Monroe Avenue Complete Streets Del Ray Citizens Association Novem - - PowerPoint PPT Presentation
Monroe Avenue Complete Streets Del Ray Citizens Association Novem - - PowerPoint PPT Presentation
Monroe Avenue Complete Streets Del Ray Citizens Association Novem ber 1 2 , 2 0 1 4 Complete Streets Streets that are designed to consider the safety and Monroe Avenue Complete Streets convenience of all users of the transportation
Monroe Avenue Complete Streets
Complete Streets
2
“Streets that are designed to consider the safety and convenience of all users of the transportation system including pedestrians, bicyclists, transit users, freight, and motor vehicle drivers and ensure that the needs of all users shall be accommodated and balanced so that even the most vulnerable – children, elderly, and persons with disabilities – can travel safely within the public right-of way.”
Monroe Avenue Complete Streets
City Plans and Policies
3
- City Council Goal # 3: A multimodal transportation
network that supports sustainable land use and provides internal mobility and regional connectivity for Alexandrians
- Complete Streets Policy: Alexandria shall
incorporate Complete Streets infrastructure into existing public streets to improve the safety and convenience of users and construct and enhance the transportation network for all users
- Transportation Master Plan: Implement a
citywide bikeway network to serve all users and trip types, provide end-of-trip facilities, improve bicycle/ transit integration, implement encouragement programs and improve safety
- Pedestrian and Bicycle Mobility Plan
Monroe Avenue Complete Streets
Monroe Avenue Project Background and Civic Engagement
- Spring 2013 – Community requests for traffic
calming on Monroe Ave.
- September 2013 - Data collection
- October 2013 - Community meeting
- February 2014 – Monroe Ave. listed on
resurfacing schedule
- March 2014 - Expanded project scope to include
Complete Streets design
- May 2014 – Public meeting # 1
- Sept 2014 – Public meeting # 2
- November 2014 – Del Ray Citizen’s Association
4
Monroe Avenue Complete Streets
Project Limits
- Section 1: Leslie Ave. to Mt. Vernon Ave.
- Section 2: Mt. Vernon Ave. to Commonwealth Ave.
- Section 3: Commonwealth Ave. to Stonewall Rd.
1 2 3 5
Monroe Avenue Complete Streets
Community Comments
6
Monroe Avenue Complete Streets
Response to Concerns
- Most com m ents were incorporated
into proposal
- Intersection improvements
- Pedestrian crossing improvements
- Speed reduction
- A few com m ents will be address
through other projects
- Safe Routes to School
- Som e com m ents will be addressed
with redevelopment
- Bury power lines
- Modify curb lines
7
Monroe Avenue Complete Streets
Important Considerations
- City Council adopted plans
- Transportation Master Plan
- Pedestrian and Bicycle Mobility Plan
- Complete Streets Policy
- Consider all street users
- Accessibility requirements
- Provide facilities for people with disabilities
- Emergency vehicle requirements and access
- Right of way constraints
- Existing and future development
- Cost
8
Monroe Avenue Complete Streets
Section 3: Commonwealth Ave. to
Stonewall Rd.
3 9
Monroe Avenue Complete Streets
Monroe Ave. at Russell Rd.
11
Install pedestrian countdown signals Upgrade crosswalks Install new crosswalk across Russell Rd.
N
Monroe Avenue Complete Streets
Monroe Ave. between Hancock Ave. & Russell Rd.
12
Add 10 parking spaces- narrow travel lanes Add cross walks across Hancock Add parking stripe along Monroe
N
Monroe Avenue Complete Streets
Section 2: Mt. Vernon Ave. to
Commonwealth Ave.
2 13
Monroe Avenue Complete Streets
16
Monroe Ave. at Commonwealth
- Ave. - Proposed
Add 10 parking spaces- narrow eastbound travel lane Add curb extension – Relocate 1 parking spaces, shorten crossing distance & align crosswalks Install pedestrian signals
N
Monroe Avenue Complete Streets
17
Monroe Ave. at Wayne St. and Newton St.
Add curb extension – relocate 1 parking space, shorten crossing distance & create ADA bus stop Install concrete bus pad for ADA bus stop Install new crosswalk Provide parking stripe and edge line Install crosswalks
- n side streets
Install shared bike lane symbols
N
Monroe Avenue Complete Streets
Section 1: Leslie Ave. to Mt.
Vernon Ave. - Pedestrian
1 18
Monroe Avenue Complete Streets
- Mt. Vernon Ave. at Monroe
- Ave. - Proposed
20
Upgrade crosswalks Install leading pedestrian interval for crossing north and south legs of Monroe Install “No Right Turn on Red” restrictions for EB and WB turns
N
Monroe Avenue Complete Streets
Monroe Ave. at Dewitt Ave.
21
Remove crosswalk Install sidewalk extension and crosswalk Install parking lane stripes Install crosswalks for side streets
N
Monroe Avenue Complete Streets
Proposed Crosswalks
22
N
Monroe Avenue Complete Streets
Section 1: Leslie Ave. to Mt.
Vernon Ave. – Bicycle Options
1 23
Monroe Avenue Complete Streets
Existing Conditions
24 No Parking Parking North side: 18 total spaces South side: 21 total spaces
Monroe Avenue Complete Streets
Option 1 – bike lanes between Leslie (2) and Mount Vernon
N
Monroe Avenue Complete Streets
Proposed Parking – Option 1
No Parking Existing Parking New Parking North side: 0 total spaces South side: 40 total spaces
Monroe Avenue Complete Streets
Option 2 – Eastbound bike lane to Leslie (2)
N
Monroe Avenue Complete Streets
Proposed Parking – Option 2
No Parking Existing Parking New Parking North side: 9 total spaces South side: 40 total spaces
Monroe Avenue Complete Streets
Thank You. Questions, Comments and Discussion
- Hillary.Poole@AlexandriaVA.gov
29
Monroe Avenue Complete Streets
Next Steps
- Traffic and Parking Board
- Curb and gutter work Spring/ Summer
2015
- Summer 2015 Implementation
30