SLIDE 32 www.energy.gov/EM 32
System Acceptance Testing (CLIN 0020)
equipment installation, inspection, and construction acceptance testing, systems will be tested under the direction of the DOE’s startup test manager
completion of the system ATPs, an integrated system ATP will be performed to support acceptance and turnover to operations.
Process/system Associated equipment to be tested
Headworks Intake and Base Flow Bar screen, base flow gate, storm flow gate, base flow parshall flume, storm flow parshall flume, base flow transfer pumps, chemical metering system, associated equipment, valves, I&C Storm Flow Storm flow pumps, storm flow sump pumps, chemical metering system, associated equipment, valves, I&C Grit Handling Grit pumps, grit washer, grit room sump pumps, grit collection, associated equipment, valves, I&C Storm water Storage Storm water tank, tank mixers, associated equipment, valves, I&C ATP = acceptance test procedure I&C = instrumentation and control