nauset regional high school
play

Nauset Regional High School Feasibility Phase (PSR) PROJECT - PowerPoint PPT Presentation

School Building Committee April 10, 2019 Nauset Regional High School Feasibility Phase (PSR) PROJECT MANAGEMENT Massachusetts School Building Authority ADDITIONAL PROGRAMMING REQUESTS Nauset Regional High School Eastham, MA ADDITIONAL


  1. School Building Committee April 10, 2019 Nauset Regional High School Feasibility Phase (PSR) PROJECT MANAGEMENT Massachusetts School Building Authority

  2. ADDITIONAL PROGRAMMING REQUESTS Nauset Regional High School Eastham, MA

  3. ADDITIONAL PROGRAMMING REQUESTS (PSR PHASE) CORE ACADEMIC (SCIENCE) 596 SF GREEN HOUSE 400 SF x $430* x grossing factor 1.49 596 SF $256,280 TOTAL: HEALTH & PE 700 SF LOCKER ROOMS (Gender-Neutral, 2 @ 350 sf) 1,490 SF 300 SF PE OFFICES (2 @ 150 sf) x $430* 1.49 x grossing factor $640,700 1,490 SF TOTAL AUDITORIUM / DRAMA 2,222 SF 1,491 SF AUDITORIUM INCREASE TO 750 x $430* 1.49 x grossing factor $955,460 2,222 SF TOTAL * BASED ON PDP ESTIMATES WITH AN AVERAGE OF $430/SF BUILDING COST Nauset Regional High School Eastham, MA

  4. SUSTAINABILITY Nauset Regional High School Eastham, MA

  5. SUSTAINABLE DESIGN: Planning for a Zero Energy School (EUI per ft 2 ) 90-120 Energy Use Intensity per sq ft Design & (TBD) Effjciency 65 Low Energy Potential 40’s 35-40 25 Zero Energy 10-15 Renewable Energy National Existing MA MSBA Zero Net Code School Energy Positive Average Nauset Average (LEED/ Energy School NECHPS) Nauset Regional High School Eastham, MA

  6. SUSTAINABLE DESIGN: Strategies to Achieve Net Zero Energy Architectural Increase Thermal Envelope • Walls (Exposed Exterior Concrete Frame): Wrap concrete frame with insulation and new cladding • Increased roof and interior insulation • Opportunities: Double-skin curtainwall, solar thermal collectors integrated into envelope, and/or building-integrated PV (at right) Mechanical / Electrical Harness Renewable Energy • Solar Hot Water at roof or facade • Renewable Energy Generation, purchased ofg-site or generated on- site [full A/C option is energy-intensive] • Photovoltaic canopies at parking Nauset Regional High School Eastham, MA

  7. AREA DIGITAL LOCKER NO .1 BELOW ADMIN CENTER CAREER GUIDANCE/ 400 SF GRAPHIC 420 SF LOCKER NO .2 COMP . MIDI/ 800 SF FASHION/ 1,500 SF ARTS CULINARY AT 2ND LEVEL CORRIDOR 2,534 SF 2,534 SF BELOW AD OFF . HEALTH / YOGA 3,000 SF FITNESS 500 SF PT 500 SF OT 150 SF CHEM . T 1,440 SF SCIENCE LAB -4 300 SF PREP 600 SF FOREN 1,440 SF SCIENCE LAB -3 T COVERED BAND TRAIN 300 SF 1,440 SF SCIENCE LAB -5 BELOW BLACK BOX PRESENTATION/ BELOW GYM CHEM . PREP 1,440 SF OFF OFF TRNR . 500 SF SEMINAR OPTION 4A 300 SF RESOUR . DISPLACEMENT DISTRIBUTION SCIENCE LAB -6 CAFETERIA BALCONY MEDIA CENTER 120 TEST LEARNING GLOBAL T 500 SF OFF SCI_DEPT . BELOW 1,200 SF BELOW ART BELOW ROBOTICS 200 SF CNTRL BELOW STAGE BELOW HOUSE 1,200 SF 580 SF COVERED STAGE 500 SF OFF . DEPT . T T 200 SF CNTRL BELOW BELOW 15 ,000 SF) AUDITORIUM Below Gym OPTION 4A 300 SF RESOUR . 300 SF RESOUR . 500 SF (GREEN ROOF AREA: E DISPLACEMENT DISTRIBUTION T AIR CONDITIONED SPACES E 15 ,000 SF) (GREEN ROOF AREA: 500 SF OFF . DEPT . T 200 SF AIR CONDITIONED SPACES CNTRL BELOW STAGE BELOW AUDITORIUM Below Gym OPTION 4A DISPLACEMENT DISTRIBUTION SEMINAR AIR CONDITIONED SPACES OFF . 1,440 SF CHORUS T T 120 TEST 210 GRP SM . SCIENCE LAB -7 DEPT . 300 SF PREP E AT 2ND LEVEL CORRIDOR COVERED 120 SF OFF . 120 SF 1,000 SF OFF . 210 JEWELRY/METALS GRP SM . BELOW OUTDOOR AREA STOR OFF . BELOW WOODWORKING BELOW 850 SF 250 DRAMA T T T T ROOF 250 OFF . DEPT . AIR CONDITIONED SPACES 120 OPTION 4A COMP SCI/ LOBBY GALLERY / 500 SF OFF . 2 DEPT . BUS/TECH 950 SF BUSINESS 1,400 SF SCAMBLE ROBOTICS 1,400 SF ROBOTICS GALLERY / LOBBY VEST T 2,200 SF WOODWORKING 2,100 SF VEST SERVING 4@75 SF SUPPORT 210 GRP SM . CAFE' STUDENT WALKWAY COVERED 450 SF TECH 600 SF T CUST . RECEIVING DOCK LOADING 1,200 SF LIFE SKILLS 2205 SF KITCHEN JEWELRY/METALS PRAC LAB Plaza 600 SF SEM . COMP . CENTER MEDIA 2,000 SF BLACK BOX PRESENTATION/ Entry SCIENCE LAB Community Plaza Entry Academic GYMNASIUM T T 300 SF RESOUR . MARINE 1,440 SF MUSIC 300 SF 500 SF STOR . MUSIC 1,600 SF STAGE 6,033 SF AUDITORIUM 300 SF DRESS DRESS SCIENCE LAB -1 4,525 SF CAFETERIA 1,440 SF LAB BIOTECHNOLOGY 1,440 SF SCIENCE LAB -2 1,440 SF BIOLOGY VIDEO 2,400 sf TEST VEST DEPT . 250 OFF . DEPT . GALLERY KILN LOBBY NURSE VEST 250 ADMIN AREA OUTDOOR COVERED T T 120 TEST 210 OFF . DEPT . T 400 SF OFF 210 GRP SM . 210 GRP SM . AUD . STOR . RM . OFF . 3 DARK 1,200 SF ART 1,800 SF CERAMICS T T T 500 SF GRP SM . 300 SF STUDIO 453 SF WORK STAFF 476 SF LUNCH STAFF 1,450 sf OFF . TANKS PREP PREP- 2,000 SF BAND TO EXTERIOR ACCESS "BARN DOOR" SCIENCE GARDENS OUTDOOR DINING LOBBY T T OUTDOOR SCULPTURE GARDEN E WALKWAY COVERED 120 TEST 250 OFF . DEPT . 250 OFF . DEPT . 500 SF PE STOR . 300 SF STOR . T T T VEST . ATHL . DISPLACEMENT DISTRIBUTION SUSTAINABLE DESIGN: Strategies to Achieve Net Zero Energy AIR DISTRIBUTION CONCEPT (COMBINATION FULL AC / DISPLACEMENT) Nauset Regional High School Eastham, MA

  8. SUSTAINABLE DESIGN: Strategies to Achieve Net Zero Energy Preliminary Design Program (PDP) Phase Cost Estimates with approximated Net Zero Premium associated costs. Costs will be refjned during the PSR Phase. Construction Cost $ * **NET ZERO Premium Option Description % Existing Gross SF Retained (Hard Cost) (Approximate Hard Cost) 905 students Building Hazmat/Demo Sitework TOTAL ** Net Zero Premium (6%) ** TOTAL (NET ZERO) 4A $107.65M $114.11M Demo E + F 74% 220,350 $88.29M $5.84M $13.52M $6.46M 4B $108.17M $114.66M Demo 1/2 D, F, N 72% 220,350 $88.73M $5.88M $13.55M $6.49M 5B $108.94M $115.48M Demo A, C, 1/4 E, F 67% 220,350 $89.83M $5.83M $13.28M $6.54M 6B $114.4M $121.27M Demo C, E, F, G, N 37% 220,350 $94.09M $6.47M $13.84M $6.86M 7B $116.03M $123.M Full Demo 0% 220,350 $94.85M $6.7M $14.48M $6.96M * Estimated Cost subject to change as project is refined * Based on CMR Chapter 149a * Portables to be provided for 16 classrooms ** Net Zero Premium subject to change as project is refined Nauset Regional High School Eastham, MA

