Truckee Tahoe Airport Pavement Maintenance/ Management Plan 2014 Update Presentation to Truckee Tahoe Airport District December 3, 2014 R. R. Damon Brandley, P. Damon Brandley, P.E. E. Representing: Reinard W Representing: Reinard W.


  1. Truckee Tahoe Airport Pavement Maintenance/ Management Plan 2014 Update Presentation to Truckee Tahoe Airport District December 3, 2014 R. R. Damon Brandley, P. Damon Brandley, P.E. E. Representing: Reinard W Representing: Reinard W. Brandl Brandley, Consulti ey, Consulting Airpor ng Airport E t Engineer gineer 6125 Ki 6125 King Road, S ng Road, Suite 201 e 201 Loomi Loomis, Ca , Cali liforni fornia 95650 95650 (916) 652-4725 (916) 652-4725

  2. Truckee Tahoe Airport – – 2014 PMMP Update 2014 PMMP Update Truckee Tahoe Airport Goal: Update 2011 Pavement Maintenance and Management Plan with New Pavement Condition I ndex and Update the Rehabilitation Schedules. Required Elements of Study:  Surface Distress Survey - PCI (no FWD testing)  Update Rehabilitation Schedules  Maintenance Requirements  Schedule and Cost of Pavement Maintenance and Rehabilitation Data Collection:  Pavement Condition Survey – PCI  Update of Existing Pavement Sections  Recent Construction Projects Completed Reinard W . Brandley CONSULTI NG AI RPORT ENGI NEER

  3. Surface Distress – – 2013 Pavement Condition I ndex (PCI ) 2013 Pavement Condition I ndex (PCI ) Surface Distress

  4. Surface Distress – – 2011 Pavement Condition I ndex (PCI ) 2011 Pavement Condition I ndex (PCI ) Surface Distress

  5. Pavement Condition I ndex(PCI ) – – 2013 vs. 2011 2013 vs. 2011 Pavement Condition I ndex(PCI ) 2013 PCI 2011 PCI Reinard W . Brandley CONSULTI NG AI RPORT ENGI NEER

  6. Rehabilitation Plan – – Runway 11 Runway 11- -29 Complex 29 Complex Rehabilitation Plan Reinard W . Brandley CONSULTI NG AI RPORT ENGI NEER

  7. Maintenance and Rehabilitation Schedule – – 2014 2014- -2020 2020 Maintenance and Rehabilitation Schedule Reinard W . Brandley CONSULTI NG AI RPORT ENGI NEER

  8. Rehabilitation Schedule – – 2012 2012- -2015 2015 Rehabilitation Schedule

  9. Pavement Condition Survey & Rehabilitation Schedule Pavement Condition Survey & Rehabilitation Schedule Runway 11- -29 * Station 26+ 00 to Station 37+ 00 29 * Station 26+ 00 to Station 37+ 00 Runway 11 Reinard W . Brandley CONSULTI NG AI RPORT ENGI NEER

  10. Truckee Tahoe Airport – – 2014 PMMP Update 2014 PMMP Update Truckee Tahoe Airport Construction Cost Changes and Lessons Learned:  Existing Subgrades in Hangar Areas were found to be variable, soft, unstable, and required overexcavation and stabilization.  Hangar Taxilanes A-H need to be reconstructed instead of just removing and replacing the existing AC due to unstable subgrades.  Existing subgrade soils in Apron and Runway areas are much more difficult to excavate than originally anticipated due to the amount of cobbles present. Unit prices were increased for excavation in construction estimates to account for difficulty of excavation.  Added Reclaimite Seal Coat for some pavements to help surface condition of the pavement.  Updated all estimates to 2014 prices. Reinard W . Brandley CONSULTI NG AI RPORT ENGI NEER

  11. Truckee Tahoe Airport – – 2014 PMMP Update 2014 PMMP Update Truckee Tahoe Airport Summary of Major Project Changes: 2014 2011 PMMP 2014 PMMP Update Change in Cost Notable Element Recommended Reasons for Changes Change Rehabilitation Year Cost Year Cost ($) (%) Supplemental Added Resealing of Existing Joints Runway 11-29 (east) 2017 $105,000 2017 $155,000 $50,000 48% Cost Joints Added Remarking of Pavements Crack Repair and Deleted Fog Seal (Based on History/Experience) Runway 11-29 (east) 2020 $290,000 2022 $156,000 ($134,000) -46% Cost Seal Joints Additional Cracking and Rutting Taxiway A (east of E), Taxiway E removed from Project Reconstruction 2018 $1,900,000 2016 $2,000,000 $100,000 5% Date Taxiways F, H, U, & J Added 50% of T/W H Runup to Project Added Resealing of Existing Joints Supplemental Runway 2-20 and Added Reclaimite Seal Joints and 2016 $215,000 2015 $510,000 $295,000 137% Cost Taxiway G Complex Added Remarking of Pavements Reclaimte Seal Add Rock, Additional Surface Distresses Runway 2-20 and Pulverize, add 2031 $3,370,000 2022 $3,450,000 $80,000 2% Date Potential Increased Traffic Levels Taxiway G Complex 3" New AC Mill and Fill Anticipated to Extend Life Apron A1 Reconstruction 2020 $1,550,000 2023 $1,590,000 $40,000 3% Date Increased Excavation Prices Apron A2 Reconstruction 2025 $1,150,000 2025 $1,465,000 $315,000 27% Cost Added Reconstruction of Taxiway Connector to T/W A Mill and Fill Anticipated to Extend Life Increased Excavation Prices Cost Changed from Remove and Replace AC to Apron A3 Reconstruction 2017 $900,000 2021 $1,207,000 $307,000 34% and reconstruction. This is based upon the Date need to upgrade the strength of the apron to meet the latest approved aircraft fleet mix. Cracks Too Large and Too Many to Patch Cost Remove and Increased Excavation Prices South Jet Apron 2020 $550,000 2015 $845,000 $295,000 54% and Reconstruct Added Jetway Connector to Ramp to the Project Date Hangars A-H - Increased Excavation Prices Reconstruction 2020 $640,000 2019 $760,000 $120,000 19% Cost Taxilane R Changed From Replace AC to Reconstruction Hangars A-H - Remove and Increased Excavation Prices Rows West G and 2015 $338,000 2015 $867,000 $529,000 157% Cost Reconstruct Added Budget for Potential Soft, Unstable Subgrade GH Added Replacement of Slot Drain with Concrete Apron

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.