Peel Valley Works and Drought Update 5th and 6th August 2019
Dungowan and Tamworth
\
Adrian Langdon Executive Manager, System Operations Ronan Magaharan Executive Manager - Assets
Peel Valley Works and Drought Update 5 th and 6 th August 2019 - - PowerPoint PPT Presentation
Peel Valley Works and Drought Update 5 th and 6 th August 2019 Dungowan and Tamworth \ Adrian Langdon Executive Manager, System Operations Ronan Magaharan Executive Manager - Assets Discussion Agenda Introduction from Tamworth Regional
Dungowan and Tamworth
\
Adrian Langdon Executive Manager, System Operations Ronan Magaharan Executive Manager - Assets
2
Impact on the Peel
Customer Impacts
3
4
5
1 May 2017 – 30 April 2019
6
7
8
9
Water NSW
10
Water NSW
11
12
13
14
15
16
17 WaterNSW May 2019
19
INSERT GRAPH
20
INSERT GRAPH
WaterNSW 21
Gap between black and red line highlights high losses in the system = 2 years Tamworth Supply demand
22
1/07/2010 1/10/2010 1/01/2011 1/04/2011 1/07/2011 1/10/2011 1/01/2012 1/04/2012 1/07/2012 1/10/2012 1/01/2013 1/04/2013 1/07/2013 1/10/2013 1/01/2014 1/04/2014 1/07/2014 1/10/2014 1/01/2015 1/04/2015 1/07/2015 1/10/2015 1/01/2016 1/04/2016 1/07/2016 1/10/2016 1/01/2017 1/04/2017 1/07/2017 1/10/2017 1/01/2018 1/04/2018 1/07/2018 1/10/2018 1/01/2019 1/04/2019
Groundwater Depth (m)
Depth to groundwater table below the measuring point.
23
24
25
26
27
20 40 60 80 100 May-18 Aug-18 Nov-18 Feb-19 May-19 Aug-19 Nov-19 Feb-20 May-20 Aug-20 Nov-20 Feb-21 Storage capacity (GL)
Chaffey Dam - forecast storage volume (chance of exceedance)
Minimum 99% COE DRY 80% COE Median 50% COE WET 20% COE actual No Inflow
28
29
Drought stage Stage 3 severe water shortage. Storage Level
20ML/d.
Allocations
stock) and for high security users, although supply below Dungowan will be restricted later in 2019 if dry conditions continue. Action
to extend supply for Tamworth and reduce around 17,000 ML in transmission losses below Chaffey Dam. The Government has committed $3.4 million for these works and $2 million for further supply investigations. Issues
are at record high levels.
may need to sought for downstream commercial users. Outlook
supply.
30
Operational Savings Secure Alternative Supply Future Water Supply
1. Assess Late May 2019 Investigations Bathymetry and water quality for peel. Benefits: Optimises water supply and quality for towns and high security 2. Block Banks June: Development of block bank requirements with council Benefits: Supply Town water for a longer period from Chaffey Dam. 3. Block Banks June: Water quality for fauna assessment to be done for Northern Valleys Benefits: Help protect and maintain ecosystem.
1. Accessing deep water storage for Chaffey (Peel) Trigger: Last responsible moment necessary before water ceases to flow. Benefits: Possibility of supplying town water for longer period when ground water source is used as an alternative Industry 2. Develop carting and distribution
Trigger: Stopping flow at Tamworth Benefits: Extend high security water to critical industries. 3. Sinking Bores Trigger: Stopping flow at Tamworth Benefits: Water supply for towns and industries. 4. Aeration for deep/dead storage Benefits: Extend town water supply
Tamworth Develop proposal to secure supplies to Tamworth if inflows continue to stay below the drought of record
usage Options
PEEL
Mitigation Measures
32
Approach to extending Water Supply
Context
losses can be minimised, the longer we will be able to supply water to Tamworth.
Proposed Solution WaterNSW has proposed a two-staged infrastructure solution supported by NSW Government
approximately four months
Dungowan pipeline that would ensure Tamworth does not run out of town water supply (under drought-of-record conditions) if constructed early enough.
Stage 1 – Install Temporary Weirs on the Peel River To reduce heavy transmission losses and extend water supply. WaterNSW is proposing to install temporary weirs on the Peel river at two locations:
– Dungowan Village
delivery to Tamworth
length from temporary weir to existing Dungowan Pipeline.
– Jewry Street
when supply is secured (pipeline operation or significant inflows)
pipeline)
35
Proposed temporary weir location Option for temporary pipeline route Option for temporary pipeline route
37
38
39
41
Stage 2 – Construction of a Permanent Pipeline
(and connecting to the existing pipeline owned by TRC), which would conserve Chaffey’s remaining storage by reducing transmission losses on the Peel River.
Tamworth, and would ensure the town does not run out of water supply (under drought-of-record conditions) provided it is installed early in 2020.
within the Chaffey Dam property boundary.
42
Stage 2 Two routes are to be considered:
Woolomin is also to be considered.
Pipeline route
– Review of Environmental Factors to be completed. This will confirm the required approval pathways, which are expected to be numerous. – Engagement with impacted landholders to be completed Key Dates
– Environmental approvals – Pipe availability – Selected route – Contractors installation methodology
Stakeholder Coordination, Design and Scope Development – 3 Months Initiation – 1 months Tender – 3 Months Resource allocation – 1 months Planning and Environmental Approvals – 3 Months Funding and Approvals – 2 Months Procurement – 3 Months Detailed Design – 3 Months Construction – 3 Months Commission – 1-2 Months Project Close – 1-2 Months
Total Project Delivery Time = 9 Months
Route Selection, Land Identification and Acquisition – 3-4 Months
What have we done to reduce timeframe:
project
49
Fact Sheets available today DPI site www.industry.nsw.gov.au for facts Visit the website at: waternsw.com.au/drought For information including water availability reports and drought reports go to: https://www.waternsw.com.au/supply/drought-
information/regional-nsw
Call us on: 1300 662 077
Subscribe at: waternsw.com.au/subscribe
For weekly customer drought updates and more information
50
For specific inquiries about stock and domestic bores (Basic landholder rights bores) email waterregnorth@waternsw.com.au Nicole Gleeson-Lendon’s (02) 9849 9960 The WNSW general inquiry number – 1300 662 077
Customer.Helpdesk@waternsw.com.au
(EWN)- Via registration forms available here tonight.
Facebook Group
https://www.facebook.com/groups/WaterNSWPeelRiver/
53