SEPTEMBER 5 - 7, 2018
1
Todd Maersch Consultant Transmission Line Engineer American Transmission Co.
Todd Maersch Consultant Transmission Line Engineer American - - PowerPoint PPT Presentation
Todd Maersch Consultant Transmission Line Engineer American Transmission Co. SEPTEMBER 5 - 7, 2018 1 Traditional Methods for Foundation Installation Traditional Vibratory Direct Bury SEPTEMBER 5 - 7, 2018 2 SEPTEMBER 5 - 7, 2018 3
SEPTEMBER 5 - 7, 2018
1
Todd Maersch Consultant Transmission Line Engineer American Transmission Co.
SEPTEMBER 5 - 7, 2018
2
SEPTEMBER 5 - 7, 2018
3
SEPTEMBER 5 - 7, 2018
4
SEPTEMBER 5 - 7, 2018
5
SEPTEMBER 5 - 7, 2018
6
SEPTEMBER 5 - 7, 2018
7
SEPTEMBER 5 - 7, 2018
8
Direct Bury Traditional Vibratory Installation Solo-Driver™ Method Equipment Required
derrick
Crew Size 5 5 2-3 Overhead clearance 60-80 ft. 60-80 ft. 30-40 ft. Total Installation Time 150 minutes/structure 4 installations/day 75 minutes/caisson 8 installations/day 25 minutes/caisson 18 installations/day
SEPTEMBER 5 - 7, 2018
9
SEPTEMBER 5 - 7, 2018
10 10
SEPTEMBER 5 - 7, 2018
11 11
SEPTEMBER 5 - 7, 2018
12 12
– Reduced equipment costs – Reduced labor costs – Reduced project risk dollars due to smaller construction window
SEPTEMBER 5 - 7, 2018
13 13
– SOIL TYPE
– ACCESS
SEPTEMBER 5 - 7, 2018
14 14
– 9,600 miles of transmission lines – 554 substations
SEPTEMBER 5 - 7, 2018
15 15
SEPTEMBER 5 - 7, 2018
16 16