SLIDE 1 Mills Avenue Area Main Replacement
An Overview
SLIDE 2
Overview of Main Replacement Program
SLIDE 3
SLIDE 4
SLIDE 5
SLIDE 6
SLIDE 7
Mills Avenue Specifics
What All This Means To You
SLIDE 8 Project Description
§ Existing lines are 2” galvanized, 6” and 8” cast
iron
§ Installed from 1933- 1964 § Project cost: $1,299,315.00 § Saluda Construction was awarded the contract. § Bill Williams, Owner § Greenville Water will oversee the project. § Scott Tackett, Designer/Inspector Supervisor § Paul Hendsbee, Designer/Inspector
7,615 linear feet of new 6, 8, 12-inch ductile iron water mains will be installed along Hawthorne Lane and Mills Avenue from Augusta Street to Henrydale Avenue between April 10 and December 30.
SLIDE 9 Construction Schedule
Hawthorne Lane April 10- June 30 Augusta Street- Mission Street May 1- June 9 Mission Street- Guess Street June 12- July 14 Lynn/ Guess Street- Reeves Street July 17- September 29 Reeves Street- Henrydale Avenue, portion of Marue Drive October 2- December 30 *subject to change due to weather or unknown underground conditions
Work will generally occur between the hours of 8:30am and 5pm, Monday through Friday. However, weekend or night work MAY be necessary.
SLIDE 10
Temporary Inconveniences
§ Access to all properties will be maintained but may be
difficult at times.
§ SCDOT is working with us to reduce inconveniences. § Noise, dirt and vibrations are normal.
Greenville Water has worked with the contractor to maximize our efficiency and limit inconveniences.
SLIDE 11
SLIDE 12
SLIDE 13
End of Phase 2
SLIDE 14
SLIDE 15
Henrydale Avenue
SLIDE 16
Safety
§ Please keep children away from machinery,
trenches and pits at all times.
§ Please follow the posted speed limits.
Greenville Water strives to maintain safe work sites for customer, employees and contractors.
SLIDE 17
Restoration
§ Restoration of street surfaces, landscaping
and grassed areas disturbed during construction will begin after installation of the pipe is complete.
§ The City of Greenville will begin a
beautification project in the Fall of 2018. Greenville Water will do our best to leave your neighborhood as we found it.
SLIDE 18
Project Website
§ www.greenvillewater.com/millsavenueproject § This site will have information on the
progress of the project.
§ You can: § join the email list to receive important
notifications for the duration of the project
§ Send messages or questions to the
project team
§ Complete satisfaction survey at the end of
the project This site is for you!
SLIDE 19
As a Result: Irrigation Meters
Installing a separate meter for use with an irrigation system or a pool could result in significant savings on your summertime bills. Call Engineering at 864-241-6100 to sign up or go to the website!
SLIDE 20 864-918-4648 dphendsbee@greenvillewater.com
Paul Hendsbee, Designer/Inspector
864-420-3110
- vassey@greenvillewater.com
Olivia Vassey, Communications Manager
Who do I contact with questions or concerns?
On Site Daily Project Contact
Department
Scott Tackett, Designer/Inspector Supervisor
864-241-6112 stackett@greenvillewater.com