  9. DESIGN OPTIONS 4A, 4B, 5B, 6B and 7B Nauset Regional High School Eastham, MA

  10. OPTION 4A: 3-D MASSING Existing Buildings • 25% of Facade: Retain existing concrete frame • 50% of Facade: Replace wood siding with “wood-like” rainscreen infjll • 25% of Facade: Replace curtainwall/storefront/ windows • Reclad Building N entirely • PVC Roof: Maintain 100% existing New Additions • 50%: Glazing (curtainwall / storefront) • 50%: Solid Walls: 20%: Precast Concrete 30%: “wood-like” Rainscreen • Fully-adhered PVC Roof Nauset Regional High School Eastham, MA

  11. OPTION 4B: 3-D MASSING Existing Buildings • 25% of facade: Retain existing concrete frame • 50% of facade: Replace wood siding with “wood-like” rainscreen infjll • 25% of facade: Replace curtainwall/storefront/ windows • PVC Roof: Maintain 100% existing New Additions • 50%: Glazing (curtainwall / storefront) • 50%: Solid Walls: 20%: Precast Concrete 30%: “wood-like” Rainscreen • Fully-adhered PVC Roof Nauset Regional High School Eastham, MA

  12. OPTION 5B: 3-D MASSING Existing Buildings • 25% of facade: Retain existing concrete frame • 50% of facade: Replace wood siding with “wood-like” rainscreen infjll • 25% of facade: Replace curtainwall/storefront/ windows • Reclad Building N entirely • PVC Roof: Maintain 100% existing New Additions • 50%: Glazing (curtainwall / storefront) • 50%: Solid Walls: 20%: Precast Concrete 30%: “wood-like” Rainscreen • Fully-adhered PVC Roof Nauset Regional High School Eastham, MA

  13. OPTION 6B: 3-D MASSING Existing Buildings • 25% of facade: Retain existing concrete frame • 50% of facade: Replace wood siding with “wood-like” rainscreen infjll • 25% of facade: Replace curtainwall/storefront/ windows • Reclad Building N entirely • PVC Roof: Maintain 100% existing New Additions • 50%: Glazing (curtainwall / storefront) • 50%: Solid Walls: 20%: Precast Concrete 30%: “wood-like” Rainscreen • Fully-adhered PVC Roof Nauset Regional High School Eastham, MA

  14. OPTION 7B: 3-D MASSING New Additions • 50%: Glazing (curtainwall / storefront) • 50%: Solid Walls: 20%: Precast Concrete 30%: “wood-like” Rainscreen • Fully-adhered PVC Roof Nauset Regional High School Eastham, MA

  15. CONSTRUCTION PHASE (Temporary Classrooms) • Lincoln School Example Nauset Regional High School Eastham, MA

  16. Temporary Classrooms | Lincoln School Modulars F OR L INCOLN S CHOOL • 21 Classrooms (fjts approx. 30 students each) • 2 smaller classrooms • 4 multi-fjxture bathrooms 1 single-fjxture bathroom (all accessible) • Library • Teacher Break Room • Administrative offjces and conference space • Anticipated Completion: Summer 2022 • Anticipated Time Savings C URRENT L AYOUT in Project Schedule: AT H ANSCOM 1 year S CHOOL PROJECT Nauset Regional High School Eastham, MA

  17. Temporary Classrooms | Lincoln School Modulars • Buildings are all electric with individually heated units • Temporary transformer to be installed • Temporary septic, gas, water, and telecom to be connected to existing on- site systems • Fully equipped with fjre protection • Lincoln plan includes a temporary Parking Lot and lot lighting Nauset Regional High School Eastham, MA

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend