Presented by Jeffrey R. Appelbaum Pro roject Scope pe Buil - - PowerPoint PPT Presentation

presented by jeffrey r appelbaum
SMART_READER_LITE
LIVE PREVIEW

Presented by Jeffrey R. Appelbaum Pro roject Scope pe Buil - - PowerPoint PPT Presentation

Presented by Jeffrey R. Appelbaum Pro roject Scope pe Buil ildin ing Siz ize -- -- 1,003, 03,000 s 000 sf Site e Area -- -- 14.6 14.6 A Acr cres Dev evelopme ment B Budget--$4 $465M 65M Const nstruc


slide-1
SLIDE 1

Presented by Jeffrey R. Appelbaum

slide-2
SLIDE 2

 Pro

roject Scope pe

  • Buil

ildin ing Siz ize --

  • - 1,003,

03,000 s 000 sf

  • Site

e Area --

  • - 14.6

14.6 A Acr cres

  • Dev

evelopme ment B Budget--$4 $465M 65M

  • Const

nstruc uction n Sche hedul dule

 Const struction S Sta tart D t Date te– Januar uary 3 3, 2011 11  Substant antial al C Completion D n Date – Au August 3 31, 2 2013

 Project C

t Compone nents nts

  • Conve

nvent ntion n Center er –  767,000 7,000 sf unde der Mal alls B B an and C d C  230,000 sf high quality exhibit hall space  60,000 sf high tech, flexible meeting room space  31,000 sf column free ballroom space

  • Medi

dical Mart  235,000 5,000 sf a at St. C . Clair a and O Ontario  100,000 sf permanent show room space  11,000 sf junior ballroom  2,000 sf retail

  • Mall B and

d C Hardsc dscape ape and d Softsc scape pe

slide-3
SLIDE 3

 75%

Cons nstr truct uction D n Docum cument S ent Set Appro rove ved

 100%

0% Cons nstruct uction D n Docum cumen ent Set et - Prepa pared t d to Recom

  • mmend

d for Con

  • ndi

diti tion

  • nal Appr

prov

  • val
  • Ce

Cert rtain in ele lements in in pro roce cess of fin inal l refineme ment

slide-4
SLIDE 4

 PMC

  • Lead--Steve Zannoni

 Conventional Wisdom

  • Contract Amendment #3; Services for Remainder of

Project

slide-5
SLIDE 5

 Unique and proprietary convention center

knowledge

 Consulted with the County since 2008  Drafted the County Program Requirements  County’s watchdog regarding operational

and program requirements

 Review and advice has assisted in causing

developer to make major design modifications for benefit of County

slide-6
SLIDE 6

 Current Contract through Design Development

Phase (did not receive full services contract at

  • utset of Project); Contract Amount to date is

$278,400

 Amendment # 3 is for $270,000 (services for

remainder of Project)

 Amendment #3 Scope of Services are through

construction and commissioning including:

  • Program and Operational Milestone Reviews
  • Construction Document Reviews
  • Design revision Reviews
  • Operational Scope and Budget Reviews
  • Facility Commissioning
slide-7
SLIDE 7

 On sch

chedule le for r Augu gust 31, 31, 2013 2013 Substantia ial l Comple leti tion

 To

To date, e, $71. 71.2M 2M of

  • f co

construct ction in in pla lace ce ($ ($8. 8.26M 26M durin ring g mon

  • nth

th of

  • f August

st). ).

 Pro

roject ct is is 20 20 % co comple lete based on billin illings gs to dat date for Work in n Plac ace and and Stored d Mat Materials

 45 of 54 Bid

d pac packages have have be been awar awarded

 On sch

chedule le to re rece ceiv ive LEED LEED Silv ilver r Ce Cert rtif ifica icatio ion

slide-8
SLIDE 8

.

slide-9
SLIDE 9

8/26/11 -- East Convention Center Concourse (Formwork/Rebar Placement)

slide-10
SLIDE 10

9/10/11– Pouring Final Caisson (66 Caissons—All accepted!)

slide-11
SLIDE 11

Pouring One of Three Mat Slabsr

slide-12
SLIDE 12
slide-13
SLIDE 13

9/20/2011 --Erecting Steel; Ballroom Pre- Function Area

slide-14
SLIDE 14

On-Site Ballroom Truss Assembly (120 ft -- 1st of 30 trusses)

slide-15
SLIDE 15

Crane positioning for Truss pick

slide-16
SLIDE 16

Today—First Truss lifted in Place!

slide-17
SLIDE 17

 St. Clair Crack  Methane Collection  West 3d Street Elevated Roadway

slide-18
SLIDE 18

 Data Collection has been completed

  • Soil borings, inclinometers, tilt meters, crack meters, Ground

Penetrating Radar, video of existing sewer

 No Material Impact to Project Construction/Schedule  Design/Builder Consultant’s Recommendations

  • St.Clair can be temporarily patched and reopened immediately
  • Long term resurfacing at conclusion of project

 City has requested additional data– all data has been

provided

 Meeting scheduled to discuss reopening  Responsibility for costs

slide-19
SLIDE 19

 After installation of caissons and micropiles,

low levels of methane gas continued to be

  • bserved

 Design Builder engaged SCS Engineers to

investigate; result is design and implementation of conventional gas collection and venting system

 Cost-- $200k (to be covered by Developer’s

Contingency)

slide-20
SLIDE 20

 Engineers have discovered severe deterioration of

underside of existing elevated road structure

 The “bridge deck” needs to be replaced  The new road must be operational by 3/1/11 in

  • rder to avoid cost and schedule impacts to the

project GMP

 Must start the new deck replacement design by no

later than 10/7/11

 Probable Cost -- $1.6M

slide-21
SLIDE 21
slide-22
SLIDE 22

CLEVELAND MEDICAL MART TIMELINE

2011 2012 2013 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Demolition Deep Piles & Caisson Foundations Steel Erection Pouring of New Concrete Deck Begin Installation of Med Mart Façade Buildings Weather Enclosed Interior Build-Out Tenant Build-Out at Med Mart Grand Opening

slide-23
SLIDE 23

March 2011 145 MM Summer 2012 580MM +Fitout May 2011 185 MM June 2011 234 MM Aug 2011 234 MM

slide-24
SLIDE 24

 To date…only 1 accident resulting in lost

time.

slide-25
SLIDE 25

Contr

  • ntract G

Goa

  • al

Actu tual to to Date te SBE 25% 32%* County Residency 40% 47% City Residency 20% 22% For period concluding 8/21/2011 *42 SBE subcontractors have been hired by their respective prime contractors for the first time.

slide-26
SLIDE 26

 We have agreed to identify all SBE contractors

and post on County Website

slide-27
SLIDE 27

 We have agreed to post breakout hours

expended by prime contractor, according to:

  • Jurisdiction (City or County)
  • Minority
  • Female
slide-28
SLIDE 28
slide-29
SLIDE 29

 Current project includes “Baseline” Mall

Improvements

 Group Plan Commission seeks enhancements;

but certain design elements must be incorporated now to avoid foreclosing future

  • pportunities

 Design must also be sufficiently advanced to

demonstrate possible enhancements

slide-30
SLIDE 30

 Phase One – Masterplan / CMMCC Baseline

Update

 Phase Two – Group Plan Component

Confirmation and Infrastructure Incorporation in CMMCC Baseline Documents

  • Incorporate the necessary utilities and

infrastructure layout, connections, access, and routing path to allow the Group Plan Masterplan enhancements to be realized in subsequent phases.

  • (Phase 2A)--Conceptual Work
  • (Phase 2B)–- CD Revisions

 Phase Three – Fund Raising Materials.

slide-31
SLIDE 31

slide-32
SLIDE 32
slide-33
SLIDE 33