Peel Valley Works and Drought Update October 14th and 15th 2019
Dungowan and Tamworth
\
Adrian Langdon Executive Manager, System Operations Ronan Magaharan Executive Manager – Assets
Peel Valley Works and Drought Update October 14 th and 15 th 2019 - - PowerPoint PPT Presentation
Peel Valley Works and Drought Update October 14 th and 15 th 2019 Dungowan and Tamworth \ Adrian Langdon Executive Manager, System Operations Ronan Magaharan Executive Manager Assets Overview Introduction from Tamworth Regional Council
Dungowan and Tamworth
\
Adrian Langdon Executive Manager, System Operations Ronan Magaharan Executive Manager – Assets
2
3
4
5
1 April 2018 – 31 August 2019
6
August 2019
7
8
September 2019
9
10
Water NSW
11
12
13
IF it does not rain again and these critical drought works are not completed – there could be a day zero for the region. These works undertaken by WaterNSW in conjunction with water restrictions and other measures by Tamworth Regional Council will extend supplies for more than a year.
15
Last possible date to avoid a day zero outcome ( worse case scenario planning)
Water NSW
Cease to flow
16
Water NSW
drought works
by the Dept Planning, Industry and Environment – Water
fact sheet
the specific information and advice from the Department once it is finalised.
17
20000 40000 60000 80000 100000 120000 100 200 300 400 500 600
Volume (ML) Inflow and demand (ML/d)
Peel Valley_Inflow and storage volume
Upstream of Tamworth (419081-Taroona) Tamworth's daily demand (min) Storage volume
Year-17-18, irregular inflow upstream, which was not enough to meet even Tamworth’s min demand From 1st of Jan 18
inflow 1st of Jan 2017, dam volume was 102 GL, through which water is supplying to GS, HS, S&D till now If there was no dam, trouble would have started since early 2017 to supply for Tamworth Council and irrigators, which is around 33 months Tamworth council min demand: 20 ML/d
19
20
21
22
23 WaterNSW May 2019
25
INSERT GRAPH
26
INSERT GRAPH
WaterNSW 27
Gap between black and red line highlights high losses in the system = 2 years Tamworth Supply demand
29
1/07/2010 1/10/2010 1/01/2011 1/04/2011 1/07/2011 1/10/2011 1/01/2012 1/04/2012 1/07/2012 1/10/2012 1/01/2013 1/04/2013 1/07/2013 1/10/2013 1/01/2014 1/04/2014 1/07/2014 1/10/2014 1/01/2015 1/04/2015 1/07/2015 1/10/2015 1/01/2016 1/04/2016 1/07/2016 1/10/2016 1/01/2017 1/04/2017 1/07/2017 1/10/2017 1/01/2018 1/04/2018 1/07/2018 1/10/2018 1/01/2019 1/04/2019
Groundwater Depth (m)
Depth to groundwater table below the measuring point
33
Key Facts
channel
maintain water quality in downstream pools
34
WaterNSW 35
Stage 1 – Temporary Dungowan weir
A temporary intake would be constructed into the southern bank of the river, immediately upstream of an existing 4WD crossing shown in the images below.
Existing 4WD crossing (flow direction to left) Immediately upstream of existing crossing
36
37
38
There is very likely to be if drought continues and inflows remain low… Critical human needs is now the top priority. Here is what we are doing
releases to go down the peel from time to time
1800 043 536
39
41
44
Stage 2 – Construction of a permanent pipeline
Dungowan Town (and connecting to the existing pipeline
time.
been underway in recent weeks.
45
46
47
Stakeholder Coordination, Design and Scope Development – 3 Months Initiation – 1 months Tender – 3 Months Resource allocation – 1 months Planning and Environmental Approvals – 3 Months Funding and Approvals – 2 Months Procurement – 3 Months Detailed Design – 3 Months Construction – 3 Months Commission – 1-2 Months Project Close – 1-2 Months
Total Project Delivery Time = 9 Months
Route Selection, Land Identification and Acquisition – 3-4 Months
▪ Engaged additional resources ▪ Working closely with Tamworth Council to coordinate project ▪ Early briefings to Government Approval agencies ▪ Financial approval process commenced ▪ Land / Route selection – primarily council land ▪ Early Contractor Involvement process ▪ Pipe capacity / size review to being prioritised ▪ Pipe Suppliers engaged to minimise lead time ▪ Environmental approvals ▪ Lessons learnt from delivering the Broken Hill Pipeline
will be available on line and hard copy by 25th October.
early March 2020.
meeting.
local media.
water supply (town water supply connected or existing bore etc)
sessions
5 1
52
Fact Sheets available today DPI site www.industry.nsw.gov.au for facts Visit the website at: waternsw.com.au/drought For information including water availability reports and drought reports go to: https://www.waternsw.com.au/supply/drought-
information/regional-nsw
Call us on: 1300 662 077
Subscribe at: waternsw.com.au/subscribe
For weekly customer drought updates and more information
53
For specific inquiries about stock and domestic bores (Basic landholder rights bores) email waterregnorth@waternsw.com.au Nicole Gleeson-Lendon’s (02) 9849 9960 The WNSW general inquiry number – 1300 662 077
Customer.Helpdesk@waternsw.com.au
(EWN)- Via registration forms available here tonight.
Facebook Group
https://www.facebook.com/groups/WaterNSWPeelRiver/
56
57