Truckee River Flood Management Authority Locally Preferred Plan
Discussion of Project Elements Cost Estimate
Truckee River Flood Management Authority Locally Preferred Plan - - PowerPoint PPT Presentation
Truckee River Flood Management Authority Locally Preferred Plan Discussion of Project Elements Cost Estimate Chronology of Project Cost Development In December 2012 The USACE completed MCACES for the National Economic Development Plan
Discussion of Project Elements Cost Estimate
Feature Contingency % USACE 2012 NED HDR 2013 LPP USACE 2013 NED 01 Lands and Damages 39.1 39.1 31.3* 02 Relocations 37.9 37.9 27.12* 06 Fish & Wildlife 37.9 37.9 N/A 09 Channels & Canals 37.9 37.9 27 11 Levees & Flood Walls 37.9 37.9 27 14 Recreation 37.9 68.06 27 16 Bank Stabilization 37.9 38 27 18 Cultural Resources 33.5 33.5 23 30 Plan/Engineering/Design 11.2 11.2 27 31 Construction Management 37.9 37.9 27 *Weighted Avg.
spreadsheet shows 37.9%. That is a difference of $5.7M
Yellow Book. What is this line item?
Yellow Book. What is this line item?
it another way, could we apply for part of that $180M now?
downtown Reno?
contingency goal was 35%, but
37.9% was used for the 2013 LPP to maintain consistency with the USACE
updated the NED in 2013 to a Contingency of 27%
Feature Contingency % USACE 2012 NED HDR 2013 LPP USACE 2013 NED 01 Lands and Damages 39.1 39.1 31.3* 02 Relocations 37.9 37.9 27.12* 06 Fish & Wildlife 37.9 37.9 N/A 09 Channels & Canals 37.9 37.9 27 11 Levees & Flood Walls 37.9 37.9 27 14 Recreation 37.9 68.06 27 16 Bank Stabilization 37.9 38 27 18 Cultural Resources 33.5 33.5 23 30 Plan/Engineering/Design 11.2 11.2 27 31 Construction Management 37.9 37.9 27 *Weighted Avg.
Initial Tasks Baseline Surveys Draft Environmental Impact Statement Final Environmental Impact Statement Environmental Permitting Truckee Meadows Reach Phase 1 Pedestrian Bridge (Wells Avenue), Bank Stabilization, Non-voluntary Home Elevation
Phase 2 Lake Street Bridge Phase 3 Benching at and below Vista, Bank Stabilization Phase 4 McCarran to Purina (North & South), Existing NTD to end of Floodwall, Bank Stabilization Phase 5
Glendale to Rock, Habitat Facilities, Bank Stabilization
Phase 6
Rock to McCarran, Purina to Existing NTD, Bank Stabilization
Phase 7
Truckee Meadows Habitat Facilities2
Phase 8
Center Street Bridge, Truckee Meadows Recreation Facilities
Phase 9
Sierra Street Bridge
Phase 10
New Downtown Floodwalls, Booth Street Bridge, Pedestrian Bridges
Phase 11
Pump Stations, Existing Downtown Floodwall Replacement