Peel Valley Works and Drought Update 5 th and 6 th August 2019 - - PowerPoint PPT Presentation

peel valley works and drought update 5 th and 6 th august
SMART_READER_LITE
LIVE PREVIEW

Peel Valley Works and Drought Update 5 th and 6 th August 2019 - - PowerPoint PPT Presentation

Peel Valley Works and Drought Update 5 th and 6 th August 2019 Dungowan and Tamworth \ Adrian Langdon Executive Manager, System Operations Ronan Magaharan Executive Manager - Assets Discussion Agenda Introduction from Tamworth Regional


slide-1
SLIDE 1

Peel Valley Works and Drought Update 5th and 6th August 2019

Dungowan and Tamworth

\

Adrian Langdon Executive Manager, System Operations Ronan Magaharan Executive Manager - Assets

slide-2
SLIDE 2

2

Discussion Agenda

  • Introduction from Tamworth Regional Council
  • Overview
  • Worst Drought Ever
  • Drought Outlook

Impact on the Peel

  • Groundwater
  • Tributary Inflows

Customer Impacts

  • Peel System Users
  • BLR
  • Environment
  • What is WaterNSW doing now?
  • How to keep updated
  • Next steps
  • Questions and Answers
slide-3
SLIDE 3

3

The Peel System

slide-4
SLIDE 4

4

Worst Drought Ever

slide-5
SLIDE 5

5

NSW rainfall

1 May 2017 – 30 April 2019

slide-6
SLIDE 6

6

NSW rainfall

slide-7
SLIDE 7

7

NSW rainfall

slide-8
SLIDE 8

8

NSW rainfall

slide-9
SLIDE 9

9

Temperature

Water NSW

slide-10
SLIDE 10

10

Maximum temperature

1 May 2018 – 30 April 2019

Water NSW

slide-11
SLIDE 11

11

Drought Stages

slide-12
SLIDE 12

12

State Policy

slide-13
SLIDE 13

13

Peel River Operations

slide-14
SLIDE 14

Peel System Inflows

14

slide-15
SLIDE 15

15

slide-16
SLIDE 16

16

Peel Tributary Inflows

slide-17
SLIDE 17

Chaffey Dam Levels

17 WaterNSW May 2019

slide-18
SLIDE 18

Chaffey Dam releases 16-17

19

INSERT GRAPH

slide-19
SLIDE 19

Chaffey Dam releases 17-18

20

INSERT GRAPH

slide-20
SLIDE 20

Chaffey 18-19 Releases

WaterNSW 21

Gap between black and red line highlights high losses in the system = 2 years Tamworth Supply demand

slide-21
SLIDE 21

Groundwater Table

22

  • 11.5
  • 11
  • 10.5
  • 10
  • 9.5
  • 9
  • 8.5
  • 8

1/07/2010 1/10/2010 1/01/2011 1/04/2011 1/07/2011 1/10/2011 1/01/2012 1/04/2012 1/07/2012 1/10/2012 1/01/2013 1/04/2013 1/07/2013 1/10/2013 1/01/2014 1/04/2014 1/07/2014 1/10/2014 1/01/2015 1/04/2015 1/07/2015 1/10/2015 1/01/2016 1/04/2016 1/07/2016 1/10/2016 1/01/2017 1/04/2017 1/07/2017 1/10/2017 1/01/2018 1/04/2018 1/07/2018 1/10/2018 1/01/2019 1/04/2019

Groundwater Depth (m)

Depth to groundwater table below the measuring point.

slide-22
SLIDE 22

23

Drought Outlook

slide-23
SLIDE 23

24

Temperate Outlook

slide-24
SLIDE 24

25

Rainfall Outlook

slide-25
SLIDE 25

26

So… What does all this mean for the Peel Valley ?

slide-26
SLIDE 26

Storage Forecast

27

20 40 60 80 100 May-18 Aug-18 Nov-18 Feb-19 May-19 Aug-19 Nov-19 Feb-20 May-20 Aug-20 Nov-20 Feb-21 Storage capacity (GL)

Chaffey Dam - forecast storage volume (chance of exceedance)

Minimum 99% COE DRY 80% COE Median 50% COE WET 20% COE actual No Inflow

slide-27
SLIDE 27

Block banks will extend water supply (Zero Inflow Model)

28

slide-28
SLIDE 28

Block banks - Drought of Record Model

29

slide-29
SLIDE 29

Peel River: Current State of Play

Drought stage Stage 3 severe water shortage. Storage Level

  • Chaffey Dam at 23% of active storage and currently releasing

20ML/d.

Allocations

  • No allocation for general security in 2019/20.
  • Last general security allocation made in October 2018.
  • Reduced allocations for high priority (town and domestic and

stock) and for high security users, although supply below Dungowan will be restricted later in 2019 if dry conditions continue. Action

  • Work is underway for a series of temporary weirs in the Peel River

to extend supply for Tamworth and reduce around 17,000 ML in transmission losses below Chaffey Dam. The Government has committed $3.4 million for these works and $2 million for further supply investigations. Issues

  • Inflows into the dam and transmission losses below Chaffey Dam

are at record high levels.

  • Supply below Dungowan will be restricted and alternative supply

may need to sought for downstream commercial users. Outlook

  • All efforts are being made to secure and extend Tamworth’s

supply.

30

slide-30
SLIDE 30

Now Medium Longer

Operational Savings Secure Alternative Supply Future Water Supply

1. Assess Late May 2019 Investigations Bathymetry and water quality for peel. Benefits: Optimises water supply and quality for towns and high security 2. Block Banks June: Development of block bank requirements with council Benefits: Supply Town water for a longer period from Chaffey Dam. 3. Block Banks June: Water quality for fauna assessment to be done for Northern Valleys Benefits: Help protect and maintain ecosystem.

1. Accessing deep water storage for Chaffey (Peel) Trigger: Last responsible moment necessary before water ceases to flow. Benefits: Possibility of supplying town water for longer period when ground water source is used as an alternative Industry 2. Develop carting and distribution

  • ptions

Trigger: Stopping flow at Tamworth Benefits: Extend high security water to critical industries. 3. Sinking Bores Trigger: Stopping flow at Tamworth Benefits: Water supply for towns and industries. 4. Aeration for deep/dead storage Benefits: Extend town water supply

  • 1. Pipeline Chaffey to

Tamworth Develop proposal to secure supplies to Tamworth if inflows continue to stay below the drought of record

  • 2. Groundwater storage and

usage Options

PEEL

Mitigation Measures

slide-31
SLIDE 31

32

What are we doing Now?

slide-32
SLIDE 32

Infrastructure Solutions Ronan Magaharan

slide-33
SLIDE 33

Approach to extending Water Supply

Context

  • Chaffey Dam supplies most of Tamworth Regional Council’s water
  • High transmission losses incurred through delivering water along the Peel River
  • Prolonging supply in Chaffey is the most effective way of servicing Tamworth’s water needs.
  • The sooner the rate of depletion level in the dam can be reduced and river transmission

losses can be minimised, the longer we will be able to supply water to Tamworth.

  • Doing nothing is simply not an option.

Proposed Solution WaterNSW has proposed a two-staged infrastructure solution supported by NSW Government

  • Stage 1: Installation of temporary weirs and pump station, extending supply for

approximately four months

  • Stage 2: Construction of permanent infrastructure, pipeline for Chaffey Dam to existing

Dungowan pipeline that would ensure Tamworth does not run out of town water supply (under drought-of-record conditions) if constructed early enough.

slide-34
SLIDE 34

Stage 1 – Temporary Weirs

Stage 1 – Install Temporary Weirs on the Peel River To reduce heavy transmission losses and extend water supply. WaterNSW is proposing to install temporary weirs on the Peel river at two locations:

– Dungowan Village

  • Allows for pooling of water to be pumped into the existing TRC owned Dungowan pipeline for

delivery to Tamworth

  • Water pumped via a temporary pump station with a temporary pipeline of approximately 700M in

length from temporary weir to existing Dungowan Pipeline.

– Jewry Street

  • to control flow downstream of Tamworth and provide further backup of town supply
  • Construction options being analysed (soil, gabion, sump), and will be removed

when supply is secured (pipeline operation or significant inflows)

  • Weirs are expected to be 1.5 to 2m high, and store 22ML (capacity of Dungowan

pipeline)

  • Tributary flows downstream of the dam will continue
  • Installation required by November 2019 to maximise available water supply
  • Funding commitment of $3.4M by Minister Pavey to complete the works

35

slide-35
SLIDE 35

Stage 1 – Location of Infrastructure

Proposed temporary weir location Option for temporary pipeline route Option for temporary pipeline route

slide-36
SLIDE 36

37

slide-37
SLIDE 37

Stage 1 – Key Dates

  • Commencement of construction works at Dungowan is

likely to be early October 2019

  • Completion of construction works at Dungowan is early

November 2019.

  • Pump Station Operational at Dungowan same time
  • Completion of Construction works a Jewry St to be

confirmed after Dungowan project is completed.

38

slide-38
SLIDE 38

39

Local Tributary inflows

  • nly below weir.
slide-39
SLIDE 39

What about impacts on Fish and Wildlife?

There is very likely to be if drought continues and inflows remain low… Critical human needs is now the top priority. Here is what we are doing

  • Working with DPI Fisheries around priority refuge water holes.
  • Monitor water quality and quantity
  • Tributary inflows will flow through the system
  • Community can report issues with fish / wildlife to DPI Fisheries
  • n 1800 043 536

41

slide-40
SLIDE 40

Stage 2 – Permanent Pipeline

Stage 2 – Construction of a Permanent Pipeline

  • Pipeline (approx. 17-20km in length) from Chaffey Dam to Dungowan Town

(and connecting to the existing pipeline owned by TRC), which would conserve Chaffey’s remaining storage by reducing transmission losses on the Peel River.

  • Critically, this project would provide long-term drought security for

Tamworth, and would ensure the town does not run out of water supply (under drought-of-record conditions) provided it is installed early in 2020.

  • Funding of $1.9M announced my Minister Pavey to complete planning
  • works. Funding for construction (~$38M) subject to further Govt approval.
  • Where possible construction to be within existing road easements or land

within the Chaffey Dam property boundary.

42

slide-41
SLIDE 41

Where could the pipeline run?

Stage 2 Two routes are to be considered:

  • Currently preferred route (~18.5 km) via Back-Woolomin Road (Red Line).
  • Alternate route (~16.5 km) via Tamworth-Nundle Road (Yellow Line).
  • A third “Yellow, Pink & Red Lines” connecting pipeline of about 490 m length along Westbank Road at

Woolomin is also to be considered.

slide-42
SLIDE 42

Stage 2 – Permanent Pipeline

Pipeline route

  • Pipeline route has not been selected:

– Review of Environmental Factors to be completed. This will confirm the required approval pathways, which are expected to be numerous. – Engagement with impacted landholders to be completed Key Dates

  • Extremely challenging timeframes with multiple parallel paths
  • Targeting award of D&C Contract in September 2019
  • Construction commencement pending

– Environmental approvals – Pipe availability – Selected route – Contractors installation methodology

slide-43
SLIDE 43

Stakeholder Coordination, Design and Scope Development – 3 Months Initiation – 1 months Tender – 3 Months Resource allocation – 1 months Planning and Environmental Approvals – 3 Months Funding and Approvals – 2 Months Procurement – 3 Months Detailed Design – 3 Months Construction – 3 Months Commission – 1-2 Months Project Close – 1-2 Months

Total Project Delivery Time = 9 Months

Route Selection, Land Identification and Acquisition – 3-4 Months

Key Challenge - Time

What have we done to reduce timeframe:

  • Engaged additional resources
  • Working closely with Tamworth Council to coordinate

project

  • Early briefings to Government Approval agencies
  • Financial approval process commenced
  • Land / Route selection – primarily council land
  • Early Contractor Involvement process
  • Pipe capacity / size review to being prioritised
  • Pipe Suppliers engaged to minimise lead time
  • Lessons learnt from delivering the Broken Hill Pipeline
slide-44
SLIDE 44

When do the temporary weirs get removed ?

Two triggers for removal 1) Dungowan Pipeline project is installed and operational. 2) Chaffey Dam has more than two years supply in storage. Which ever occurs first !

slide-45
SLIDE 45

Such is the severity of the drought and forecasts showing no improvement….. Doing nothing is simply not an option. A collaborative response between NSW Government, WaterNSW, Tamworth Regional Council is needed to secure Critical Human Water supply needs.

slide-46
SLIDE 46

Next Steps

  • If you are a riverfront landholder with BLR rights with no

alternate water supply (town water supply connected or existing bore etc) option, please let us know.

  • Will be back to talk to the community in Mid October,
  • WaterNSW to update Tamworth Water Taskforce in 2 weeks.
  • Continue planning and feasibility on Stage 2 Pipeline project.
  • Updates also via our website, social media and local media.
slide-47
SLIDE 47

49

Questions?

slide-48
SLIDE 48

Fact Sheets available today DPI site www.industry.nsw.gov.au for facts Visit the website at: waternsw.com.au/drought For information including water availability reports and drought reports go to: https://www.waternsw.com.au/supply/drought-

information/regional-nsw

Call us on: 1300 662 077

Subscribe at: waternsw.com.au/subscribe

For weekly customer drought updates and more information

50

More information

slide-49
SLIDE 49

More Information Bores

For specific inquiries about stock and domestic bores (Basic landholder rights bores) email waterregnorth@waternsw.com.au Nicole Gleeson-Lendon’s (02) 9849 9960 The WNSW general inquiry number – 1300 662 077

Customer.Helpdesk@waternsw.com.au

Early Warning network Registration

(EWN)- Via registration forms available here tonight.

slide-50
SLIDE 50

Dedicated Peel Valley information

Facebook Group

https://www.facebook.com/groups/WaterNSWPeelRiver/

Dedicated web pages

slide-51
SLIDE 51

53

Thankyou for your attendance