outfall project
play

OUTFALL PROJECT PORT COMMUNITY LIAISON COMMITTEE - DELTA John Newby - PowerPoint PPT Presentation

Annacis Island Wastewater Treatment Plant OUTFALL PROJECT PORT COMMUNITY LIAISON COMMITTEE - DELTA John Newby Andrea Winkler SENIOR VICE PRESIDENT PROGRAM MANAGER CDM SMITH PUBLIC INVOLVEMENT LIQUID WASTE SERVICES Delta, Tuesday, March 7,


  1. Annacis Island Wastewater Treatment Plant OUTFALL PROJECT PORT COMMUNITY LIAISON COMMITTEE - DELTA John Newby Andrea Winkler SENIOR VICE PRESIDENT PROGRAM MANAGER CDM SMITH PUBLIC INVOLVEMENT LIQUID WASTE SERVICES Delta, Tuesday, March 7, 2017

  2. Project Overview 2

  3. Project Setting 3

  4. Outfall System Requirements • Provide a total capacity of 25.3 m 3 /s (i.e. Stage VIII PWWF) at a 200-year river level of 103.18 m GD. • Achieve a minimum dilution ratio of 20:1 under slack water and low flows in the river • Meet “Post Disaster” requirements in accordance with MV Seismic Design Criteria • Meet all other standard requirements for MV facilities 4

  5. Project Plan 5

  6. Selected Diffuser Location 6

  7. Permitting Activities • Integrated Liquid Waste Resource Management Plan (GVS&DD) • Ministry of Environment (MoE): Stage 1 and 2 EIS • Port of Vancouver (VFPA): PER Submission • Environment and Climate Change Canada (ECCC): Disposal at Sea • Fisheries and Oceans Canada (DFO): Request for Review • Ministry of Forests, Lands and Natural Resource Operations (FLNRO): WSA Change Approval Submission • Transport Canada (TC): Navigation Corporation of Delta • • First Nations Engagement (MV, VFPA, FLNRO) 7

  8. Construction Impacts 8

  9. Construction Elements and Impacts  Outfall Tunnel and Shaft Construction  Traffic (excavation spoil, segments, concrete)  Work Hours / Noise (minor)  Outfall Riser  Navigation (generally within safety zone)  River Caisson (piles/sheet piles, excavation spoil, concrete)  Work Hours / Noise (limited periods)  Diffuser System  Navigation (generally within safety zone)  Buried Diffuser Pipeline (dredging, bedding, backfill, riprap) 9

  10. Tunnel Launch Shaft Site 10

  11. Riser Shaft Plan 11

  12. Riser Shaft Section 12

  13. Diffuser Section 13

  14. Dredge Prism 14

  15. Design and Construction Schedule  March 2017 – 60% Design Complete  April 2017 – DFO Application for Review Spring/Summer 2017 – Public and First Nations Engagement  August 2017 – 90% Design Complete   September 2017 – MoE Stage 2 EIS, VFPA Application, FLNRO  April 2018 – RFP Issued  January 2019 – Notice to Proceed, Shaft Construction June 2019 – Start of In-River Riser Construction  June 2020 – Dredging and Diffuser Installation  15

  16. Construction Schedule 16

  17. Consultation & Communications 17

  18. Role of Public Involvement 18

  19. 19

  20. Communi mmunications cations Impac acted ed Groups CLO* Interviews/ Fact sheet Website Road and River Mobilization Meetings** Signage Notification Businesses       Marine users       Environmental groups      Agricultural users      General public     First Nations     * Community Liaison Officer ** As required 20

  21. Ti Time meline line Design ign (30%) %) Design ign (60%) %) Design ign (90%) %) RFP issued ued Pre Pre-co cons nstruc uction ion During ing cons nstruc uction ion Summer er 2018 In Advanc ance of Spring ng-Sum Summer er Spring ng 2018 2019 - 2021 Summer er 2016 Summer er - Fall l 2017 (Min.10 business Constru ruction tion 2017 (6-8 months) (ongoing) days in advance of construction) • Meet with • Presentation Submit Port • Fact sheet • Newsletters • Notifications Corporation to PCLC application including: Engagem agemen ent t • Newspaper ad • Road/river • Website updates of Delta Acti tivi viti ties es • Draft Construction signage • Final • Road/river • Website Communications Construction signage Plan Communication • Traffic advisories • First Nations Plan submitted Engagement Plan to Port of • CLO Vancouver • Ongoing First Nations engagement 21 • High impact stakeholder meetings

  22. Businesses • Businesses located along construction/outfall project route (and AIWWTP upgrade project) • Businesses located on Annacis Island but not directly affected by construction • Businesses (and some residents) on the southern shore of the river 22

  23. Environmental Groups • Metro Vancouver Watch • Fraser River Sturgeon Conservation Society • Save the Fraser BC Nature • • David Suzuki Foundation • Nature Vancouver • Pacific Salmon Foundation • Pacific Wildlife Foundation • South Fraser Action Network • Georgia Straight Alliance • Fraser Health Authority 23

  24. Marine Users • Catherwood • Quality Towing • Council of Marine Carriers • Samson Tugboats • Delta Tug & Barge Ltd. • Seaspan • Forrest Marine • Saam Smit Canada Inc. • Fraser River Pile and • SRY Rail Link Dredge • Trident Navigation Ltd. • Fraser River Pilots • Valley Towing • Harken Towing • Vancouver Pile and Dredge • Hodder Towing • JJM Construction Ltd. • LaFarge Canada • Ledcor • Amix Marine Services • Mercury Launch & Tug LTD. North Arm Transportation • Quadrant Towing • 24

  25. Agricultural Groups • Delta Farmer’s Association • Delta Farmer’s Institute 25

  26. Port Community Liaison Committee - Delta 26

  27. Questions or comments?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend