recovered (See MEC Recovery Table)
slide-3
SLIDE 3
  • Extreme terrain within Unit 28 presented fieldwork challenges

– Surface MEC Removal: 90 acres complete (12 acres inaccessible) – Digital Geophysical Mapping: 63 acres complete (39 acres inaccessible)

3

Unit 28 Inaccessible Areas

slide-4
SLIDE 4

4

Unit 28 Sensitive Fuze Type Munitions

  • 119 sensitive fuze type munitions
  • Portion of the southern third of the unit recommended for additional

evaluation (See Figure 6)

slide-5
SLIDE 5

5

Unit 28 Joint Inspection Results

  • BLM-Army Joint Inspection performed July 2017
  • Areas such as erosion features and Impossible Canyon Road reroute may

require subsurface MEC removal

slide-6
SLIDE 6
  • Remedial objectives have been met for Unit 28
  • Likelihood of surface MEC remaining in inaccessible acreage is low
  • No additional surface MEC remediation is recommended
  • Recommended evaluation of potential for munitions with sensitive fuzes to

remain in the shallow subsurface in Unit 28 “area of concern”

  • Unit 28 will be included in 2018 annual surface monitoring

6

Technical Memorandum Summary

slide-7
SLIDE 7

1

Track 3 Surface Area Monitoring Reports

slide-8
SLIDE 8

2

Objectives

  • Comply with Track 3 ROD
  • Address potential changes in site conditions due to erosion
  • Monitor units/areas until vegetation growth is sufficient to minimize erosion
slide-9
SLIDE 9

3

Procedures

  • Monitor one percent, at minimum of all units/areas in the program
  • Enhanced surface monitoring in all units/areas with high

subsurface anomaly density and UXO with sensitive fuzes

slide-10
SLIDE 10

4

Surface Monitoring Program Summary

2017 Additions

  • Unit 23
  • Unit 5A
  • Unit 9

2018 Additions

  • Unit 25
  • Unit 28
  • Recommended continue monitoring in all units/areas except Units 4 and 34
  • 2018 Surface Monitoring scheduled for Spring