Monroe Avenue Complete Streets Community Meeting May 20, 2014 - - PowerPoint PPT Presentation

monroe avenue complete
SMART_READER_LITE
LIVE PREVIEW

Monroe Avenue Complete Streets Community Meeting May 20, 2014 - - PowerPoint PPT Presentation

Monroe Avenue Complete Streets Community Meeting May 20, 2014 Complete Streets Streets that are designed to consider the safety and Monroe Avenue Complete Streets convenience of all users of the transportation system including


slide-1
SLIDE 1

Community Meeting May 20, 2014

Monroe Avenue Complete Streets

slide-2
SLIDE 2

Monroe Avenue Complete Streets

Complete Streets

2

“Streets that are designed to consider the safety and convenience of all users of the transportation system including pedestrians, bicyclists, transit users, freight, and motor vehicle drivers and ensure that the needs of all users shall be accommodated and balanced so that even the most vulnerable – children, elderly, and persons with disabilities – can travel safely within the public right-of way.”

slide-3
SLIDE 3

Monroe Avenue Complete Streets

City Plans and Policies

3

  • City Council Goal #3: A multimodal transportation

network that supports sustainable land use and provides internal mobility and regional connectivity for Alexandrians

  • Complete Streets Policy: Alexandria shall

incorporate Complete Streets infrastructure into existing public streets to improve the safety and convenience of users and construct and enhance the transportation network for all users

  • Transportation Master Plan: Implement a

citywide bikeway network to serve all users and trip types, provide end-of-trip facilities, improve bicycle/transit integration, implement encouragement programs and improve safety

  • Pedestrian and Bicycle Mobility Plan
slide-4
SLIDE 4

Monroe Avenue Complete Streets

4

2013 Infrastructure Improvements

Project Total Quantity Completed Designed Redesigned streets through resurfacing projects 8 lane miles New sidewalk 7,550 feet 1,300 6,250 New and upgraded crosswalks 140 crosswalks New pedestrian countdown signals 6 intersections Signal modifications for conflict free crossings 1 intersection Access to transit pedestrian improvements 5 bus stops Rapid flashing beacons for uncontrolled crossings 3 crossings HAWK Signal for safer pedestrian crossing 1 crossing 15MPH Flashing School Zone signs 6 schools 1 5 Intersection redesign for pedestrian safety 3 locations 3 On street bicycle facility design 20 lane miles 12 8 Bicycle Box 1 intersection New bicycle parking spaces 100 spaces

slide-5
SLIDE 5

Monroe Avenue Complete Streets

Monroe Avenue Project Background

  • Spring 2013 – Community requests for

traffic calming on Monroe Avenue

  • September 2013 - Additional data

collection

  • October 2013 - Community meeting
  • Winter 2014 – Resurfacing Schedule
  • Spring 2014 - Expanded project scope

to include Complete Streets design

  • May 2014 – Community Meeting

5

slide-6
SLIDE 6

Monroe Avenue Complete Streets

Meeting Activities

  • Presentation
  • Questions and Comments
  • Mark location specific comments on

maps

  • Comment forms
  • Report back – main themes
  • Next Steps

6

slide-7
SLIDE 7

Monroe Avenue Complete Streets

Project Limits

  • Section 1: Leslie Ave. to Mt. Vernon Ave.
  • Section 2: Mt. Vernon Ave. to Russell Rd.
  • Section 3: Russell Rd. to Stonewall Rd.

1 2 3 7

slide-8
SLIDE 8

Monroe Avenue Complete Streets

Data Collection

Location 85th percentile speed Eastbound peak hour volume (8am) Increase since May 2010* Westbound peak hour volume (5pm) Increase since May 2010*

Monroe at Dewitt 25 mph 381 vph 87% (204vph) 483 vph 197% (162vph) Monroe at Wayne 32 mph 300 vph

  • 312 vph
  • Monroe at:

Total Crashes (2009-2013) Pedestrian Bicycle Vehicular Commonwealth 4 4

  • Mt. Vernon

2 2 Russell 2 2 East of Wayne 1 2 Leslie 1 1

*Data not collected at Wayne in 2010

8

slide-9
SLIDE 9

Monroe Avenue Complete Streets

Pedestrian and Bicycle Mobility Plan Recommendations – Section 1

Recommended bike lane Missing sidewalk Curb ramp deficiency

9

slide-10
SLIDE 10

Monroe Avenue Complete Streets

Recommended bike lane Missing sidewalk Curb ramp deficiency

Pedestrian and Bicycle Mobility Plan Recommendations – Sections 2 & 3

10

slide-11
SLIDE 11

Monroe Avenue Complete Streets

Existing Conditions – Section 1

11

slide-12
SLIDE 12

Monroe Avenue Complete Streets

  • Commonwealth to Hancock – 32’ with no parking on the

either side

  • Getting cyclists from Mt. Vernon to lanes on

Commonwealth

Existing Conditions – Section 2

12

slide-13
SLIDE 13

Monroe Avenue Complete Streets

Existing Conditions – Section 3

13

slide-14
SLIDE 14

Monroe Avenue Complete Streets

Types of Potential Improvements

  • Crosswalks
  • Curb ramps
  • Sidewalks
  • Signage
  • Bike lanes
  • Shared lanes
  • Speed boards

14

slide-15
SLIDE 15

Monroe Avenue Complete Streets

Considerations

  • Accessibility
  • Safety
  • Parking
  • Accommodating

pedestrians, transit, bicyclists, and motorists

  • Roadway width
  • Existing and future

development

  • Cost

15

slide-16
SLIDE 16

Monroe Avenue Complete Streets

Thank you! Questions and Comments

  • Hillary.Poole@AlexandriaVA.gov