Locally Preferred Alternative PRESENTATI O N Study Overview Existing Conditions A proposed Locally Preferred Alternative (The details) 2 slide PURPOSE STAT EMENT The purpose of the project is to implement multi-modal transportation
2
slide
PRESENTATI O N
Study Overview Existing Conditions A proposed Locally Preferred Alternative (The details)
3
slide
PURPOSE STAT EMENT
The purpose of the project is to implement multi-modal transportation improvements that enhance mobility and
safety along the Harmony Road Corridor.
Improvements will support local and
regional travel needs, land uses,
economic health and environmental
stewardship goals.
4
slide
Tier 1 Alternatives Tier 1 Screening Tier 2 Alternatives Broad Range of Ideas Fatal Flaw Analysis Most Promising
Vision Phasing Cost Triple Bottom Line
Tier 2 Screening Refinement Locally Preferred Alternative
Public Boards / Commissions City Council
5
slide
1950 1960 1970 1980 1990 2000 2010
Farm Road I-25 Built Becomes State Hwy Harmony Road transferred to City HP Builds Facility Harmony Corridor Plan Harmony Bicycle Plan 6-lanes to Boardwalk
Harmony Road History
H I S TO RY
Taft Hill Rd Shields St College Ave Lemay Ave Timberline Rd Ziegler Rd
Harmony Rd
$3,100,000 2012 $8,000,000 2009 $2,200,000 2010 $5,500,000 2011 $6,000,000 2008 $60,000 2010
7
slide Source: NFRMPO Travel Demand Model, as modified for Fort Collins Transportation Master Plan
8
slide Source: NFRMPO Travel Demand Model, as modified for Fort Collins Transportation Master Plan
9
slide
10
slide
11
slide
Rout ute e 1 about bout 300 0 on and offs fs Rout ute e 16 & 17 over 300 0 on and offs fs combine mbined
12
slide
Existing ting Bus St Stop
13
slide
Existing ting Bus St Stop
14
slide
Wa Walking king Co Cond nditio itions ns
15
slide
Walking Conditions on Harmony Road
16
slide
17
slide
18
slide
19
slide
20
slide
Proposed Locally Preferred Alternative Roadway & Intersection Improvements Transit Service Bicycle Facilities Pedestrian Facilities
21
slide
Alternative Roadway Infrastructure Transit Infrastructure
- n Harmony
Transit Service
- n Harmony
Bicycle and Pedestrian Accommodation
No Action Existing Existing
- Committed FY14 Transfort
service modifications Existing Transportation System Management (TSM)
- Widen Harmony
(Boardwalk to College) to 6 Lanes
- Intersection
improvements Existing
- Expanded Local Bus service
(Phase 1 of TSOP) FRCC to HTC Options:
- Bike lanes +
detached sidewalks
- Buffered bike lanes +
detached sidewalks
- Cycle tracks + detached
sidewalks
- Shared use paths
Enhanced Bus Same as TSM
- Queue jumps
at major intersections
- Enhanced bus service
(FRCC to HTC)
- Increased frequency
End to End BRT/HOV Same as TSM
- Outside lanes for
bus/HOV (one in each direction)
- BRT service (FRCC to HTC)
- Increased frequency
Interlined BRT/HOV Same as TSM
- Outside lanes for
bus/HOV (one in each direction)
- BRT service interlined with
Mason corridor
- Increased frequency
22
slide
Widen en Colle llege ge to 6 lanes es Widen en Timb mberline rline to 6 lanes es Impr prove
- ve interse
rsections ctions with h turn lane nes Widen en Harmony mony to 6 lanes es
23
slide
Harmony Rd. Timberline Lemay College Shields Ziegler Horsetooth Boardwalk Lady Moon
South uth Tran ansit sit Cent nter er Harmony rmony Transfe nsfer r Center ter
Harmony
- ny Rout
ute Runs every ry 20 minutes tes
24
slide
25
slide
26
slide
27
slide
Seatt attle le San Franci ncisco sco
28
slide
Harmony Rd. Timberline Lemay College Shields Ziegler Horsetooth Boardwalk Lady Moon
Pedestr strian ian and bicycle cycle Under or overpa pass sses es
Mason Trail Power Trail
29
slide
30
slide
Proposed Locally Preferred Alternative
Widen Harmony (Boardwalk to College) to 6 Lanes & Intersection improvements Enhanced bus service with queue jumps at major intersections, increased frequency with improved bus plazas Fill in missing sidewalks, pursue over or
underpasses and improve crossings at signalized
intersections
Buffered bike lanes with green marking, along with
detached multi-use paths
Bus Bike Walk Road
31
slide
Next Steps
Conduct final public outreach Develop conceptual cost estimates Develop implementation plan (phasing and funding) Complete ETC Master Plan report City Council this Summer for Adoption
32
slide
For More Information
Project Website: fcgov.com/harmony
Contact: Aaron Iverson aiverson@fcgov.com