Nauset Regional High School Feasibility Phase (PSR) PROJECT - - PowerPoint PPT Presentation

nauset regional high school
SMART_READER_LITE
LIVE PREVIEW

Nauset Regional High School Feasibility Phase (PSR) PROJECT - - PowerPoint PPT Presentation

School Building Committee April 10, 2019 Nauset Regional High School Feasibility Phase (PSR) PROJECT MANAGEMENT Massachusetts School Building Authority ADDITIONAL PROGRAMMING REQUESTS Nauset Regional High School Eastham, MA ADDITIONAL


slide-1
SLIDE 1

Nauset Regional High School

Feasibility Phase (PSR)

School Building Committee April 10, 2019

PROJECT MANAGEMENT Massachusetts School Building Authority

slide-2
SLIDE 2

Nauset Regional High School

Eastham, MA

ADDITIONAL PROGRAMMING REQUESTS

slide-3
SLIDE 3

Nauset Regional High School

Eastham, MA

ADDITIONAL PROGRAMMING REQUESTS (PSR PHASE)

CORE ACADEMIC (SCIENCE)

GREEN HOUSE x grossing factor

TOTAL: HEALTH & PE

LOCKER ROOMS (Gender-Neutral, 2 @ 350 sf) PE OFFICES(2 @ 150 sf) x grossing factor

TOTAL AUDITORIUM / DRAMA

AUDITORIUM INCREASE TO 750 x grossing factor

TOTAL

400 SF 1.49 596 SF

700 SF 300 SF 1.49 1,490 SF 1,491 SF 1.49 2,222 SF

596 SF x $430* $256,280 1,490 SF x $430* $640,700 2,222 SF x $430* $955,460

* BASED ON PDP ESTIMATES WITH AN AVERAGE OF $430/SF BUILDING COST

slide-4
SLIDE 4

Nauset Regional High School

Eastham, MA

SUSTAINABILITY

slide-5
SLIDE 5

Nauset Regional High School

Eastham, MA

SUSTAINABLE DESIGN: Planning for a Zero Energy School

(EUI per ft2)

90-120 (TBD) 65 40’s 35-40 25 10-15 National Average Existing Nauset School MA Average MSBA School

(LEED/ NECHPS)

Code Zero Energy Net Positive Energy Energy Use Intensity per sq ft

Design & Effjciency

Potential

Low Energy Zero Energy Renewable Energy

slide-6
SLIDE 6

Nauset Regional High School

Eastham, MA

SUSTAINABLE DESIGN: Strategies to Achieve Net Zero Energy

Architectural

Increase Thermal Envelope

  • Walls (Exposed Exterior Concrete Frame): Wrap concrete frame with

insulation and new cladding

  • Increased roof and interior insulation
  • Opportunities: Double-skin curtainwall, solar thermal collectors

integrated into envelope, and/or building-integrated PV (at right)

Mechanical / Electrical

Harness Renewable Energy

  • Solar Hot Water at roof or facade
  • Renewable Energy Generation, purchased ofg-site or generated on-

site [full A/C option is energy-intensive]

  • Photovoltaic canopies at parking
slide-7
SLIDE 7

Nauset Regional High School

Eastham, MA

SUSTAINABLE DESIGN: Strategies to Achieve Net Zero Energy

RESOUR. 300 SF T T GYMNASIUM Academic Entry Plaza Community Entry Plaza PRESENTATION/ BLACK BOX 2,000 SF MEDIA CENTER COMP. SEM. 600 SF MARINE SCIENCE LAB 1,440 SF SCIENCE LAB -1 BIOLOGY 1,440 SF SCIENCE LAB -2 1,440 SF BIOTECHNOLOGY LAB 1,440 SF CAFETERIA 4,525 SF DRESS 300 SF DRESS 300 SF AUDITORIUM 6,033 SF STAGE 1,600 SF MUSIC STOR. 500 SF MUSIC PRAC 4@75 SF JEWELRY/METALS 2,100 SF WOODWORKING 2,200 SF T VEST GALLERY / LOBBY ROBOTICS 1,400 SF ROBOTICS 1,400 SF COMP SCI/ BUSINESS 950 SF BUS/TECH DEPT.
  • OFF. 2
500 SF GALLERY / LOBBY VEST SCAMBLE SERVING 600 SF KITCHEN 2205 SF LIFE SKILLS 1,200 SF LOADING DOCK RECEIVING CUST. T TECH SUPPORT 450 SF COVERED WALKWAY STUDENT CAFE' SM. GRP 210 VIDEO LAB 2,400 sf T LOBBY OUTDOOR DINING SCIENCE GARDENS "BARN DOOR" ACCESS TO EXTERIOR BAND 2,000 SF PREP- TANKS STUDIO OFF. 1,450 sf STAFF LUNCH 476 SF STAFF WORK 453 SF T T OUTDOOR SCULPTURE GARDEN ATHL. VEST. T T T STOR. 300 SF PE STOR. 500 SF DEPT. OFF. 250 DEPT. OFF. 250 TEST 120 COVERED WALKWAY E PREP 300 SF SM. GRP 210 TEST 120 T T COVERED OUTDOOR AREA ADMIN VEST VEST NURSE LOBBY KILN GALLERY DEPT. OFF. 250 DEPT. OFF. 250 DEPT.
  • OFF. 3
500 SF T T T CERAMICS 1,800 SF ART 1,200 SF DARK RM. 400 SF
  • AUD. STOR.
SM. GRP 210 SM. GRP 210 OFF TEST 120 COVERED AREA AIR CONDITIONED SPACES DISPLACEMENT DISTRIBUTION RESOUR. 300 SF

OPTION 4A

SEMINAR 500 SF TRNR. OFF OFF PREP 300 SF CHEM. GYM BELOW PRESENTATION/ BLACK BOX BELOW SCIENCE LAB -5 1,440 SF SCIENCE LAB -6 1,440 SF CAFETERIA BELOW HOUSE BELOW STAGE BELOW CNTRL 200 SF ROBOTICS BELOW ART 1,200 SF MEDIA CENTER BELOW SCI_DEPT. OFF 500 SF T GLOBAL LEARNING TEST 120 BALCONY BAND BELOW COVERED CORRIDOR AT 2ND LEVEL CULINARY ARTS 1,500 SF FASHION/ 800 SF MIDI/ COMP. 420 SF DIGITAL GRAPHIC 400 SF GUIDANCE/ CAREER CENTER ADMIN BELOW LOCKER NO.1 2,534 SF LOCKER NO.2 2,534 SF T T SCIENCE LAB -3 1,440 SF FOREN 600 SF PREP 300 SF SCIENCE LAB -4 1,440 SF CHEM. AD OFF. 150 SF OT 500 SF PT 500 SF FITNESS 3,000 SF HEALTH / YOGA 1,200 SF TRAIN 580 SF OFF. 120 SF OFF. 120 SF COVERED CORRIDOR AT 2ND LEVEL E PREP 300 SF SCIENCE LAB -7 1,440 SF SM. GRP 210 TEST 120 T T CHORUS 1,000 SF DEPT. OFF. 250 DEPT. OFF. 250 ROOF T T T T DRAMA 850 SF JEWELRY/METALS BELOW WOODWORKING BELOW OFF. STOR OUTDOOR AREA BELOW SM. GRP 210 AIR CONDITIONED SPACES DISPLACEMENT DISTRIBUTION SEMINAR 500 SF RESOUR. 300 SF RESOUR. 300 SF

OPTION 4A

Gym Below AUDITORIUM BELOW STAGE BELOW CNTRL 200 SF T T DEPT. OFF. 500 SF (GREEN ROOF AREA: 15,000 SF) E AIR CONDITIONED SPACES DISPLACEMENT DISTRIBUTION

OPTION 4A

Gym Below

AUDITORIUM BELOW STAGE BELOW CNTRL 200 SF T T DEPT. OFF. 500 SF

(GREEN ROOF AREA: 15,000 SF)

E

AIR CONDITIONED SPACES DISPLACEMENT DISTRIBUTION

OPTION 4A

AIR DISTRIBUTION CONCEPT (COMBINATION FULL AC / DISPLACEMENT)

slide-8
SLIDE 8

Nauset Regional High School

Eastham, MA

SUSTAINABLE DESIGN: Strategies to Achieve Net Zero Energy

Option Description % Existing Gross SF Retained 905 students Building Hazmat/Demo Sitework TOTAL ** Net Zero Premium (6%) ** TOTAL (NET ZERO)

4A

Demo E + F 74% 220,350 $88.29M $5.84M $13.52M

$107.65M

$6.46M

$114.11M

4B

Demo 1/2 D, F, N 72% 220,350 $88.73M $5.88M $13.55M

$108.17M

$6.49M

$114.66M

5B

Demo A, C, 1/4 E, F 67% 220,350 $89.83M $5.83M $13.28M

$108.94M

$6.54M

$115.48M

6B

Demo C, E, F, G, N 37% 220,350 $94.09M $6.47M $13.84M

$114.4M

$6.86M

$121.27M

7B

Full Demo 0% 220,350 $94.85M $6.7M $14.48M

$116.03M

$6.96M

$123.M

* Estimated Cost subject to change as project is refined * Based on CMR Chapter 149a * Portables to be provided for 16 classrooms ** Net Zero Premium subject to change as project is refined

**NET ZERO Premium

(Approximate Hard Cost)

Construction Cost $ *

(Hard Cost)

Preliminary Design Program (PDP) Phase Cost Estimates with approximated Net Zero Premium associated costs. Costs will be refjned during the PSR Phase.

slide-9
SLIDE 9

Nauset Regional High School

Eastham, MA

DESIGN OPTIONS 4A, 4B, 5B, 6B and 7B

slide-10
SLIDE 10

Nauset Regional High School

Eastham, MA

OPTION 4A: 3-D MASSING

New Additions

  • 50%: Glazing (curtainwall / storefront)
  • 50%: Solid Walls: 20%: Precast Concrete

30%: “wood-like” Rainscreen

  • Fully-adhered PVC Roof

Existing Buildings

  • 25% of Facade: Retain existing concrete frame
  • 50% of Facade: Replace wood siding with “wood-like”

rainscreen infjll

  • 25% of Facade: Replace curtainwall/storefront/

windows

  • Reclad Building N entirely
  • PVC Roof: Maintain 100% existing
slide-11
SLIDE 11

Nauset Regional High School

Eastham, MA

OPTION 4B: 3-D MASSING

New Additions

  • 50%: Glazing (curtainwall / storefront)
  • 50%: Solid Walls: 20%: Precast Concrete

30%: “wood-like” Rainscreen

  • Fully-adhered PVC Roof

Existing Buildings

  • 25% of facade: Retain existing concrete frame
  • 50% of facade: Replace wood siding with “wood-like”

rainscreen infjll

  • 25% of facade: Replace curtainwall/storefront/

windows

  • PVC Roof: Maintain 100% existing
slide-12
SLIDE 12

Nauset Regional High School

Eastham, MA

OPTION 5B: 3-D MASSING

New Additions

  • 50%: Glazing (curtainwall / storefront)
  • 50%: Solid Walls: 20%: Precast Concrete

30%: “wood-like” Rainscreen

  • Fully-adhered PVC Roof

Existing Buildings

  • 25% of facade: Retain existing concrete frame
  • 50% of facade: Replace wood siding with “wood-like”

rainscreen infjll

  • 25% of facade: Replace curtainwall/storefront/

windows

  • Reclad Building N entirely
  • PVC Roof: Maintain 100% existing
slide-13
SLIDE 13

Nauset Regional High School

Eastham, MA

OPTION 6B: 3-D MASSING

New Additions

  • 50%: Glazing (curtainwall / storefront)
  • 50%: Solid Walls: 20%: Precast Concrete

30%: “wood-like” Rainscreen

  • Fully-adhered PVC Roof

Existing Buildings

  • 25% of facade: Retain existing concrete frame
  • 50% of facade: Replace wood siding with “wood-like”

rainscreen infjll

  • 25% of facade: Replace curtainwall/storefront/

windows

  • Reclad Building N entirely
  • PVC Roof: Maintain 100% existing
slide-14
SLIDE 14

Nauset Regional High School

Eastham, MA

OPTION 7B: 3-D MASSING

New Additions

  • 50%: Glazing (curtainwall / storefront)
  • 50%: Solid Walls: 20%: Precast Concrete

30%: “wood-like” Rainscreen

  • Fully-adhered PVC Roof
slide-15
SLIDE 15

Nauset Regional High School

Eastham, MA

CONSTRUCTION PHASE (Temporary Classrooms)

  • Lincoln School Example
slide-16
SLIDE 16

Nauset Regional High School

Eastham, MA

Temporary Classrooms | Lincoln School Modulars

FOR LINCOLN SCHOOL

  • 21 Classrooms (fjts approx.

30 students each)

  • 2 smaller classrooms
  • 4 multi-fjxture bathrooms

1 single-fjxture bathroom (all accessible)

  • Library
  • Teacher Break Room
  • Administrative offjces and

conference space

  • Anticipated Completion:

Summer 2022

  • Anticipated Time Savings

in Project Schedule: 1 year

CURRENT LAYOUT

AT HANSCOM

SCHOOL PROJECT

slide-17
SLIDE 17

Nauset Regional High School

Eastham, MA

Temporary Classrooms | Lincoln School Modulars

  • Buildings are all electric

with individually heated units

  • Temporary transformer to

be installed

  • Temporary septic, gas,

water, and telecom to be connected to existing on- site systems

  • Fully equipped with fjre

protection

  • Lincoln plan includes a

temporary Parking Lot and lot lighting

slide-18
SLIDE 18

Nauset Regional High School

Eastham, MA

School Tours | Rockland High School

160,000+ SF complete renovation (no addition)

  • Tight site (next to new

construction of middle school)

  • Full “gut renovation”
  • Occupied, phased by wing
  • f building
  • Limited natural light +

stafg blocking windows

  • LEED Silver certifjed
slide-19
SLIDE 19

Nauset Regional High School

Eastham, MA

School Tours | Winchester High School

288,840 SF Addition & Renovation

  • Tight urban site
  • Full “gut renovation”

plus new construction of additions

  • Occupied, phased with use
  • f approx. 35 temporary

classrooms (leased)

  • Similar Brutalist

architecture circa 1970’s

  • Enclosed outdoor

courtyard to create a large dining commons

  • Large windows and good

use of natural light

  • LEED Gold certifjed
slide-20
SLIDE 20

Nauset Regional High School

Eastham, MA

School Tours | Dearborn STEM 6-12 Academy

128,000 SF new construction

  • High-tech science labs
  • Common areas for

grade groups (“cohort commons”)

  • Glazed teacher offjces &

usable public space

  • Natural light
  • Highly effjcient building

management systems (low

  • perational costs)
  • LEED Gold certifjcation