ICMC Meeting #3 March 2015 MEETING AGENDA Introduction of ICMC - - PowerPoint PPT Presentation

icmc meeting 3
SMART_READER_LITE
LIVE PREVIEW

ICMC Meeting #3 March 2015 MEETING AGENDA Introduction of ICMC - - PowerPoint PPT Presentation

Ashbridges Bay Treatment Plant Outfall Conceptual Design & Receiving Water Assessment ICMC Meeting #3 March 2015 MEETING AGENDA Introduction of ICMC & Project Team Meeting Objective Project Background Evaluation of


slide-1
SLIDE 1

Ashbridges Bay Treatment Plant Outfall Conceptual Design & Receiving Water Assessment

ICMC Meeting #3

March 2015

slide-2
SLIDE 2

MEETING AGENDA

  • Introduction of ICMC & Project Team
  • Meeting Objective
  • Project Background
  • Evaluation of Alternatives
  • Project Implementation
  • Achieved Outcomes
  • Discussion

2

slide-3
SLIDE 3

INTRODUCTIONS

  • Personal Introductions
  • Project Team
  • CH2M HILL – Prime consultant for outfall modelling
  • Hatch Mott MacDonald – Outfall conceptual design
  • Baird – Lake modelling and sediment modelling
  • Previous ICMC Meetings
  • March 2012 – Background and Project Approach
  • October 2013 – Preliminary Evaluation of Alternatives

3

slide-4
SLIDE 4

Meeting Objective

4

To obtain ICMC input on the draft conceptual

  • utfall design.

MEETING OBJECTIVE

slide-5
SLIDE 5

PROJECT BACKGROUND

5

slide-6
SLIDE 6

WHY ARE WE LOOKING TO REPLACE THE EXISTING OUTFALL?

  • The existing outfall was

constructed in the late 1940s and has insufficient capacity

  • The existing outfall does not

meet current regulatory standards

  • For these reasons a

commitment to the public was made to replace it

6

slide-7
SLIDE 7

PROJECT OBJECTIVE & SUCCESS FACTORS

  • Project Objective
  • Deliver a conceptual design for a new outfall that meets

regulatory acceptance and improves nearshore water quality in Lake Ontario

  • What are the important success factors for the

project?

  • Achieve regulatory endorsement and acceptance on the

Conceptual Design

  • Gain stakeholder understanding
  • Develop an economically and environmentally feasible solution
slide-8
SLIDE 8

PROJECT OBJECTIVE & SUCCESS FACTORS

  • Your key success factors
  • Reduce impacts on the natural environment
  • Effective stakeholder process
  • Fulfills EA commitments
  • Timely project completion

(From March 2012 ICMC meeting)

slide-9
SLIDE 9

EVALUATION OF ALTERNATIVES

9

slide-10
SLIDE 10

10

EVALUATION PROCESS

We were here at the last ICMC meeting in October 2013 We are now here

slide-11
SLIDE 11

11

SCREEN OUTFALL CONFIGURATIONS Recap from previous meeting

Outfall Lengths that Passed Screening 2700m 3500m

  • Configurations based on 1986 preferred

alignment which is clear of buried valley and ridge features

  • “Must Have” Screening Criteria included:
  • Mixing performance
  • Water quality at water treatment plant intakes
  • Water quality at recreational beaches
  • Longer outfall lengths met mixing and water

quality criteria

slide-12
SLIDE 12

12

  • Tunnel

Construction

  • Open Cut

Construction

  • Hybrid Construction

DEVELOP OUTFALL ALTERNATIVES Construction Approaches

slide-13
SLIDE 13

13

Criteria Categories:

  • Technical – Ease of implementation, operation and maintenance
  • Natural – Aquatic systems, terrestrial systems, air quality
  • Social – Public health, safety of plant and construction workers,

quality of life

  • Economic – Life-cycle costs

ASSESS OUTFALL ALTERNATIVES Evaluation Criteria

slide-14
SLIDE 14

14

ASSESS OUTFALL ALTERNATIVES Tunnel Construction

  • No dredging required - minimizes social and natural impacts
  • Fewer permits
  • Less complex to construct
slide-15
SLIDE 15

15

ASSESS OUTFALL ALTERNATIVES Open Cut Construction

  • Shoreline excavation and shallow water dredging – high

social and natural impacts

  • More permit requirements
  • Construction limited by weather and timing windows
slide-16
SLIDE 16

16

ASSESS OUTFALL ALTERNATIVES Hybrid Construction

  • Dredging in deeper water – fewer social and natural impacts
  • Moderate permit requirements
  • A portion of construction is limited by weather and timing

windows

slide-17
SLIDE 17

17

  • Single tunnel
  • Similar to 1986 Concept
  • 7.0m internal diameter
  • 3500m length
  • Tunnel Boring Machine

(TBM) in bedrock

  • 61 vertical “tunnel risers”
  • 61 diffuser ports

RECOMMENDED ALTERNATIVE 3500m Tunnel

slide-18
SLIDE 18

18

RECOMMENDED ALTERNATIVE 3500m Tunnel

slide-19
SLIDE 19

19

Total Project Cost (2020 CAD) $340M Total Estimated Project Duration 7.3 years

RECOMMENDED ALTERNATIVE Cost Estimate and Schedule

2015 2016 2017 2018 2019 2020 2021 2022

Completion Tender Award Project

Construction Design

slide-20
SLIDE 20

ACHIEVED OUTCOMES

20

slide-21
SLIDE 21

21

  • Capacity shortfall of existing outfall has been addressed
  • New outfall peak capacity will be 3,900 million litres per day
  • Outfall is designed to not discharge through seawall gates to

Ashbridges Bay

INCREASED OUTFALL CAPACITY

slide-22
SLIDE 22

IMPROVED NEARSHORE WATER QUALITY

PROPOSED OUTFALL

slide-23
SLIDE 23

EA CONDITIONS HAVE BEEN MET

EA Condition Is the Condition Met?

Condition (1) – Document effluent quality for blended effluent during secondary bypass events.

YES

Condition 10 (ii) – Meet Provincial Water Quality Objectives (PWQO) at the edge of the mixing zone

YES

Condition 10 (iii) – Mitigate impacts on the Island and Harris WTPs

YES

Condition 10 (iii) – Eliminate need for seawall gates

YES

Condition 10 (viii) – Mitigate impacts on the beaches and shoreline

YES

Condition 12 – Mitigate impacts on fish and fish habitat

YES

23

slide-24
SLIDE 24

24

  • Met with the ICMC at each stage of this project
  • We will finalize the conceptual design after receiving your input

COMMITMENT TO THE PUBLIC

slide-25
SLIDE 25

DISCUSSION

25