Massaro About E CS The mission of The Environmental Charter School - PDF document

Massaro About E CS The mission of The Environmental Charter School at Frick Park is to educate each student to high academic learning standards using a themed curriculum that will foster knowledge, love of and respect for the environment and


  1. Massaro

  2. About E CS The mission of The Environmental Charter School at Frick Park is to educate each student to high academic learning standards using a themed curriculum that will foster knowledge, love of and respect for the environment and the will to preserve it for future generations. • Founded in 2008 with the Lower School K-3 (S. Braddock Ave.) • Expanded and added Upper School 4-8 (Milton Street) • Public Charter School • City of Pittsburgh School District • 501c(3) Non-Profit Massaro

  3. Pr oje c t T e am • Owner – Environmental Charter School • Chief Executive Officer – Jon McCann • Architect – Rothschild Doyno Collaborative • Principal - Dan Rothschild • Lead Architect – Matt Diersen • Sustainability Consultant – EvolveEA • Principal – Christine Mondor • Construction Manager – Massaro CM Services, LLC • Director of Preconstruction – Dan Kiefer • Project Manager – Dave Parker • Project Engineer – Nancy Gorgas • Site Manager – TBD Massaro

  4. Pr oje c t Ove r vie w • Interior Alterations with Limited Exterior /Site Work • Multiple Prime Contracts, direct to the Owner: • General Construction, HVAC, Plumbing, Electrical • Owner Occupancy During Construction – Staff only during Summer Break. • Tax Status – ECS is a 501c(3) Non-Profit • Public School Code, 24 P.S. § 7-752 - First Class Workers • Prevailing Wages (PA State Wage Rates) & Certified Payroll • Steel Products Procurement Act • Clearances Required - All On-Site Personnel • Criminal Records Check (Act 34) • Department of Public Welfare Child Abuse History Clearance (Act 151) • Federal Criminal Background Check (Act 114) • Non-Discrimination in Hiring Practices and Performance of the Work Massaro

  5. Pr oje c t Ove r vie w - Continue d • Safety : • Comply with MCMS Safety Program • OSHA 30 Supervision Required • 100% PPE – Hardhats, Eye Protection, High Visibility Clothing • First Day Safety Briefing • Quality : • Comply with MCMS Quality Control Plan • Sustainability : • Waste Management Plan / Waste Diversion • Low/No VOC Materials • Fundamental Commissioning - HVAC Equipment ONLY Massaro

  6. Pr e liminar y Sc he dule • Project Milestone Dates: • Notice to Proceed May 22, 2013 • Submittals Issued (to Arch.) – Long Leads May 31, 2013 • Submittals Issued (to Arch.) – ALL June 18, 2013 • Start of Construction June 24, 2013 • Close-In Inspections Complete July 24, 2013 • Date of Substantial Completion – Ph1 August 16, 2013 • First Day of School (FYI) August, 23, 2013 • Date of Substantial Completion – Ph2 Sept. 17, 2013 • Project Durations: • Phase 1 – 53 Calendar Days • Phase 2 – 81 Calendar Days Massaro

  7. Site L ogistic s / Wor k R e str ic tions • Regular Work Hours : 7:00AM – 3:30PM • Off-Hours Work : Not permitted, unless prior written permission is obtained from the Owner and MCMS • Contractor Parking • On-Site – • 8 Spaces at rear • Use of Loading Zone ONLY on Henrietta • Off-Site – • Free Parking at Biddle Lot, 1 block away • No Parking permitted on Milton Street • Major Deliveries : Coordinate with MCMS Site Manager Massaro

  8. Site L ogistic s Plan Massaro

  9. Ge ne r al Sc ope s of Wor k See the Project Manual, including Division 00 and Division 01 GENERAL CONSTRUCTION HVAC • Schedule Development • Selective Demolition • Limited Site Work • New Split System Heat Pump • Selective Demolition / Salvage • New Rooftop Unit and Distribution • Structural & Misc Steel • Modifications to existing ductwork • Masonry • New Kitchen Exhaust fan & • Enclosure & Waterproofing ductwork • Framing / Drywall / Ceilings • New Exhaust fans at toilet rooms. • Finish Carpentry / Casework • HVAC Controls • Doors / Windows / Glazing • HVAC Testing & Balancing • Folding Glass Partition • Fundamental Commissioning • Limited Roofing • Estimated Value : $150-225K • Finish Flooring • Food Service Equipment • Lockers and Furnishings • Paint / Acoustic Panels • Estimated Value : $600-750K Massaro

  10. Ge ne r al Sc ope s of Wor k – Cont’d See the Project Manual, including Division 00 and Division 01 PLUMBING ELECTRICAL • Selective Demolition • Selective Demolition • New Plumbing Fixtures & • Interior Lighting Fittings • Interior and exterior Power • Domestic Water Modification & Distribution Distribution • Building Communications wiring • Sanitary Waste Modification & and terminations Distribution • Fire Alarm modification and • Connections for Food Service improvements Equipment and other Contracts • Connections for Food Service • NO Fire Protection Work Equipment and other Contracts • Estimated Value : $100-140K • Estimated Value : $220-260K MCMS Estimated Project Value (Base Bid) : $1MM – 1.4MM Massaro

  11. Bid Alte r nate s See also Section 012300 - Alternates ALTERNATES • GC-1 : Classroom Painting • GC-2 : Exterior Doors – General • EC-2 : Exterior Doors – Electrical • GC-3 : Lockers • GC-4 : Auditorium Window • GC-5 : Skylights Massaro

  12. Gr ound F loor Massaro

  13. F ir st & Se c ond F loor (Similar ) Massaro

  14. We b-Base d Pr oje c t Administr ation • Platform : Prolog Converge • Fee : $200/Month per Prime Contractor • Administration and Support : Provided by MCMS • Training : Provided by MCMS • Administrative Procedures in Prolog : • Submittals • RFI’s • Daily Reports • Change Order Requests (COR) • Applications for Payment (AFP) Massaro

  15. Bid Pe r iod Note s • All Bid Period Communications are being managed by Massaro CM Services. • Platform : Printscape Online Planroom • Fee : Free to view all items, Print/download costs as needed, order direct. • Registration : Send request for registration to Nancy Gorgas at ngorgas@massarocms.com • Submit Bid RFI’s using required form to Nancy Gorgas at ngorgas@massarocms.com. • Last day for RFI’s Submission is May 9, 2013 . • Additional Bid Information provided through the Online Planroom: • RFI responses • Addenda • Bidder’s List • Bid Drop-off / Bid Day Information • Public Bid Opening is at 3PM on Tuesday May 14, 2013 . Massaro

  16. Questions? REMINDER: Any questions asked or responses given today are for general information only and will not become part of the Bid Documents. All Bid-related questions MUST be submitted as written RFI using the required process. Massaro

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.