1
CITY OF PHOENIX REQUEST FOR BIDS AVIATION DEPARTMENT PHOENIX DEER VALLEY AIRPORT (DVT) CONSTRUCT RUN-UP AREAS ADJACENT TO TAXIWAY C DESIGN-BID-BUILD
PROJECT NO. AV31000082-1 FAA AIP NO. 3-04-0028-037-2017 July 10, 2017
Pre-Bid Meeting CITY OF PHOENIX REQUEST FOR BIDS AVIATION - - PowerPoint PPT Presentation
Pre-Bid Meeting CITY OF PHOENIX REQUEST FOR BIDS AVIATION DEPARTMENT PHOENIX DEER VALLEY AIRPORT (DVT) CONSTRUCT RUN-UP AREAS ADJACENT TO TAXIWAY C DESIGN-BID-BUILD PROJECT NO. AV31000082-1 FAA AIP NO. 3-04-0028-037-2017 July 10, 2017 1
1
PROJECT NO. AV31000082-1 FAA AIP NO. 3-04-0028-037-2017 July 10, 2017
2
Emeka Ekpe, Contracts Specialist
Point of Contact for RFB Questions Office of the City Engineer emeka.ekpe@phoenix.gov (602) 256-4107
Joanne McLaughlin, Business Relations Programs Assistant
Point of Contact for DBE Requirements Equal Opportunity Department joanne.mclaughlin@phoenix.gov (602) 534-1279
Marci Thies, Labor Compliance Supervisor
Point of Contact for Labor Compliance / Davis Bacon Requirements Street Transportation Department marci.thies@phoenix.gov (602) 261-8287
Rubben Lolly, Project Manager
Aviation Department Representative
3
http://phoenix.gov/streets/procurement/current-opportunities
■ Planholder List ■ RFQ / RFB ■ Addendums / Notifications (if applicable)
4
The FAA approved a triennial DBE goal of 4.44% for fiscal years 2016-19, to be achieved through fostering Small Business participation and outreach requirements.
Copies of the actual solicitations sent to DBEs & Small Businesses Names of the DBEs & Small Businesses whom bidder negotiated with and the firms that have been selected to participate in the contract MUST demonstrate how, when, and the name of the person to whom the bidder specifically communicated its selection decisions Outcomes to each DBE and Small Business NOT selected Documentation may be in the form of a letter, e-mail, telephone log, or
Monitors and enforces the federal labor
Applies to all federally funded contracts in
All contractors and subcontractors, including
Davis-Bacon Act (DBA) Copeland Anti-Kickback Act Contract Work Hours and Safety Standards
Code of Federal Regulations, Title 29 Part 3 Code of Federal Regulations, Title 29 Part 5 FHWA 1273 / LCP Tracker Wage Decision
Labor Compliance Pre-Construction
Labor Compliance Office, (602) 261-8287 Websites available:
– http://www.dol.gov/dol/esa/programs/dbra
19
20
21
22
23
Demolition of existing run-up area asphaltic concrete (AC)
Construction of nearly 20,000 SY of new AC Pavement Excavation of existing west basin to add additional capacity Grading and drainage improvements
24
Salvaging (Blade and stockpile along west haul route with
Installation of storm drain pipe, manholes and catch basins Installation of LED and incandescent edge lights Removal of chain-link fence and installation of approximately
Construction and Removal of two temporary run-up areas,
25
26
Rocks and cobbles will be encountered and must be
27
The Project is divided into 8 phases with subsequent sub phases Phases 1-4 are located on the west side of the Airport Phases 5-8 are located on the east side of the Airport Primary Access for Phases 1 – 4 will be through the access gate
Primary access for phases 5-8 will be through Airport Access
Contractor shall limit activities to designated haul routes and
Contractor Shall not use airport service roads for hauling
Some phases require nighttime-work only Caution should be taken to protect a fiber optic line south of
28
29
30
An airport access badge will be required Construction equipment cannot traverse on any new
Airfield lighting and NAVAIDS must remain operational
Access to the fueling station must be maintained at all
NOTAMS require 72 hour advanced notice
31
Contractor provide quality controls – City QA Follow all federal, state and local permitting requirements Coordinate Owner / Project issues Maintain a safe & secure work site at all times Must use the City’s web based project management system:
NTP will be issued for the Contract once the NTP from FAA
32
Contact Theodore Iniguez (602) 571-2638. Removal and disposal by others. Removal during start of each phase. Contractor to cooperate and provide access.
33
Test for lead and asbestos containing materials Remove any lead and asbestos containing materials
Review all Safety Data Sheets. Approve locations of all disposal sites. Approve all materials disposed offsite. Approve paint materials. P&E Contact: Theodore Iniguez (602) 571-2638
34
35
36
Information for Bidders (IFB) Section:
Failure to provide Bid Bond Failure to submit all required Bid-and-Post Bid documents Failure to acknowledge / signatures as required
37
Receipt of Bid after the specified cut-off date and time Deposit of Bid in the wrong location Violating the “Contact with City Employees” policy Failure to provide Bid Bond
38
39
40