Feasibility Report Summary March 24 th , 2017 McCall, Idaho - - PowerPoint PPT Presentation

feasibility report summary march 24 th 2017
SMART_READER_LITE
LIVE PREVIEW

Feasibility Report Summary March 24 th , 2017 McCall, Idaho - - PowerPoint PPT Presentation

Feasibility Report Summary March 24 th , 2017 McCall, Idaho Project Schedule Recap November 18 th , 2016 Council Briefing/Workshop Dec. 19 th -23 rd , 2016 Informational Mailer Sent January 4 th , 2017 Open House with Property Owners Draft


slide-1
SLIDE 1

Feasibility Report Summary – March 24th, 2017

McCall, Idaho

slide-2
SLIDE 2

Project Schedule Recap

Council Briefing/Workshop November 18th, 2016 Informational Mailer Sent

  • Dec. 19th-23rd, 2016

Open House with Property Owners January 4th, 2017 Draft Feasibility Report Jan-March, 2017 Final Council Meeting March 24th, 2017

slide-3
SLIDE 3

Project Phasing Options

Originally Shown to Council and the Public

  • Option 1: Original Streets L.O.T. Schedule – 4 years of construction; 6 years to complete
  • Option 2: 3 years of construction; 5 years to complete
  • Option 3: 3-4 years of construction; 3-4 years to complete
slide-4
SLIDE 4

Construction Season Options

  • Option 1: All surface and subsurface improvements constructed April –

November

  • Option 2: Subsurface improvements constructed August – November

(Phase 1) and surface improvements constructed April-June (Phase 2)

slide-5
SLIDE 5

Open House Summary

Which Proj Project Ph Phasing o

  • ption
  • n d

do you

  • you pref

efer er? Answe swer O Opt ptions Res espons nse e Per ercent ent Res espons nse e Coun unt Option 1 – 4 years of construction 6 years to complete 0.0% Option 2 – 3 years of construction 5 years to complete 29.0% 9 Option 3 – 3 to 4 years of construction 4 years to complete 64.5% 20 No Preference 6.5% 2 answe wered q d quest stion 31 31 skip ipped q que uestio ion 1

  • Occurred January 4, 2017
  • 41 people signed in
  • 32 comment forms were collected
  • Two questions were asked
  • Preference for Project Phasing Option 3
  • Preference for Construction Season

Option 2

Which c con

  • nstru

ruction

  • n s

season

  • n w

wou

  • uld you

you pre refer? Answe swer O Opt ptions Res espons nse e Per ercent ent Res espons nse e Coun unt Option 1 - Construct all improvements April – November 21.9% 7 Option 2 - Construct subsurface utilities from Sept – Nov, with surface construction from April - June 71.9% 23 No Preference 6.2% 2 answe wered q d quest stion 32 32 skip ipped q que uestio ion

slide-6
SLIDE 6

Recommendation

It is recommended that the Downtown Core be reconstructed following:

  • Project Phasing Option 3a

(3-4 Years Construction)

  • Construction Season Option 2

(No work during peak Summer Season)

slide-7
SLIDE 7

Project Phasing Option 3a (Recommended)

  • Underground Franchise Utilities

in 2017, 2018 or 2019

  • 2nd Street & Lenora Street finish

in 2019

  • Park Street & Veteran’s Alley

finish in 2020

  • 3-4 years of construction 3-4

years to complete

  • 1st Street and Storm Water

Facilities when funding is available

slide-8
SLIDE 8

Design and Construction Schedule

Option 3 3A Recommende ded d Design n & & Construc uctio ion S Sche hedule ule

slide-9
SLIDE 9

Streets L.O.T. Funding Schedule

Based on Project Phasing Option 3a and Construction Season Option 2

*Carries over $1.1 million in Streets L.O.T. fund from 2016 Assumes $1 million from Streets L.O.T. per year after 2016

Year Road Name/Description Current Estimated Total Cost Current Estimated LOT Funds Required Estimated LOT Funds Accumulated Estimated LOT Funds Available after Improvements

2017

Commerce St

$651,000 $651,000 *$2,100,000 $1,449,000 2018

Idaho St/Brown Circle + 2nd St & Lenora Phase 1

$1,735,680 $1,316,046 $2,449,000 $1,132,954 2019

2nd St & Lenora Phase 2 + Park St & Veteran's Alley Phase 1

$4,004,860 $2,403,470 $2,132,954 ($270,516) 2020

Park St & Veteran's Alley Phase 2

$1,332,422 $1,211,562 $729,484 ($482,078) 2021

1st Street Phase 1

$346,016 $194,164 $517,922 $323,758 2022

1st Street Phase 2

$901,037 $844,702 $1,323,758 $479,056 2023

E Deinhard Ln

$1,349,270 $1,349,270 $1,479,056 $129,786 2024

Storm Water Facilities

$720,391 $720,391 $1,129,786 $409,395

slide-10
SLIDE 10

City Council Decisions

  • Approval of Project Phasing Option
  • Approval of Construction Season Option
  • Adding 1st St reconstruction and Veteran’s Alley to

improvements

  • Adding storm water management facilities to improvements
slide-11
SLIDE 11

Next Steps

  • Snow removal responsibility policies
  • Annual and long term infrastructure maintenance

responsibility policies

  • Execute the preliminary design and investigate more specific

design components

slide-12
SLIDE 12

Questions or Comments?